100% satisfaction guarantee Immediately available after payment Both online and in PDF No strings attached
logo-home
Project Time Management with complete verified solutions already graded A+ $14.49   Add to cart

Exam (elaborations)

Project Time Management with complete verified solutions already graded A+

 0 view  0 purchase
  • Course
  • Time management
  • Institution
  • Time Management

Project Time Management with complete verified solutions already graded A+

Preview 2 out of 8  pages

  • November 15, 2024
  • 8
  • 2024/2025
  • Exam (elaborations)
  • Questions & answers
  • Time management
  • Time management
avatar-seller
GUARANTEEDSUCCESS
Project Time Management with
complete verified solutions
already graded A+
Project Time Management - answer describes the processes and
methods required to create and manage appropriate schedules to
complete the project.
involves the processes required to ensure timely completion of a
project.


Project Time Management processes - answer 1. plan schedule
management:involves determining the policies, procedures, and
documentation that will be used for planning, executing, and
controlling the project schedule
2. define activities:identifies the lowest level of work on the WBS,
"work packages", that needs to be performed to create the finished
product deliverable.
3. sequence activities:identifying and documenting the relationships
between project activities.
4. estimate activity resources:estimating how many resources
(people, equipment, materials) a project team should use to
perform project activities.
5. estimate activity durations:estimating the number of work
periods that are needed to complete individual activities.
6. develop schedule:analyzing activity sequences, activity resource
estimates, and activity duration estimates to create the project
schedule.
7. control schedule:involves controlling and managing changes to
the project schedule


1. Planning Schedule Management - answer involves controlling and
managing changes to the

, Information Technology Department project schedule
A schedule management plan includes:
*Project schedule model development:contains project activities
with estimated durations, dependencies, and other planning
information that can be used to produce a project schedule.
*Level of accuracy and units of measure :discusses how accurate
schedule estimates should be and determines whether time is
measured in hours, days, or another unit
*Control thresholds(the maximum amount of time in which an action
or process may take place):Variance thresholds, such as ±10%, are
established for monitoring schedule performance.
*Rules of performance measurement :For example, if team members
are expected to track the percentage of work completed, this
section specifies how to determine the percentages.
*Reporting formats:describes the format and frequency of schedule
reports required for the project.
*Process descriptions:describes how all of the schedule
management processes will be performed.


2. Defining Activities - answer *An activity or task is an element of
work normally found on the work breakdown structure (WBS) that
has an expected duration, cost, and resource requirements.
*Activity definition involves developing a more detailed WBS and
supporting explanations to understand all the work to be done so
you can develop realistic cost and duration estimates.
*The goal of defining activities is to ensure that the project team
completely understands all the work it must do as part of the
project scope so they can start scheduling the work.
What are needed to define the activities (inputs) Schedule
management plan
Scope baseline
Enterprise environmental factors
(Include relevant government or industry standards, the
organization's infrastructure, and marketplace conditions)

The benefits of buying summaries with Stuvia:

Guaranteed quality through customer reviews

Guaranteed quality through customer reviews

Stuvia customers have reviewed more than 700,000 summaries. This how you know that you are buying the best documents.

Quick and easy check-out

Quick and easy check-out

You can quickly pay through credit card or Stuvia-credit for the summaries. There is no membership needed.

Focus on what matters

Focus on what matters

Your fellow students write the study notes themselves, which is why the documents are always reliable and up-to-date. This ensures you quickly get to the core!

Frequently asked questions

What do I get when I buy this document?

You get a PDF, available immediately after your purchase. The purchased document is accessible anytime, anywhere and indefinitely through your profile.

Satisfaction guarantee: how does it work?

Our satisfaction guarantee ensures that you always find a study document that suits you well. You fill out a form, and our customer service team takes care of the rest.

Who am I buying these notes from?

Stuvia is a marketplace, so you are not buying this document from us, but from seller GUARANTEEDSUCCESS. Stuvia facilitates payment to the seller.

Will I be stuck with a subscription?

No, you only buy these notes for $14.49. You're not tied to anything after your purchase.

Can Stuvia be trusted?

4.6 stars on Google & Trustpilot (+1000 reviews)

79223 documents were sold in the last 30 days

Founded in 2010, the go-to place to buy study notes for 14 years now

Start selling
$14.49
  • (0)
  Add to cart