What types of projects establish prevailing wage rates? correct answers Federally Funded
Projects
Which of the following documents are submitted by the Contractor at Bid opening? correct
answers Proposal Form, Bid Breakdown, Addendum, Bid Bond & Non-collusive Affidavit
Which document establishes the forms, content, and procedures for submitting the bid proposals?
correct answers Instruction to Bidders
Which of the following documents is normally incorporated by reference? correct answers
General Conditions
What is the name of the law principle for referring the Contractor to other documents that are not
contained in the package provided? correct answers Incorporated by Reference
Which document establishes the labor rates on a project? correct answers Prevailing Wage Rate
Schedule
Which document contains a description of the alternate(s)? correct answers General Requiremnts
Which document specifies the existing soil conditions? correct answers Information Available to
Bidders
Which document applies to the Contractor and the Subcontractors and describes the
administrative, procedural and temporary procedures on the job site? correct answers General
Requirements
Which document specifies the temporary facilities needed on a project? correct answers General
Requirements
Which document is submitted by each bidder stating that their bid was arrived at without any
conferring with other prime bidders? correct answers Non-Collusive Affidavit
Which document is submitted to the Owner for bid consideration before the Contractor can
receive the bidding documents? correct answers Pre-qualification Forms
Which document describes the quality of work and the quality of the materials and the
construction execution procedures? correct answers Technical Specifications
Which document describes the business procedures for a specific project and they change the
initial procedures? correct answers Supplementary Conditions
Which document specifies the Regulations required such as soil erosion or minorities? correct
answers General Requirements
,Which document requests that additional information be submitted by the bidder within 48 hours
of bid opening? correct answers Proposal Supplements
Which document issued by the Architect illustrates what is to be built? correct answers Plans
Which document makes changes, modifications and corrections prior to bid openings? correct
answers Addenda
Which documents describe the duties and responsibilities of each party and the business
procedures for administering the contract? correct answers General Conditions
What is the term called which requires all Bidders to include in their bid a specified amount or
unit price for a particular item? correct answers Cash Allowance
Which of the following systems is utilized for supporting an existing structure when the new
excavation will be below the existing structures foundation while the extension to the existing
foundation is being placed? correct answers Underpinning
What is the lifting system called which consists of two vertical towers with a cross beam on top
with the intended purpose of lifting an unusually long piece of equipment which was transported
horizontally and it is lifted into its permanent vertical position? correct answers Jin Pole
What is the concrete pouring method called that is used to pour concrete under water? correct
answers Tremie
In construction, what is the proper terminology for transporting the off-road equipment to the job
site? correct answers Mobilization
Assume you are lifting an item onto the roof. The Height of the exterior wall is 27 Feet above the
ground and the horizontal distance from the centerline of the rotation is 40 feet. What is the
minimum length of the boom required? correct answers 70 Feet
Which of the following temporary systems is utilized to support freshly placed concrete which is
poured on the ground as a slab and lifted up to its final horizontal elevation using hydraulic
jacks? correct answers Lift slab form system
Which piece of equipment is most efficient for compacting granular soils such as sand, gravel,
and crushed stone? correct answers Smooth-Wheel Roller
What is the primary cause for a masonry wall to collapse while under construction? correct
answers Lack of masonry wall bracing and a change in wind conditions
Assume you are lifting an item onto the bridge deck. The Deck is 27 feet above the ground and
the horizontal distance from the centerline of the rotation is 40 feet. What is the minimum boom
angle? correct answers 57
, What is the working range of a Clam Shell? correct answers 40-54 degrees
Which piece of equipment and attachment would be the most efficient method to excavate inside
a cofferdam? correct answers Crane with a Clamshell attachment
Which party is normally responsible for designing the temporary structures? correct answers
Contractor
What is another name for Sheeting? correct answers Uprights
What does "close sheeting" mean in relationship to a shoring system? correct answers The
spacing between timber planks is not to exceed 1/2 inch.
What are the components of a cofferdam or a support system? correct answers Sheeting, Wales,
and Cross Braces
Which piece of equipment sets below the excavation and the bucket pushes up? correct answers
Power Shovel
Which piece of equipment has its boom above the structure and it lifts the load vertically until it
is above the structure, then it can move the load horizontally? correct answers Tower Crane
What is the working range of a lift crane? correct answers 55-80 degrees
According to the OSHA Construction Safety Standards, what is required for shoring systems
more than 20 feet deep? correct answers The Registered Professional Engineer shall design the
protection system
Which piece of equipment is used to excavate ponds or soil under water? correct answers
Dragline
What is the working range of a Dragline? correct answers 25-39 degrees
Assume you are lifting an item onto the bridge deck. The deck is 37 feet above the ground and
the horizontal distance from the centerline of the rotation is 70 feet. What is the minimum length
of the boom required? correct answers 120 Feet
Which party is normally responsible for estimating and pricing the temporary structures? correct
answers Contractor
Assume you are lifting an item onto the bridge deck. The deck is 37 feet above the ground and
the horizontal distance from the centerline of the rotation is 70 feet. What is the minimum boom
angle? correct answers 57 degrees