PROJECT MA 586 (PROJECT MA 586)
Devry University
All 2 results
Sort by
-
Week 3 Homework: AIB Problems questions with correct answers
- Exam (elaborations) • 4 pages • 2021
-
- $13.49
- + learn more
Problem 1 
 
The following data were obtained from a project to create a new portable electronic. 
 
Activity	Duration	Predecessors	 
A		5 Days		--- 
B		6 Days		--- 
C		8 Days		--- 
D		4 Days		 
E		3 Days		 
F		5 Days		 
G		5 Days		 
H		9 Days		 
I		12 Days	 
 
Step 1: Construct a network diagram for the project. 
Step 2: Answer the following questions: (15 points total) 
 
a)	What is the Scheduled Completion of the Project? (5 points) 
 
 
b)	What is the Critical Path of the Project? (5 points)...
-
PROJ586_W3_Homework_AIB_Problems
- Exam (elaborations) • 5 pages • 2021
-
- $15.99
- + learn more
PROJ586_W3_Homework_AIB_Problems 
 
Problem 1 
 
The following data were obtained from a project to create a new portable electronic. 
 
Activity	Duration	Predecessors	 
A		5 Days		--- 
B		6 Days		--- 
C		8 Days		--- 
D		4 Days		A, B 
E		3 Days		C 
F		5 Days		D 
G		5 Days		E, F 
H		9 Days		D 
I		12 Days	G 
 
Step 1: Construct a network diagram for the project. 
Step 2: Answer the following questions: (15 points total) 
 
a)	What is the Scheduled Completion of the Project? (5 points) 
 
 
b)	What...
Fear of missing out? Then don’t!
Do you wonder why so many students wear nice clothes, have money to spare and enjoy tons of free time? Well, they sell on Stuvia! Imagine your study notes being downloaded a dozen times for $15 each. Every. Single. Day. Discover all about earning on Stuvia