ICC Codes 104 Questions with Correct Answers 100% Verified
- Exam (elaborations) • 9 pages • 2024
-
- $10.99
- + learn more
ICC Codes 104 Questions with Correct Answers 100% Verified 
Which of the following publications is most useful for a Special Inspector? - Correct Answers ACI 318 
 
A ____ is a horizontal member that transfers loads laterally. - Correct Answers Beam 
 
Plain concrete refers to: - Correct Answers Concrete with less than the minimum amount of reinforcement 
 
A beam is primarily subject to _____ while a column is primarily subject to ______. - Correct Answers Flexure, compression 
 
The best place...
-
ICC Reinforced Concrete Exam Questions with Correct Answers
- Exam (elaborations) • 8 pages • 2024
-
- $10.99
- + learn more
ICC Reinforced Concrete Exam Questions with Correct Answers 
ACI 318 - Correct Answers Governs structural concrete design, construction, inspection and acceptance 
 
Load Path - Correct Answers A continuous system of structural elements that transfer an applied load to the supporting soil. 
 
Which of the following publications are most useful for a Special Inspector? - Correct Answers ACI 318 
 
A_____ is a horizontal member that transfers loads laterally. - Correct Answers Beam 
 
Plain concre...
-
General Requirements ICC Exam Questions with Correct Answers
- Exam (elaborations) • 4 pages • 2024
- Available in package deal
-
- $13.49
- + learn more
General Requirements ICC Exam Questions with Correct Answers 
 
The type and extent of each special inspection shall be located in - Answer-The statement of special inspection 
 
Who has the legal authority to enforce the special inspection provisions of the building code - Answer-Building official 
 
Who can hire an approved inspection agency - Answer-Owners agent 
 
Who can perform a structural observation - Answer-Registered design professional 
 
Who is required to receive the final report -...
-
ICC General Requirements Exam Questions with Correct Answers
- Exam (elaborations) • 4 pages • 2024
- Available in package deal
-
- $13.39
- + learn more
ICC General Requirements Exam Questions with Correct Answers 
The type and extent of each special inspections shall be located in? - Answer-The statement of special inspections -IBC 1704.3.1 
 
Who has the legal authority to enforce a special inspections provision building code? - Answer-building official -SIM page. 28 -page30 
 
Who can hire an approved inspection agency? - Answer-Owner or owner agent -IBC 1704.2 
 
Who can perform a structural observation? - Answer-Registered design professio...
-
ICC Codes Exam Questions with Correct Answers
- Exam (elaborations) • 7 pages • 2024
- Available in package deal
-
- $13.49
- + learn more
ICC Codes Exam Questions with Correct Answers 
Which of the following publications is most useful for a Special Inspector? - Answer-ACI 318 
 
A ____ is a horizontal member that transfers loads laterally. - Answer-Beam 
 
Plain concrete refers to: - Answer-Concrete with less than the minimum amount of reinforcement 
 
A beam is primarily subject to _____ while a column is primarily subject to ______. - Answer-Flexure, compression 
 
The best place to look up definitions in ACI 318-14 is: - Answ...
And that's how you make extra money
-
2024 ICC GENERAL REQUIREMENTS EXAM WITH 200+ REAL EXAM QUESTIONS AND CORRECT ANSWERS (100% CORRECT VERIFIED ANSWERS) ICC GR GENERAL REQUIREMENTS ACTUAL EXAM 2024-2025 (NEWEST!!)
- Exam (elaborations) • 43 pages • 2024
-
- $25.99
- + learn more
2024 ICC GENERAL REQUIREMENTS EXAM WITH 200+ REAL EXAM QUESTIONS AND CORRECT ANSWERS (100% CORRECT VERIFIED ANSWERS) ICC GR GENERAL REQUIREMENTS ACTUAL EXAM (NEWEST!!)
-
ICC General Requirements Practice Exam All Possible Questions and Answers with complete solution
- Exam (elaborations) • 4 pages • 2024
- Available in package deal
-
- $7.99
- + learn more
Who performs a structural observation? 
A) the RDP in responsible charge 
B) The special inspector 
C) The contractor 
D) The building official - Answer-A) the RDP in responsible charge 
Who prepares the statement of special inspections? 
A) The building offficial 
B) The contractor 
C) The owner 
D) The RDP - Answer-D) The RDP 
Who is in charge of reviewing and approving reports? 
A) The building offficial 
B) The contractor 
C) The owner 
D) The RDP - Answer-D) The RDP 
ICC exams are based on ...
-
ICC GENERAL REQUIREMENTS PRACTICE EXAM WITH GUARANTEED ACCURATE ANSWERS
- Exam (elaborations) • 5 pages • 2024
- Available in package deal
-
- $13.49
- + learn more
Who performs a structural observation? 
A) the RDP in responsible charge 
B) The special inspector 
C) The contractor 
D) The building official - ACCURATE ANSWERS A) the RDP in responsible charge 
 
Who prepares the statement of special inspections? 
A) The building offficial 
B) The contractor 
C) The owner 
D) The RDP - ACCURATE ANSWERS D) The RDP 
 
Who is in charge of reviewing and approving reports? 
A) The building offficial 
B) The contractor 
C) The owner 
D) The RDP - ACCURATE ANSWERS D...
-
ICC Bolting Exam Questions with Correct Answers.docx
- Exam (elaborations) • 13 pages • 2024
- Available in package deal
-
- $13.89
- + learn more
ICC Bolting Exam Questions with Correct A 
 
According to the IBC, the "blank" is to hire the special inspector. - Answer-owner or owners agent. 2009 IBC Section 1704.1 
 
According to the IBC, the "blank" is the responsible for the approval of a person's qualifications to act as a special inspector. - Answer-code official. 2009 IBC, Section 1704.1 
 
According to the IBC, discrepancy corrections are made known to the building official by: - Answer-final report. 2009 IBC, Section1704.1.2 
 ...
-
ICC General Requirements Practice Exam Questions With Complete Solutions 2024
- Exam (elaborations) • 5 pages • 2024
-
- $8.49
- + learn more
ICC General Requirements Practice Exam Questions With 
Complete Solutions 2024 
Who performs a structural observation? 
A) the RDP in responsible charge 
B) The special inspector 
C) The contractor 
D) The building official - -A) the RDP in responsible charge 
Who prepares the statement of special inspections? 
A) The building offficial 
B) The contractor 
C) The owner 
D) The RDP - -D) The RDP 
Who is in charge of reviewing and approving reports? 
A) The building offficial 
B) The contractor 
C...