100% satisfaction guarantee Immediately available after payment Both online and in PDF No strings attached
logo-home
HUT CAPM Test Questions & Answers 2024/2025 $8.49   Add to cart

Exam (elaborations)

HUT CAPM Test Questions & Answers 2024/2025

 2 views  0 purchase
  • Course
  • HUT CAPM
  • Institution
  • HUT CAPM

HUT CAPM Test Questions & Answers 2024/2025 As defined in PMBOK, there are three baselines in total. They are time, scope, and cost. Which of the following is true about them? - ANSWERSTime and cost can be computer generated whereas scope can not In your organization you have a team of SMEs...

[Show more]

Preview 2 out of 7  pages

  • October 8, 2024
  • 7
  • 2024/2025
  • Exam (elaborations)
  • Questions & answers
  • HUT CAPM
  • HUT CAPM
avatar-seller
Bensuda
HUT CAPM Test Questions & Answers
2024/2025

As defined in PMBOK, there are three baselines in total. They are time, scope, and cost. Which of the
following is true about them? - ANSWERSTime and cost can be computer generated whereas scope can
not



In your organization you have a team of SMEs from whom you have asked opinions on certain areas of
your project. This was done anonymously with all the SMEs so that opinion of one person does not
influence another. What kind of tools and techniques are you following? - ANSWERSDelphi Technique



You joined a project as a manager during the later stage of the project. During the final testing a number
of defects were found and you have decided to prioritize the defects and fix depending on the schedule.
Which tool should you use? - ANSWERSPareto Chart - Pareto chart is based on frequency it priories the
most common causes. Run Chart is used for trend analysis and gives a snapshot at a point of time.
Control Chart is used to determine whether a process is in control or not. Flow chart is used to predict
where a quality problem might happen. Hence, Choice -D is the best choice.



Work has been broken down to the activity level in the project WBS. Who should make the estimation of
these activities? - ANSWERSTeam members doing the work - these members are most knowledgeable
about the work that needs to be done



In which process and in which knowledge area is the initial cost management plan developed? -
ANSWERSDevelop Project Management Plan in Integration Management



The main difference between GANTT chart and Precedence Diagramming Method (PDM) is: -
ANSWERSGANTT Chart can show loops and branches where as PDM can not



Which chart reports on the trends and variances of the quality problems that have occurred over a
period of time? - ANSWERSRun chart

, How is a project coordinator different than a project expeditor? - ANSWERSA project coordinator has
some authority to make decisions whereas the project expeditor does not (this is not usually on the test
but shows up sometimes)



You have been promoted to the rank of PM. However, you have very little knowledge in PM and
experience about the project. Which of the following should be your best source of information for
management of the project? - ANSWERSHistorical records from your organization



A project management plan is all but: - ANSWERSApproved by all the stakeholders of the projects - A
project management plan need not be approved all the stakeholders. There are direct and indirect
stakeholders in a project and approval from all of them is not required. A project management plan is a
formal document which is distributed among stakeholder inline with the communication management
plan and it is used for the execution of the project. Hence, Choice-A is the most appropriate answer.



Perform Integrated Change Control process falls under which process group? - ANSWERSMonitoring and
Controlling Process Group



Gerry is a certified CAPM professional and is a member of PMO in his organization. The PMO selects the
project that will be initiated and executed by the organization. Gerry can use any of the following
techniques to initiate a project EXCEPT: - ANSWERSEarned Value Management - this is only used when
the project is getting executed



Larry has been assigned as a project manager in a high-end consulting project during the integration
phase. He has been poured with a number of change requests and is having difficulty on prioritizing
them. You are one of the colleagues of Larry and wanted to help him. What should you advise Larry
about project integration? - ANSWERSA project manager should spend his time in problem-solving and
decision making between project subsystems



John is a project manager for a newly formed project team. The project team has worked hard for last 4
months and has taken very few leaves. John wants to motivate the team members by informing them
that he can give a couple of paid leaves if they complete the Phase-1 deliverables on time. Which theory
is applied by John to achieve the result? - ANSWERSExpectancy Theory



Accepted Deliverables is an output of which process? - ANSWERSValidate Scope

The benefits of buying summaries with Stuvia:

Guaranteed quality through customer reviews

Guaranteed quality through customer reviews

Stuvia customers have reviewed more than 700,000 summaries. This how you know that you are buying the best documents.

Quick and easy check-out

Quick and easy check-out

You can quickly pay through credit card or Stuvia-credit for the summaries. There is no membership needed.

Focus on what matters

Focus on what matters

Your fellow students write the study notes themselves, which is why the documents are always reliable and up-to-date. This ensures you quickly get to the core!

Frequently asked questions

What do I get when I buy this document?

You get a PDF, available immediately after your purchase. The purchased document is accessible anytime, anywhere and indefinitely through your profile.

Satisfaction guarantee: how does it work?

Our satisfaction guarantee ensures that you always find a study document that suits you well. You fill out a form, and our customer service team takes care of the rest.

Who am I buying these notes from?

Stuvia is a marketplace, so you are not buying this document from us, but from seller Bensuda. Stuvia facilitates payment to the seller.

Will I be stuck with a subscription?

No, you only buy these notes for $8.49. You're not tied to anything after your purchase.

Can Stuvia be trusted?

4.6 stars on Google & Trustpilot (+1000 reviews)

83249 documents were sold in the last 30 days

Founded in 2010, the go-to place to buy study notes for 14 years now

Start selling
$8.49
  • (0)
  Add to cart