OMIS 635 Test 2 questions with correct answers

Preview 3 out of 30  pages

  • September 30, 2024
  • 30
  • 2024/2025
  • Exam (elaborations)
  • Questions & answers
  • OMIS
  • OMIS
avatar-seller
BravelRadon
OMIS 635 Test 2
What is resource smoothing (or leveling)? - correct answer ✔✔Involves attempting to even out varying
demands
on resources by using slack (delaying noncritical activities) to manage resource utilization when
resources are adequate over the life of the project



What is resource-constrained scheduling? - correct answer ✔✔The duration of a project may be
increased by delaying the late start of some of its activities if resources are not adequate to meet peak
demands



What are technical or logic constraints? - correct answer ✔✔Constraints related to the networked
sequence in which project activities must occur



What are physical constraints? - correct answer ✔✔Activities that cannot occur in parallel or are affected
by contractual or environmental conditions



What are resource constraints? - correct answer ✔✔The absence, shortage, or unique interrelationship
and interaction characteristics of resources that require a particular sequencing of project activities

People, materials, equipment



What are the types of project constraints? - correct answer ✔✔-Technical or logic

-Physical

-Resource



How do you determine the classification of a problem? - correct answer ✔✔Using a priority matrix will
help determine if the project is time or resource constrained.



What is a time-constrained project? - correct answer ✔✔-Must be completed by an imposed date

,-Require use of leveling techniques that focus
on balancing or smoothing resource demands.



-Use positive slack (delaying noncritical activities) to manage resource utilization over the duration
of the project.



-Time is fixed, resources are flexible: additional resources are required to ensure project meets
schedule.



What is resource-constrained project? - correct answer ✔✔-Is one in which the level of resources
available cannot be exceeded.

-Resources are fixed, time is flexible: inadequate resources
will delay the project.



What are limiting assumptions? - correct answer ✔✔-Splitting activities is not allowed—once an activity
is start, it is carried to completion



-Level of resources used for an activity cannot be changed



What are risk assumptions? - correct answer ✔✔-Activities with the most slack pose the least risk.



-Reduction of flexibility does not increase risk.



-The nature of an activity (easy, complex) doesn't increase risk



What are the advantages of resource demand leveling techniques for time-constrained projects? -
correct answer ✔✔-Peak resource demands are reduced



-Resources over the life of the project are reduced



-Fluctuation in resource demand is minimized.

, What are the disadvantages of resource demand leveling techniques for time-constrained projects? -
correct answer ✔✔-Loss of flexibility that occurs from reducing slack



-Increases in the criticality of all activities



What are the order of heuristics
(rules-of-thumb)? - correct answer ✔✔1) Minimum slack



2) Smallest (least) duration



3) Lowest activity identification number



What is an EMR project? - correct answer ✔✔The development of a handheld electronic medical
reference guide to be used by emergency medical technicians and paramedics



What is the problem with EMR projects? - correct answer ✔✔There are only eight design engineers who
can be assigned to the project due to a shortage of design engineers and commitments to other projects.



What are the impacts of resource-constrained scheduling? - correct answer ✔✔-Reduces slack; reduces
flexibility

-Increases criticality of events

-Increases scheduling complexity

-May make the traditional critical path no longer meaningful

-Can break sequence of events

-May cause parallel activities to become sequential

-Activities with slack may become critical



What is splitting? - correct answer ✔✔-A scheduling technique for creating a better project schedule
and/or increase resource utilization

The benefits of buying summaries with Stuvia:

Guaranteed quality through customer reviews

Guaranteed quality through customer reviews

Stuvia customers have reviewed more than 700,000 summaries. This how you know that you are buying the best documents.

Quick and easy check-out

Quick and easy check-out

You can quickly pay through credit card or Stuvia-credit for the summaries. There is no membership needed.

Focus on what matters

Focus on what matters

Your fellow students write the study notes themselves, which is why the documents are always reliable and up-to-date. This ensures you quickly get to the core!

Frequently asked questions

What do I get when I buy this document?

You get a PDF, available immediately after your purchase. The purchased document is accessible anytime, anywhere and indefinitely through your profile.

Satisfaction guarantee: how does it work?

Our satisfaction guarantee ensures that you always find a study document that suits you well. You fill out a form, and our customer service team takes care of the rest.

Who am I buying these notes from?

Stuvia is a marketplace, so you are not buying this document from us, but from seller BravelRadon. Stuvia facilitates payment to the seller.

Will I be stuck with a subscription?

No, you only buy these notes for $19.99. You're not tied to anything after your purchase.

Can Stuvia be trusted?

4.6 stars on Google & Trustpilot (+1000 reviews)

78310 documents were sold in the last 30 days

Founded in 2010, the go-to place to buy study notes for 14 years now

Start selling
$19.99
  • (0)
  Add to cart