BMS UY 1004
New York University
All 1 results
Sort by
-
LAB TEST
- Exam (elaborations) • 1 pages • 2021
-
- $10.49
- + learn more
Using the three-point estimating technique, if the most likely duration is four months, the 
optimistic duration is two months, and the pessimistic duration is one year, how many 
months is the expected activity duration? 
A. Two 
B. Four 
C. Five 
D. Twelve 
Hide Answer 
Question No : 679 - Topic 5 
When a permitting agency takes longer than planned to issue a permit, this can be 
described as a risk: 
A. event. 
B. response, 
C. perception. 
D. impact. 
Hide Answer 
Question No : 680 - Topic 5...
Make study stress less painful
Study stress? For sellers on Stuvia, these are actually golden times. KA-CHING! Earn from your study resources too and start uploading now. Discover all about earning on Stuvia