100% satisfaction guarantee Immediately available after payment Both online and in PDF No strings attached
logo-home
Asphalt Paving Gc Exam Questions With Solutions $10.99   Add to cart

Exam (elaborations)

Asphalt Paving Gc Exam Questions With Solutions

 3 views  0 purchase
  • Course
  • FDOT ASPHALT PAVING LEVEL 2
  • Institution
  • FDOT ASPHALT PAVING LEVEL 2

Asphalt Paving Gc Exam Questions With Solutions

Preview 2 out of 14  pages

  • November 5, 2024
  • 14
  • 2024/2025
  • Exam (elaborations)
  • Questions & answers
  • base course
  • bridge
  • FDOT ASPHALT PAVING LEVEL 2
  • FDOT ASPHALT PAVING LEVEL 2
avatar-seller
Divinehub
Asphalt Paving Gc Exam Questions
With Solutions
Base Course - ANSWER- Layer or layers of specified material of designated thickness
or rate of application based on a subbase or subgrade to support the subsequent layers

Bridge - ANSWER- Over a depression; longer than 20'

The subgrade is the top _______ of roadbed upon which the pavement structure and
shoulders are constructed - ANSWER- 18"

Do not use glass in the top _____ of the embankment - ANSWER- 18"

Clear and grub minimum of ____ from each edge of proposed pavement along both
lanes and legs of interchange - ANSWER- 30'

Where clearing and grubbing within the roadway is indicated at a bridge site, clear by
cutting all trees, stumps, etc. to within ______ of the ground or to low water in the full
width of the ROW for a distance of 75' beyond the beginning and end of the proposed
bridge - ANSWER- 8"

Compact the subgrade between the lines ____ inches outside the area occupied by the
pavement structure, including C&G & SW to not less than 95% of max density -
ANSWER- 18"

Pulverize base course material so that the completion of the moist mixing 100% (by dry
weight) passes the 1.5" sieve and a minimum of _____ passes the #4 sieve, exclusive
of gravel and stone retained on the sieve - ANSWER- 80%

#4 sieve - ANSWER- 4.75 mm

Ensure finished surface of base varies neither than 3/8" from a straight edge 10' long
when applied parallel to the CL of the rd, no more than ______ inch from the typical
cross-section on the plans - ANSWER- 1/2"

Thickness of completed modified base is measured at staggered intervals not to exceed
_____ feet in length for two-lane roads - ANSWER- 250'

Use _______ in all base courses as an anti-stripping additive - ANSWER- hydrated lime

Where plans required uniform thickness of base course and the contract provides for
pavement on sq yd bases, thickness of base course is determined from measurements

Page | 1

, taken of the completed base course at intervals not exceeding _____ feet for two-lane
roads - ANSWER- 500'

For HMA, use aggregates with a combined specific gravity of _____ or less - ANSWER-
2.90

ON HMA use pneumo-rollers that are self propelled and have an effective rolling width
of not less than _______ - ANSWER- 60"

Ensure intermediate rolling of HMA is completed before mat temp drops below _____ -
ANSWER- 175 degrees

First step in applying asphalt surface treatment (single) - ANSWER- Clean surface

Last step in applying asphalt surface treatment (single) - ANSWER- Remove excess
aggregate

Spread aggregate for HMA within _____ feet of the application of the emulsion -
ANSWER- 200'

Place asphalt surface treatment (double) within ____ days of the base course being
primed - ANSWER- 7

When rolling aggregate applications for asphalt surface treatment (double) on each trip
of the roller, overlap prior by _____ the width of the roller - ANSWER- 1/2

On portland cement pavement, position lower surface of preformed joint filler on or
below surface of base while upper surface is _____ inches below surface of the slab -
ANSWER- 1/2"

When using surface vibrators on portland concrete, ensure frequency is not less than
______ impulses per minute - ANSWER- 3500

Construct subbase and base beneath concrete pavement to include area _____ inches
in width extending beyond edges to provide stability for paver tracks - ANSWER- 18"

Min. width of any reinforced concrete slab is ______ feet - ANSWER- 16'

Max. length of any reinforced concrete slab is ______ feet - ANSWER- 20'

Exclude all vehicle traffic from newly constructed concrete pavement for a period of not
less than ______ days - ANSWER- 14

Finish joints should not deviate more than ____ inch in the horizontal alignment from a
straight line - ANSWER- 1/4"


Page | 2

The benefits of buying summaries with Stuvia:

Guaranteed quality through customer reviews

Guaranteed quality through customer reviews

Stuvia customers have reviewed more than 700,000 summaries. This how you know that you are buying the best documents.

Quick and easy check-out

Quick and easy check-out

You can quickly pay through credit card or Stuvia-credit for the summaries. There is no membership needed.

Focus on what matters

Focus on what matters

Your fellow students write the study notes themselves, which is why the documents are always reliable and up-to-date. This ensures you quickly get to the core!

Frequently asked questions

What do I get when I buy this document?

You get a PDF, available immediately after your purchase. The purchased document is accessible anytime, anywhere and indefinitely through your profile.

Satisfaction guarantee: how does it work?

Our satisfaction guarantee ensures that you always find a study document that suits you well. You fill out a form, and our customer service team takes care of the rest.

Who am I buying these notes from?

Stuvia is a marketplace, so you are not buying this document from us, but from seller Divinehub. Stuvia facilitates payment to the seller.

Will I be stuck with a subscription?

No, you only buy these notes for $10.99. You're not tied to anything after your purchase.

Can Stuvia be trusted?

4.6 stars on Google & Trustpilot (+1000 reviews)

76799 documents were sold in the last 30 days

Founded in 2010, the go-to place to buy study notes for 14 years now

Start selling
$10.99
  • (0)
  Add to cart