CHST 3 Practice Questions and Answers Minimum air capacity for employees working underground is ? cubic feet per minute of fresh air is required for each employee. - Answer-200 The OSHA provisions in 1926.800 provide the basis for worksite safety requirements of underground workers employed in ...

[Show more]

Preview 2 out of 15  pages

  • October 16, 2024
  • 15
  • 2024/2025
  • Exam (elaborations)
  • Questions & answers
  • 2024/2025
  • 2024/2025
avatar-seller
Emillect
EMILLECT 2024/2025 ACADEMIC YEAR ©2024 EMILLECT. ALL RIGHTS RESERVED FIRST PUBLISH OCTOBER, 2024




CHST 3 Practice Questions and Answers

Minimum air capacity for employees working underground is ? cubic feet per minute of fresh air

is required for each employee. - Answer✔✔-200


The OSHA provisions in 1926.800 provide the basis for worksite safety requirements of

underground workers employed in the excavation of underground cavities, tunnels, shafts or

chambers. Four specific provisions of those requirements include: - Answer✔✔-Air flow

direction should be reversible. If blasting is to be conducted in an underground tunnel or cavity,

workers cannot return to work until the ventilation system has cleared the area of all exhaust

and fumes. Ventilation doors must be designed to remain closed when in use regardless of the

direction of air flow. Ventilation doors are designed to provide a barrier to dangerous fumes

should they build up in adjacent areas. If the ventilation system has been shut down for any

purpose, testing must be done by a competent person to determine whether the area is safe for

reoccupation by workers.


The velocity of air must be regulated to flow at least ? per minute in underground areas where

conditions are likely to create dust, fumes, or gas vapors. - Answer✔✔-30 ft per min


When ? or more employees are working underground, contingency must be made for two

rescue teams. One team must be located within a ? traveling distance; the other must be within

a ? travel time period. - Answer✔✔-25/half hour/two hour



Page 1/15

, EMILLECT 2024/2025 ACADEMIC YEAR ©2024 EMILLECT. ALL RIGHTS RESERVED FIRST PUBLISH OCTOBER, 2024


If less than ? persons are working underground, contingency plans may involve a single rescue

crew which must be positioned within ? travel time from the job site. - Answer✔✔-25/half hour


When a trenching system is to be dug to a depth of ? or more, a professional engineer is

required to design a safe, strong, and reliable method of shoring up the excavation. The -

Answer✔✔-20ft


The maximum slope of an excavation into Type A soil is ? degrees. - Answer✔✔-53


Gravel and silt are Type B materials. The maximum height to depth ratio for trenching in Type B

soil is ? yielding a maximum ?degree angle. - Answer✔✔-1:1/45 degrees


Type C is sand, which is very unstable for trenching. The slope angle for a trench into Type C soil

can be no more than ? degrees. - Answer✔✔-34


The only material in which vertical trench walls are allowed is - Answer✔✔-Solid rock


? inspections of excavation sites are required as a minimum but inspections can be made at any

time a change in work, weather, or environmental conditions makes more frequent inspections

desirable. - Answer✔✔-Daily


Means of exit or egress should be inspected. Stairways, ladders, ramps or other safe means of

evacuation from trenches are required in ditches or trenches that are ? feet or more in depth. A

worker should not have to travel more than ? feet to reach a means of safe exit. - Answer✔✔-

4/25


WBGT = ? - Answer✔✔-WBGT = 0.7NWB + 0.2GT + 0.1DB


Page 2/15

The benefits of buying summaries with Stuvia:

Guaranteed quality through customer reviews

Guaranteed quality through customer reviews

Stuvia customers have reviewed more than 700,000 summaries. This how you know that you are buying the best documents.

Quick and easy check-out

Quick and easy check-out

You can quickly pay through credit card or Stuvia-credit for the summaries. There is no membership needed.

Focus on what matters

Focus on what matters

Your fellow students write the study notes themselves, which is why the documents are always reliable and up-to-date. This ensures you quickly get to the core!

Frequently asked questions

What do I get when I buy this document?

You get a PDF, available immediately after your purchase. The purchased document is accessible anytime, anywhere and indefinitely through your profile.

Satisfaction guarantee: how does it work?

Our satisfaction guarantee ensures that you always find a study document that suits you well. You fill out a form, and our customer service team takes care of the rest.

Who am I buying these notes from?

Stuvia is a marketplace, so you are not buying this document from us, but from seller Emillect. Stuvia facilitates payment to the seller.

Will I be stuck with a subscription?

No, you only buy these notes for $9.99. You're not tied to anything after your purchase.

Can Stuvia be trusted?

4.6 stars on Google & Trustpilot (+1000 reviews)

79373 documents were sold in the last 30 days

Founded in 2010, the go-to place to buy study notes for 14 years now

Start selling
$9.99
  • (0)
  Add to cart