MSP (2024) Questions & Answers Already Passed What is the purpose of the Programme Communication Plan? - Answers:It sets out the timetable for managing stakeholder engagement What are the Assurance Management Principles? - Answers:Integrated - this is $7.99   Add to cart

Exam (elaborations)

MSP (2024) Questions & Answers Already Passed What is the purpose of the Programme Communication Plan? - Answers:It sets out the timetable for managing stakeholder engagement What are the Assurance Management Principles? - Answers:Integrated - this is

 0 view  0 purchase
  • Course
  • CGFM - Certified Government Financial Manager
  • Institution
  • CGFM - Certified Government Financial Manager

MSP (2024) Questions & Answers Already Passed What is the purpose of the Programme Communication Plan? - Answers:It sets out the timetable for managing stakeholder engagement What are the Assurance Management Principles? - Answers:Integrated - this is about how assurance reviews should be s...

[Show more]

Preview 2 out of 5  pages

  • October 1, 2024
  • 5
  • 2024/2025
  • Exam (elaborations)
  • Questions & answers
  • CGFM - Certified Government Financial Manager
  • CGFM - Certified Government Financial Manager
avatar-seller
Denyss
MSP (2024) Questions & Answers
Already Passed
What is the purpose of the Programme Communication Plan? - Answers:It sets out the
timetable for managing stakeholder engagement

What are the Assurance Management Principles? - Answers:Integrated - this is about
how assurance reviews should be scheduled to support decision-making, from the start
of the programme to the realization of the benefits.

• Linked to major decision points - for example, reviews at the end of a tranche.

• Risk-based - for example assurance activities should be focused on the areas of
greatest risk

• Action and intervention - assurance is most effective when follow-up actions are taken
to resolve serious issues identified through the planned assurance activity. These
actions, in turn, may be the subject of further reviews.

What is the relationship between a Programme Mandate and a Programme Brief? -
Answers:The programme mandate is confirmend and then expanded into a Programme
brief.

What is a Vision Led Programme? - Answers:Comes into existence to deliver a clearly
defined vision.

Sponsoring Group Responsibilities - Answers:Specific responsibilities include the
following:
• Establishing the organizational context for the programme.
• Authorise the programme mandate and the progression into Defining a Programme.
• Authorize funding.
• Resolve strategic and directional issues between programmes.
• Confirming the organization's strategic direction.
• They participate in 'end-of-tranche' reviews and approve the progress of the
programme against the strategic objectives.
• Leading by example.
• As well as providing continued commitment and endorsement to the programme at
communication events, they should:
• Support the senior responsible owner.
• Act as the programme's 'champion',
• Confirm successful delivery and signoff of the programme at closure.

, Who produces the Benefits Management Strategy? - Answers:The Programme
Manager

What is the reason for the process " Realizing the Benefits"? - Answers:It ensures that
project outputs are suitable for operational use

What is a key area of programme focus when monitoring the progress of the projects? -
Answers:Avoidance of scope creep

What is scope creep? - Answers:Refers to how a project's requirements tend to
increase over a project lifecycle, e.g. what once started out as a single deliverable
becomes five. Or a product that began with three essential features, now must have ten.

What are the critical validation tests for a benefit? - Answers:It is known as the DOAM
test.

Description - What precisely is the benefit?
• Observable outcomes - What difference will be noticeable between before and after
the programme implementation?
• Attribution - is, for example, the accountability and responsibility for
delivering the change clear and agreed?
• Measurement - How and when will achievement of the benefit be measured?

Responsibilities of Business Change Managers - Answers:Maintaining a focus on
realizing beneficial change.
• Ensuring benefit profiles and a benefits realization plan are developed and business
responsibility for them is established.
• Providing evidence and notification of expected benefits delivery.
• Contributing to design the future operating model, or the 'to be' state and ensuring this
is contained and maintained in the programme blueprint.
• Defining metrics for monitoring to enable assessment of the organization's operational
'health'.
• Ensuring business stability is maintained during the transition.
• Reporting to the SRO on the readiness of change, achievement of outcomes and
realization of benefits. • Advising the programme manager regarding whether the
programme and each project will deliver the outputs and outcomes that will lead to
benefits.
• Identifying, defining and tracking of programme benefits and outcomes.
• Managing the realization of benefits. • Implementing benefit realization and
measurement mechanisms.
• Preparation of key business areas for transition.
• Initiation of business assurance reviews.

What is Proximity in MSP? - Answers:how quickly the risk is likely to materialize

What are the 9 Governance Themes? - Answers:1. Programme Organization

The benefits of buying summaries with Stuvia:

Guaranteed quality through customer reviews

Guaranteed quality through customer reviews

Stuvia customers have reviewed more than 700,000 summaries. This how you know that you are buying the best documents.

Quick and easy check-out

Quick and easy check-out

You can quickly pay through credit card or Stuvia-credit for the summaries. There is no membership needed.

Focus on what matters

Focus on what matters

Your fellow students write the study notes themselves, which is why the documents are always reliable and up-to-date. This ensures you quickly get to the core!

Frequently asked questions

What do I get when I buy this document?

You get a PDF, available immediately after your purchase. The purchased document is accessible anytime, anywhere and indefinitely through your profile.

Satisfaction guarantee: how does it work?

Our satisfaction guarantee ensures that you always find a study document that suits you well. You fill out a form, and our customer service team takes care of the rest.

Who am I buying these notes from?

Stuvia is a marketplace, so you are not buying this document from us, but from seller Denyss. Stuvia facilitates payment to the seller.

Will I be stuck with a subscription?

No, you only buy these notes for $7.99. You're not tied to anything after your purchase.

Can Stuvia be trusted?

4.6 stars on Google & Trustpilot (+1000 reviews)

81311 documents were sold in the last 30 days

Founded in 2010, the go-to place to buy study notes for 14 years now

Start selling
$7.99
  • (0)
  Add to cart