100% satisfaction guarantee Immediately available after payment Both online and in PDF No strings attached
logo-home
CSLB CONCRETE C8 LICENSE FINAL EXAM, PRACTICE EXAM AND STUDY GUIDE NEWEST 2024 ACTUAL EXAM COMPLETE 100 QUESTIONS AND CORRECT DETAILED ANSWERS (VERIFIED ANSWERS) |ALREADY GRADED A+||BRAND NEW!! $29.49   Add to cart

Exam (elaborations)

CSLB CONCRETE C8 LICENSE FINAL EXAM, PRACTICE EXAM AND STUDY GUIDE NEWEST 2024 ACTUAL EXAM COMPLETE 100 QUESTIONS AND CORRECT DETAILED ANSWERS (VERIFIED ANSWERS) |ALREADY GRADED A+||BRAND NEW!!

 13 views  0 purchase
  • Course
  • CSLB CONCRETE C8 LICENSE
  • Institution
  • CSLB CONCRETE C8 LICENSE

CSLB CONCRETE C8 LICENSE FINAL EXAM, PRACTICE EXAM AND STUDY GUIDE NEWEST 2024 ACTUAL EXAM COMPLETE 100 QUESTIONS AND CORRECT DETAILED ANSWERS (VERIFIED ANSWERS) |ALREADY GRADED A+||BRAND NEW!!

Preview 4 out of 83  pages

  • October 9, 2024
  • 83
  • 2024/2025
  • Exam (elaborations)
  • Questions & answers
  • cslb concrete c8
  • CSLB CONCRETE C8 LICENSE
  • CSLB CONCRETE C8 LICENSE
avatar-seller
johnkabiru
1|Page



CSLB CONCRETE C8 LICENSE FINAL EXAM,
PRACTICE EXAM AND STUDY GUIDE NEWEST
2024 ACTUAL EXAM COMPLETE 100
QUESTIONS AND CORRECT DETAILED
ANSWERS (VERIFIED ANSWERS) |ALREADY
GRADED A+||BRAND NEW!!




CSLB CONCRETE C8 LICENSE FINAL EXAM
What is the most common size or thickness of polyethylene
sheet used as a moisture barrier (with/without sand layer) in the
concrete industry? - ANSWER- 4 to 6 mil


Which of the following fastening mechanisms holds the collar
strongly fixed around the finished columns? - ANSWER-
Friction


If you want to place a crushed stone layer over the vapor barrier,
which of the following thicknesses of polyethylene is it
recommended to use? - ANSWER- 50 mil

,2|Page


Which of the following are the types of footings commonly used
in the concrete construction industry? - ANSWER- ALL


-Pad footing, Strap footing, Combined footing


-Spread footing, Isolated footing, Strip footing


-Mat footing, Continuous footing, Raft footing


What is the minimum slope-away recommended in the final
grading of foundation backfilling after the placement of
concrete? - ANSWER- ¼" per foot pitch


Which of the following options is not related to concrete pouring
preparation? - ANSWER- Legal site inspector should be
available on site


Which of the following concrete pouring strategies works well
for a long normal slab? - ANSWER- Start from farther area of
slab


Which of the following pieces of equipment are commonly used
for manual excavation for small buildings? - ANSWER-
Crowbar , pickaxe, shovel

,3|Page




Explanation:
The answer is crowbar, pickaxe, and shovel because of the
key phrase "small buildings" in the question.


Which of the following activities is performed to measure the
quality of compaction a building foundation? - ANSWER- Proof
Rolling


How many methods of construction dewatering are commonly
used in concrete building projects? - ANSWER- 3


Explanation:
There are three dewatering methods as given below:
Well points
Sumps and ditches
Relief wells


Which of the following are the results of a concrete slump test
carried out during the placing of concrete on site? - ANSWER-
Zero, True, Shear , collapsed

, 4|Page


What is the unit of concrete quantity take-off? - ANSWER-
Cubic feet


Which of the following concrete pouring strategies is commonly
adopted while filling stair steps? - ANSWER- From bottom to
top


How much water needs to be added to the concrete to increase
the slump value of a cubic yard of concrete by one unit? -
ANSWER- One gallon


Which of the following factors increases the drying shrinkage as
well as creeping in concrete structures ? - ANSWER- Low
Temperature & Low Relative Humidity


Which of the following are three major types of concrete project
cost estimates that are commonly used in the project planning? -
ANSWER- Preliminary Estimate, Detailed Estimate, Engineer's
Estimate


Explanation:
Preliminary estimate is general conceptual estimate based
on the conceptual design of a project.

The benefits of buying summaries with Stuvia:

Guaranteed quality through customer reviews

Guaranteed quality through customer reviews

Stuvia customers have reviewed more than 700,000 summaries. This how you know that you are buying the best documents.

Quick and easy check-out

Quick and easy check-out

You can quickly pay through credit card or Stuvia-credit for the summaries. There is no membership needed.

Focus on what matters

Focus on what matters

Your fellow students write the study notes themselves, which is why the documents are always reliable and up-to-date. This ensures you quickly get to the core!

Frequently asked questions

What do I get when I buy this document?

You get a PDF, available immediately after your purchase. The purchased document is accessible anytime, anywhere and indefinitely through your profile.

Satisfaction guarantee: how does it work?

Our satisfaction guarantee ensures that you always find a study document that suits you well. You fill out a form, and our customer service team takes care of the rest.

Who am I buying these notes from?

Stuvia is a marketplace, so you are not buying this document from us, but from seller johnkabiru. Stuvia facilitates payment to the seller.

Will I be stuck with a subscription?

No, you only buy these notes for $29.49. You're not tied to anything after your purchase.

Can Stuvia be trusted?

4.6 stars on Google & Trustpilot (+1000 reviews)

81113 documents were sold in the last 30 days

Founded in 2010, the go-to place to buy study notes for 14 years now

Start selling
$29.49
  • (0)
  Add to cart