SCM 455 - Midterm Exam Question and answers already passed 2024/2025 SCM 455 - Midterm Exam
Projects - correct answer are a series of tasks with specific objectives, defined start and stop dates AND Limited resources, time, personnel, and budgets
Examples of Projects in Supply Management -...
SCM 455 - Midterm Exam
Projects - correct answer ✔are a series of tasks with specific objectives,
defined start and stop dates AND Limited resources, time, personnel, and
budgets
Examples of Projects in Supply Management - correct answer ✔-Developing
new products within / across organizations
-Supplier development / improvement
-New internal systems (e.g. information technology)
-Developing sourcing / category strategy
Dimensions of a Project - correct answer ✔-Defined Scope
-Defined Success
Plan... Analyze... Execute
Defined Scope - correct answer ✔-Project overview
-Agreed-upon tasks, responsibilities, deliverables
-Starting and ending points
Costs
Defined Success - correct answer ✔-Attainment of objectives (goals, time,
budget, etc)
-Stakeholder satisfaction (client, user, mgt, etc.)
-Minimal modifications or disruptions
,Work Breakdown Structure (WBS) - correct answer ✔Summation of activities
and resources required, Broken down into tasks, sub-tasks, responsibilities,
precedents, costs, Like a bill of material but for projects
Uses: Simplify understanding, estimation, & control, Basis for Gantt, PERT,
other tools
Project planning and control techniques - correct answer ✔-Gantt Charts
-Program evaluation and review technique (PERT)
-Critical Path method (CPM)
Rules for Constructing a CPM Network - correct answer ✔1. Identify each
unique activity
2. "Arc" is relationship, "node" is an activity
3. Connect arcs and nodes by precedence
4. Arcs show progression
5. Networks generally start and stop at single node
Early Start (ES) - correct answer ✔Earliest date task can begin
Early Finish (EF) - correct answer ✔Earliest date task can finish (ES + task
time)
Late Finish (LF) - correct answer ✔Latest date task can finish without
delaying entire project
Late Start (LS) - correct answer ✔Latest date a task can begin without
delaying entire project (LF - task time)
CPM Two Pass Method: Forward Pass - correct answer ✔-From start,
compute ES & EF dates only
-ES is last precedent task's EF
-Last task EF is the project's EF
The benefits of buying summaries with Stuvia:
Guaranteed quality through customer reviews
Stuvia customers have reviewed more than 700,000 summaries. This how you know that you are buying the best documents.
Quick and easy check-out
You can quickly pay through credit card or Stuvia-credit for the summaries. There is no membership needed.
Focus on what matters
Your fellow students write the study notes themselves, which is why the documents are always reliable and up-to-date. This ensures you quickly get to the core!
Frequently asked questions
What do I get when I buy this document?
You get a PDF, available immediately after your purchase. The purchased document is accessible anytime, anywhere and indefinitely through your profile.
Satisfaction guarantee: how does it work?
Our satisfaction guarantee ensures that you always find a study document that suits you well. You fill out a form, and our customer service team takes care of the rest.
Who am I buying these notes from?
Stuvia is a marketplace, so you are not buying this document from us, but from seller flyhigher329. Stuvia facilitates payment to the seller.
Will I be stuck with a subscription?
No, you only buy these notes for $13.99. You're not tied to anything after your purchase.