Using the three-point estimating technique, if the most likely duration is four months, the 
optimistic duration is two months, and the pessimistic duration is one year, how many 
months is the expected activity duration? 
A. Two 
B. Four 
C. Five 
D. Twelve 
Hide Answer 
Question No : 679 - Topic 5 
When a permitting agency takes longer than planned to issue a permit, this can be 
described as a risk: 
A. event. 
B. response, 
C. perception. 
D. impact. 
Hide Answer 