NABCEP PV Installation Professional Exam Questions
And 100% Correct Answers
NABCEP
North American Board of Certified Energy Practioners
JTA
Job Task Analysis
The JTA details what is expected of a qualified PV installation professional.
Conduit Fill
(i.e. Maximum Percent of Conduit Area Available for Conductors)
NEC Chapter 9 Table 1
Voltage Drop Limits
ASHRAE 90.1 Standards suggests no more than 3% of nominal voltage.
NEC suggests no more than 5% in an "Informational Note".
Sunpower standard is no more than 1%.
Voltage Drop Equation
% drop =(0.2 x D x I x R )/V
Where:
D= one-way distance (in feet)
,I = current (nominal actual value, no 125% factors, use Imp for solar circuits)
R = resistance of conductors (in ohms/1000ft)
V = voltage (typical, nominal, use Vmp for solar circuits)
Resistance values are provided in the NEC Chapter 9 Table 8 "Conductor Properties"
What size FMC conduit would be needed for four size 6 AWG XHHW conductors, one
size 8 AWG XHHW EGC and four 10 AWG THHN conductors? Use only the NEC code
book to answer this question.
1-1/4"
Chapter 9 Tables 4 and 5.
BIPV
Building-Integrated Photovoltaics
Can single phase inverters be connected to 3-phase power systems?
Yes, provided significant unbalanced voltages cannot result
705.100
What is the minimum busbar rating for a subpanel used as an inverter ac combiner
panel to combine three 4000W, 240V single phase inverters?
125A
Rating of each breaker = 16.7 X 1.25 = 25A
Sum of inverter breakers = 3 x 25A = 75A
, Minimum size of back-fed breaker in main service panel = 3 x 16.7A x 1.25 = 62.2 --> 70A
Minimum size busbars in subpanel x 1.2 = inverter breakers + utility breaker = 75A + 70A
Is it acceptable to connect an inverter output to a subpanel instead of the main
distribution panel?
Yes - see 705.12(D).
However, be aware that each panel in series needs to meet the minimum busbar size
requirements.
Grounded conductor
A current carrying conductor that is intentionally bonded to ground. It is the neutral
conductor in any AC system.
Equipment grounding conductor (EGC)
The green or bare copper conductor linking exposed non-current-carrying metal parts
of module frames, equipment and enclosures
Grounding electrode conductor (GEC)
The bare copper conductor connecting the system grounding bus to a ground rod or to
the earth.
The benefits of buying summaries with Stuvia:
Guaranteed quality through customer reviews
Stuvia customers have reviewed more than 700,000 summaries. This how you know that you are buying the best documents.
Quick and easy check-out
You can quickly pay through credit card or Stuvia-credit for the summaries. There is no membership needed.
Focus on what matters
Your fellow students write the study notes themselves, which is why the documents are always reliable and up-to-date. This ensures you quickly get to the core!
Frequently asked questions
What do I get when I buy this document?
You get a PDF, available immediately after your purchase. The purchased document is accessible anytime, anywhere and indefinitely through your profile.
Satisfaction guarantee: how does it work?
Our satisfaction guarantee ensures that you always find a study document that suits you well. You fill out a form, and our customer service team takes care of the rest.
Who am I buying these notes from?
Stuvia is a marketplace, so you are not buying this document from us, but from seller Easton. Stuvia facilitates payment to the seller.
Will I be stuck with a subscription?
No, you only buy these notes for $13.99. You're not tied to anything after your purchase.