Summary GFEBS L230E Cost Management Process Overview Complete Solutions Direct Cost A cost such as labor, materials, or supplies that can be traced directly to producing a specific output of an organization, product, and service Indirect Cost A cost that cannot be traced directly to a specific organization, product, and/or service output They often are allocated on a predetermined basis and generally are synonymous with overhead costs such as general and administrative expenses. Funded Cost The value of goods or services received because of an obligation of funds by the organization performing the work Unfunded Cost A cost that is financed by another organization's or activity's appropriations. Variable cost A cost that changes with a change in output fixed cost A cost that remains the same regardless of a change in output sunk cost A cost incurred in the past that will not be affected by any present or future decision incremental cost The increase or decrease in cost that would result from a decision to increase or decrease output levels avoidable cost A cost incurred on an object that will no longer be incurred due to a decision to change the output. unavoidable cost A cost incurred on an object that will be incurred regardless of the decision to change Activity Type An Activity Type is the cost master data that represents a group of resources within a Cost Center. These resource groups have capacity and a unit of measure such as: labor hours, machine hours, square footage, etc. Activity Types are used to produce the products and services of the organization. Cost Center A Cost Center is a responsibility center on which costs are incurred. It has an operational manager who is accountable for the resources consumed to produce the cost center's output. Project A Project is an object used to plan, collect, monitor, and control costs for large scale time-based events in Project Systems, when extensive scheduling and resource management capabilities are required. Projects have definite start and end dates WBS A WBS element is an activity within the Project used to plan and update cost data. Some examples of WBS Elemen

Mostrar más Leer menos
Institución
Grado









Ups! No podemos cargar tu documento ahora. Inténtalo de nuevo o contacta con soporte.

Escuela, estudio y materia

Grado

Información del documento

Subido en
19 de enero de 2023
Número de páginas
5
Escrito en
2022/2023
Tipo
Examen
Contiene
Preguntas y respuestas

Temas

Vista previa del contenido

Summary GFEBS L230E Cost Management Process
Overview Complete Solutions
Direct Cost
A cost such as labor, materials, or supplies that can be traced directly to producing a
specific output of an organization, product, and service
Indirect Cost
A cost that cannot be traced directly to a specific organization, product, and/or service
output They often are allocated on a predetermined basis and generally are
synonymous with overhead costs such as general and administrative expenses.
Funded Cost
The value of goods or services received because of an obligation of funds by the
organization performing the work
Unfunded Cost
A cost that is financed by another organization's or activity's appropriations.
Variable cost
A cost that changes with a change in output
fixed cost
A cost that remains the same regardless of a change in output
sunk cost
A cost incurred in the past that will not be affected by any present or future decision
incremental cost
The increase or decrease in cost that would result from a decision to increase or
decrease output levels
avoidable cost
A cost incurred on an object that will no longer be incurred due to a decision to change
the output.
unavoidable cost
A cost incurred on an object that will be incurred regardless of the decision to change
Activity Type
An Activity Type is the cost master data that represents a group of resources within a
Cost Center. These resource groups have capacity and a unit of measure such as:
labor hours, machine hours, square footage, etc. Activity Types are used to produce the
products and services of the organization.
Cost Center
A Cost Center is a responsibility center on which costs are incurred. It has an
operational manager who is accountable for the resources consumed to produce the
cost center's output.
Project
A Project is an object used to plan, collect, monitor, and control costs for large scale
time-based events in Project Systems, when extensive scheduling and resource
management capabilities are required. Projects have definite start and end dates
WBS
A WBS element is an activity within the Project used to plan and update cost data.
Some examples of WBS Elements are: tasks, partial tasks, and work packages

, Order
Orders are cost objects used to plan, collect, monitor, and settle the costs of jobs and
tasks
Internal Order
An object used to track costs and revenues (in some cases) associated with internal
jobs and tasks. Internal Orders are often used to monitor the costs related to shorter-
term projects or those individual services offered by an organization.
Work Order
A Work Order is a specific task performed on a demand or preventative basis. Work
Orders reside in the Plant Maintenance Module in GFEBS. Work Orders are task-driven
and specific in nature.
Business Process
is a cost object used to capture costs of cross-functional Cost Center activities.
Business Processes are the "work" being performed by the Cost Center and Activity
Types.
Statistical Key Figure
is a unit of measure, including quantity or time, by which costs are reported. For
example, the number of people (headcount) served at a meal in a dining facility.
Cost Management Process
four sub-processes that interact and affect one another.
The sub-processes are:
- Cost Planning
- Cost Accounting
- Cost Analysis
- Cost Controlling
Cost Planning
Set Cost Targets and Efficiency Goals.
Compute Standard Rates

Cost Planning allows managers to plot out the expected costs to accomplish their
assigned mission for the coming year
Cost Accounting
Captures and validates data.
Provides accurate, timely, and relevant data.
Connects operational output/performance data to financial data. Allocates overhead

Cost accounting covers the activities of capturing and collecting primary costs and
assigning secondary costs. All primary costs are collected in cost objects as a result of
a transaction performed in a GFEBS module.
Assignment
The establishment of a relationship between a sending cost object and a receiving cost
object based on a quantity, with a rate for valuation being consumed by the receiver.
Allocation
The establishment of a relationship between a sending cost object to one or more
receiving cost object(s) based on a % (even if a quantity is used to generate a %, e.g.,
number of FTEs).
7,98 €
Accede al documento completo:

100% de satisfacción garantizada
Inmediatamente disponible después del pago
Tanto en línea como en PDF
No estas atado a nada


Documento también disponible en un lote

Conoce al vendedor

Seller avatar
Los indicadores de reputación están sujetos a la cantidad de artículos vendidos por una tarifa y las reseñas que ha recibido por esos documentos. Hay tres niveles: Bronce, Plata y Oro. Cuanto mayor reputación, más podrás confiar en la calidad del trabajo del vendedor.
ACADEMICAIDSTORE Chamberlain College Of Nursing
Seguir Necesitas iniciar sesión para seguir a otros usuarios o asignaturas
Vendido
1196
Miembro desde
4 año
Número de seguidores
889
Documentos
11557
Última venta
1 semana hace
ACADEMICAID STORE

Contact : Email: : I have solutions for : Nursing, Business, Economics, Accounting, statistics, chemistry, Biology and all Courses, Certifications and Subjects. Send us a message in case you need any additional information! Nursing Being my main profession line, I have essential guides that are Almost A+ graded, I am a very friendly person: If you would not agreed with my solutions I am ready for refund.

Lee mas Leer menos
4,1

173 reseñas

5
95
4
29
3
28
2
6
1
15

Recientemente visto por ti

Por qué los estudiantes eligen Stuvia

Creado por compañeros estudiantes, verificado por reseñas

Calidad en la que puedes confiar: escrito por estudiantes que aprobaron y evaluado por otros que han usado estos resúmenes.

¿No estás satisfecho? Elige otro documento

¡No te preocupes! Puedes elegir directamente otro documento que se ajuste mejor a lo que buscas.

Paga como quieras, empieza a estudiar al instante

Sin suscripción, sin compromisos. Paga como estés acostumbrado con tarjeta de crédito y descarga tu documento PDF inmediatamente.

Student with book image

“Comprado, descargado y aprobado. Así de fácil puede ser.”

Alisha Student

Preguntas frecuentes