100% satisfaction guarantee Immediately available after payment Both online and in PDF No strings attached
logo-home
PMBOK Chapter 6 5th edition - Practice Test 4 (A+) 100% Verified $12.99   Add to cart

Exam (elaborations)

PMBOK Chapter 6 5th edition - Practice Test 4 (A+) 100% Verified

 2 views  0 purchase
  • Course
  • PMBOK Chapter 6 5th edition
  • Institution
  • PMBOK Chapter 6 5th Edition

PMBOK Chapter 6 5th edition - Practice Test 4 (A+) 100% Verified...

Preview 3 out of 26  pages

  • November 20, 2024
  • 26
  • 2024/2025
  • Exam (elaborations)
  • Questions & answers
  • PMBOK Chapter 6 5th edition
  • PMBOK Chapter 6 5th edition
avatar-seller
Easton
PMBOK Chapter 6 5th edition - Practice Test 4 (A+) 100% Verified



All of the following are inputs to the Estimate Activity Resources process EXCEPT:



A Resource breakdown structure.

B Activity attributes.

C Organizational process assets.

D Activity list. - ANSWER Choices B, C and D are all inputs. Resource breakdown
structure (Choice A) is the correct answer because it is not an input. It is an output of
the Estimate Activity Resources process. PMBOK® 6.4.1, pgs 162-163



Schedule baseline or other elements of the project management plan are updated using
approved change requests that have previously been passed through the __________.



A Management chain

B Perform Quality Assurance process

C Control Schedule process

D Perform Integrated Change Control process - ANSWER This question pertains to how
project documents - including the schedule baseline, or other elements of the project
management plan are updated. Change requests are an output of the Control Schedule
process, and are processed for review and disposition through the Perform Integrated
Change Control process. PMBOK® 6.7.3.3, pg 191



Approved change requests that affect the project schedule will result in an update of the
approved project schedule. This updated, re-approved and re-issued schedule now
becomes:



A A reason for delaying the schedule.

B A deviation from the schedule baseline.

,C The new project schedule baseline.

D Requested changes. - ANSWER If approved change requests have an impact on the
project schedule, then the approved project schedule is updated and re-issued to
reflect the approved changes. The revised project schedule becomes the new schedule
baseline (Choice C) for future changes and is part of the project management plan.
PMBOK® 6.7.1.1, pg 187



You and your project management team are leading a two-day workshop to brainstorm
and finalize the project schedule. Which of the following information will NOT assist you
in developing the project schedule?



A Project scope statement

B Schedule baseline

C Activity list

D Resource calendars - ANSWER Choices A, C and D are inputs, and inputs are what
you need to develop the project schedule. Schedule baseline (Choice B) is an output of
the Develop Schedule process, and therefore the correct answer. PMBOK® 6, pg 143



The latest version of the __________ is an input to the Control Schedule process.



A Project schedule

B Scope baseline

C Project documents

D Gantt chart - ANSWER The current project schedule (Choice A) updated to show
status, completed activities, and activities that have started as of the date of the data is
an input to Control Schedule. PMBOK® 6.7.1.2, pg 187



What method of sequencing technique employs boxes to show activities?



A Flow chart diagram method

B Data flow diagramming

, C Activity-On-Node technique

D Work breakdown structure - ANSWER The precedence diagramming method is a
technique used for constructing a schedule model in which activities are represented by
nodes and are graphically linked by one or more logical relationships to show the
sequence in which the activities are to be performed. Activity-on-node (Choice C) is one
method of representing a precedence diagram. PMBOK® 6.3.2.1, pg 156



You are the project manager for this project. Click the View Figure button to see the
diagram. Your stakeholders ask you to see what options are possible to reduce the
duration of the project by 2 days. After an analysis your BEST recommendation would
be to:

A. Add more resources to Task E.

B. Remove Task G

C. Begin Task J after Task G is completed.

D Start Task C upon completion of Task A. - ANSWER Reducing the duration of a
non-critical path will not reduce the duration of the project; thus, Choices A, B and C
cannot be correct answers. In this instance your BEST recommendation to your
stakeholders is Choice D even though it only reduces the duration by a single day. The
stakeholders requested OPTIONS to decrease duration by 2 days and you will have to
inform them that the best you can do is one day. PMBOK® 6.3.2 pgs 156-158 and 6.6.2.2,
pgs 176-177



Decomposition is a technique used during Define Activities. It subdivides the project
work packages into smaller, more manageable components called schedule __________.
- ANSWER The technique of decomposition, as it is applied to defining activities,
involves subdividing the project work packages into smaller, more manageable
components called activities. PMBOK®, 6.2.2.1, pg 151



Project team members are uncertain about how long it will really take to complete an
activity. Deb, who is an optimist, believes it might take 5 days. Dean, the pessimist,
thinks it could take up to 10 days. What is the BEST way to express this activity's
duration?



A 7 days

B At least 5 days, but not more than 10 days

The benefits of buying summaries with Stuvia:

Guaranteed quality through customer reviews

Guaranteed quality through customer reviews

Stuvia customers have reviewed more than 700,000 summaries. This how you know that you are buying the best documents.

Quick and easy check-out

Quick and easy check-out

You can quickly pay through credit card or Stuvia-credit for the summaries. There is no membership needed.

Focus on what matters

Focus on what matters

Your fellow students write the study notes themselves, which is why the documents are always reliable and up-to-date. This ensures you quickly get to the core!

Frequently asked questions

What do I get when I buy this document?

You get a PDF, available immediately after your purchase. The purchased document is accessible anytime, anywhere and indefinitely through your profile.

Satisfaction guarantee: how does it work?

Our satisfaction guarantee ensures that you always find a study document that suits you well. You fill out a form, and our customer service team takes care of the rest.

Who am I buying these notes from?

Stuvia is a marketplace, so you are not buying this document from us, but from seller Easton. Stuvia facilitates payment to the seller.

Will I be stuck with a subscription?

No, you only buy these notes for $12.99. You're not tied to anything after your purchase.

Can Stuvia be trusted?

4.6 stars on Google & Trustpilot (+1000 reviews)

64438 documents were sold in the last 30 days

Founded in 2010, the go-to place to buy study notes for 14 years now

Start selling
$12.99
  • (0)
  Add to cart