Miller Act - ANSWER Current federal law requires that federal projects over
100k must have both a performance and a payment bond. Provided legal
distinction between construction & Design
Delivery system, Type of Procurement and Type of Contract Format. -
ANSWER Three basic decisions an Owner must make to begin a viable project
are :
Design Bid Build (Low Bid) - ANSWER What is the most common project
delivery system?
The Owner - ANSWER In traditional DBB delivery, who does the architect
sign their contract with?
None - ANSWER What type of relationship does the contractor have with an
architect in Design Bid Build?
Scheduling Restraints or needs to be fast-tracked - ANSWER Why would you
choose a Design Build delivery System?
Design Build - ANSWER If the owner wants to shift risk to one party, what
project delivery method would they choose?
Design Build - ANSWER What type of project delivery best suits a complex
project requiring close coordination of design and construction expertise?
, 1 - Joint Venture
2 - Integrated DB Firm
3- A/E Led
4 - Contractor Led - ANSWER What are some forms of Design Build entities?
Yes - ANSWER Does the Owner bear risk in a design-bid-build?
1 - Linear project delivery
2 - Well defined and familiar relationships
3 - Benefit of Open Market Competition
4 - Owner is actively involved in design until documents are 100% complete -
ANSWER What are some reasons owners choose DBB?
Limiting Factors to Design Build - ANSWER 1 - Owner wants absolute design
control
2 - The programming limits flexibility and innovation
3 - The Owner cannot provide programming and performance requirements.
Contractor Led - ANSWER The most common DB entity structural
arrangement?
1 - Contractor
2 - Architect - ANSWER What contracts does the owner holds in a CM @
Risk delivery method.
Qualifications and Best Price - ANSWER How architect/engineering firms are
typically selected?
The benefits of buying summaries with Stuvia:
Guaranteed quality through customer reviews
Stuvia customers have reviewed more than 700,000 summaries. This how you know that you are buying the best documents.
Quick and easy check-out
You can quickly pay through credit card or Stuvia-credit for the summaries. There is no membership needed.
Focus on what matters
Your fellow students write the study notes themselves, which is why the documents are always reliable and up-to-date. This ensures you quickly get to the core!
Frequently asked questions
What do I get when I buy this document?
You get a PDF, available immediately after your purchase. The purchased document is accessible anytime, anywhere and indefinitely through your profile.
Satisfaction guarantee: how does it work?
Our satisfaction guarantee ensures that you always find a study document that suits you well. You fill out a form, and our customer service team takes care of the rest.
Who am I buying these notes from?
Stuvia is a marketplace, so you are not buying this document from us, but from seller luzlinkuz. Stuvia facilitates payment to the seller.
Will I be stuck with a subscription?
No, you only buy these notes for $10.49. You're not tied to anything after your purchase.