Training Questions and answers correct The Materials Coordinator certification requirement is implemented through: *Regulatory Requirment 23 CFR 637 Standard Spec 106.1 contractors designates a CPMC The Project Material Coordinators are required to meet: WEEKLY The PMCs are respons...

[Show more]

Preview 2 out of 6  pages

  • January 16, 2025
  • 6
  • 2024/2025
  • Exam (elaborations)
  • Questions & answers
  • CMPC
  • CMPC
avatar-seller
Pogba119
Training Questions and answers correct
The Materials Coordinator certification requirement is implemented through: - answer
*Regulatory Requirment 23 CFR 637 Standard Spec 106.1 contractors designates a
CPMC

The Project Material Coordinators are required to meet: - answer WEEKLY

The PMCs are responsible to inform the project engineer of materials issues: - answer
as soon as possible

Compiling certifications records from the subcontractors is the responsibility of the: -
answer CPMC MOD 2. pg 8

What information must be included in a "Certified Report of Test or Analysis" that is not
required in a "Certification Complacence" ? - answer -Test results and sampling
reference number MOD 3 pg 22 notes

To determine material documentation requirements, the Project Material Coordinators
must first: - answer Identify the materials being used MOD 3 pg. 27

Which of the following documents is not sufficient as a primary basis for project material
acceptance? - answer Test Data Worksheets MOD 3. CMM 8-45 3.1

Select the four testing areas of the WisDOT Concrete Materials Laboratory Unit: -
answer -Soil Lab, Aggregate Lab, Steel and Geo textile, Concrete Lab

Identify by selecting three "primary" elements of the quality management programs -
answer Personal Certifications Department of QV Contractor Quality Control

Independent Assurance is performed - answer As an unbiased review of testing
personnel, procedures, and equipment MOD 5. pg 12

Random numbers determining production QC sample locations must be: - answer
Determined in accordance with AASHTO T. 3665

Select three primary software programs used for WisDot materials electronic reporting: -
answer Materials Information (MIT) The Materials Tracking System (MITS) Materials
Reporting System (MRS) MOD. 5 pg 18

Nonconformance of Materials pertains to: - answer Physical materials being supplied
to the job MOD 7 pg 4

, Select three common examples resulting in nonperformance of QMP: - answer -Non
random Tests -Calculation Errors -Use of non qualified laboratory MOD 7 pg. 7

The purpose of the E-guide is to: - answer -Provide project specific details

The "Buy America" provision requires that for federal-aid funded contracts: - answer
Steel products incorporated into the project

Project Materials coordinators tasks are intended to: - answer Improve efficiency of
project close out activities MOD 1 pg 6

Materials sampling and testing "documentation" on WISDOT projects is: - answer A
federal regulatory requirement MOD 3 8-20

The CMPC is designed by the: - answer The contractor per standard spec 106.1

The WPMC is designated by the: - answer WisDOT or the department

The Project Materials Coordinators are required to be "certified" through: - answer
HTCP

One of the responsibilities of the PMC's is to: - answer Sample and test materials

Who is responsible for preparing the E-Guide? - answer WPMC mod 2. pg 10

All acceptable certifications documents should be dated within how many years of the
contract date? - answer 2 years

Each WISDOT project will have: - answer one WPMC

A primary goal of the project material coordinators is to - answer Ensure the
materials concerns are address and timely corrective MOD 2. pg. 6

Select three places to find materials " documentations requirements" - answer 8-45,
8-50 standard specification

Materials to be used in a project are identified by reviewing: - answer -E-Guide

The departments central office is NOT the primary testing facility for: - answer HMA
production samples

To be considered as supporting information for the engineer's approval, on-site
materials must be: - answer Sampled and tested by certified personnel

When published, Additional special Provisions (ASPs): - answer Affect all contracts
forward from asp publishing date

The benefits of buying summaries with Stuvia:

Guaranteed quality through customer reviews

Guaranteed quality through customer reviews

Stuvia customers have reviewed more than 700,000 summaries. This how you know that you are buying the best documents.

Quick and easy check-out

Quick and easy check-out

You can quickly pay through credit card or Stuvia-credit for the summaries. There is no membership needed.

Focus on what matters

Focus on what matters

Your fellow students write the study notes themselves, which is why the documents are always reliable and up-to-date. This ensures you quickly get to the core!

Frequently asked questions

What do I get when I buy this document?

You get a PDF, available immediately after your purchase. The purchased document is accessible anytime, anywhere and indefinitely through your profile.

Satisfaction guarantee: how does it work?

Our satisfaction guarantee ensures that you always find a study document that suits you well. You fill out a form, and our customer service team takes care of the rest.

Who am I buying these notes from?

Stuvia is a marketplace, so you are not buying this document from us, but from seller Pogba119. Stuvia facilitates payment to the seller.

Will I be stuck with a subscription?

No, you only buy these notes for $12.99. You're not tied to anything after your purchase.

Can Stuvia be trusted?

4.6 stars on Google & Trustpilot (+1000 reviews)

70089 documents were sold in the last 30 days

Founded in 2010, the go-to place to buy study notes for 15 years now

Start selling
$12.99
  • (0)
Add to cart
Added