100% satisfaction guarantee Immediately available after payment Both online and in PDF No strings attached 4.2 TrustPilot
logo-home
Exam (elaborations)

ACI TEST QUESTIONS & ANSWERS

Rating
-
Sold
-
Pages
6
Grade
A+
Uploaded on
22-02-2025
Written in
2024/2025

ACI TEST QUESTIONS & ANSWERS

Institution
ACI
Course
ACI









Whoops! We can’t load your doc right now. Try again or contact support.

Written for

Institution
ACI
Course
ACI

Document information

Uploaded on
February 22, 2025
Number of pages
6
Written in
2024/2025
Type
Exam (elaborations)
Contains
Questions & answers

Subjects

Content preview

ACI TEST QUESTIONS & ANSWERS
The total time allowed between obtaining the first and final portions of a composite
sample is - Answers - 15 minutes

When it is necessary to wet sieve the concrete sample, wet sieving should be
performed after the individual samples are remixed into a composite sample (T or F) -
Answers - F

Tests for slump, temperature, and air content must begin within ______ minutes after
obtaining the composite sample - Answers - 5 minutes

Begin molding test specimens within ______ minutes after obtaining the composite
sample - Answers - 15 minutes

The concrete samples should be protected from - Answers - the sun, wind, and other
sources of rapid evaporation, from contamination

When test specimens are to be molded, the minimum size of sample obtained is -
Answers - 28 L (1 ft^3)

The primary objective of the sampling process is to obtain a representative sample (T or
F) - Answers - T

When sampling from a revolving drum truck mixer collect concrete from ______ portions
of the batch - Answers - 2 or more


Submerge the sensing portion of the thermometer at least ______ inches into the
concrete - Answers - 3

Gently press concrete around the thermometer such that the_______ does not
affect the reading. - Answers - ambient air temp

The thermometer must remain in the concrete during the measurement for a minimum
of ______ minutes. In addition, the temperature measurement must be completed within
_______ minutes after obtaining the sample. - Answers - 2, 5

The temperature of freshly mixed concrete is measured and recorded to the nearest
_____ - Answers - 1 degree

SLUMP TEST - Answers -

****The slump test does not provide an indication of the water content of a concrete
mixture. - Answers - F

, A slump mold can be fabricated from both plastic and metal. - Answers - T

****The length of the tamping for the slump test shall be approximately - Answers -

The slump test is applicable to concrete having a coarse aggregate up to _______ inch
in size. - Answers - 1.5 inches

The height of the slump cone is - Answers - 12 in

6. The exterior of the slump cone is tapped 10 to 15 times after rodding each layer. -
Answers - F

The slump mold is filled with three layers of concrete - Answers - by volume

8. If the top surface of the concrete falls below the top of the slump cone while rodding
the final layer of concrete, - Answers - stop, add concrete to maintain an excess, then
continue the rod count from
where you left off.

Raise the mold vertically a distance of 12 inches - Answers - in5±2seconds

The slump of a mixture is found by - Answers - measuring the vertical distance to the
displaced original center on the top
surface of the slumped concrete.

AIR CONTENT BY PRESSURE METHOD - Answers -

It is allowable to use the Air Content by Pressure Method test to measure the air content
of fresh concrete made with - Answers - dense aggregates only

Assuming an appropriately sized coarse aggregate, it is not allowable to use the bowl of
the pressure meter to determine the density of the concrete per ASTM C138. - Answers
-F

When the coarse aggregate of a concrete mixture can be retained on a 2in. sieve, wet
sieve a sufficient amount of material for the air content test (ASTM C 231) over a
______ sieve - Answers - 1.5 in

Proper consolidation of concrete in the bowl of the pressure meter is accomplished by -
Answers - either rodding or vibration depending on the slump of the concrete

Strike off the top surface of the concrete by using - Answers - either strike off bar or
plate

The length of the tamping rod for the air pressure test shall not be less than - Answers -
16 in

Get to know the seller

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
GEEKA YALA UNIVERSITY
View profile
Follow You need to be logged in order to follow users or courses
Sold
1997
Member since
3 year
Number of followers
1444
Documents
46559
Last sold
1 day ago

3.8

341 reviews

5
169
4
61
3
44
2
16
1
51

Recently viewed by you

Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Frequently asked questions