SWM plan must be approved by ___ before land disturbance -
Answer-VSMP program authority
The water quality criteria sets a site-based load limit of ____ of
total phosphorus for new development - Answer-0.41
lbs/acre/year
The phosphorus load limit uses the - Answer-10% impervious
cover
Part II B and II C water quantity criteria addresses - Answer-
channel protection and flood protection
Which two plans in the SWPPP must be approved? - Answer-
SWM plan, ESC plan
Does the SWM plan address runoff during or after
construction? - Answer-post-construction
,What is the lower limit of the range of imperviousness that can
result in stream degradation? - Answer-10%
What do land disturbing activities consist of? - Answer-
excavating, clearing, grading
LDA threshold for the SWM Act and Regulation - Answer-1 acre
or 2500 square feet for Chesapeake Bay Preservation Act
In situations where an initial exemption was applicable because
LDAs were related to emergency work, VSMP authority shall be
advised of the disturbance within - Answer-7 days of
commencing the LDA and shall submit a permit application
within 30 days of starting the land-disturbing activity
Localities with MS4 - Answer-must adopt and administer a
stormwater program
Localities without MS4 - Answer-may choose to administer a
VSMP or have DEQ administer the program
, DEQ is responsible for enforcing the ____ while locality ____
are responsible for enforcing local ordinances - Answer-
Construction GP, VSMP
A locality VSMP authority must include enforcement authority
and a schedule of civil penalties for enforcement actions in its
local ordinance. The maximum penalty the authority may issue
is - Answer-$32,500 per violation per day
Any civil penalty assessed by a court as a result of a summons
issued by a locality VSMP authority must be paid - Answer-into
the locality's treasury
Any person who violates..... shall be subject to a civil penalty
not to exceed - Answer-$32, 500
The Virginia Stormwater Management Program is authorized by
the ______ and administered through the ______ - Answer-
Virginia Stormwater Management Act, Virginia Stormwater
Management Program Regulation
VPDES Permit/Construction GP authorizes discharge of
stormwater from construction activities that are - Answer-
greater than or equal to an acre
The benefits of buying summaries with Stuvia:
Guaranteed quality through customer reviews
Stuvia customers have reviewed more than 700,000 summaries. This how you know that you are buying the best documents.
Quick and easy check-out
You can quickly pay through credit card or Stuvia-credit for the summaries. There is no membership needed.
Focus on what matters
Your fellow students write the study notes themselves, which is why the documents are always reliable and up-to-date. This ensures you quickly get to the core!
Frequently asked questions
What do I get when I buy this document?
You get a PDF, available immediately after your purchase. The purchased document is accessible anytime, anywhere and indefinitely through your profile.
Satisfaction guarantee: how does it work?
Our satisfaction guarantee ensures that you always find a study document that suits you well. You fill out a form, and our customer service team takes care of the rest.
Who am I buying these notes from?
Stuvia is a marketplace, so you are not buying this document from us, but from seller Rnseller. Stuvia facilitates payment to the seller.
Will I be stuck with a subscription?
No, you only buy these notes for $18.49. You're not tied to anything after your purchase.