CCCA Exam Questions and Answers 100% correct 2024

 12 vistas  1 veces vendidas
  • Grado
  • CCCA - Certified Construction Contract Administrator
  • Institución
  • CCCA - Certified Construction Contract Administrator

Exam of 13 pages for the course CCCA - Certified Construction Contract Administrator at CCCA - Certified Construction Contract Administrator (CCCA Exam)

Vista previa 2 fuera de 13  páginas

  • 30 de abril de 2024
  • 13
  • 2023/2024
  • Examen
  • Preguntas y respuestas
  • CCCA - Certified Construction Contract Administrator
  • CCCA - Certified Construction Contract Administrator
avatar-seller
CCCA Exam

Preliminary Project Description PPD - answer describes the scope and relationships
of major elements organized in terms of building systems and components - CSI
recommends UniFormat for PPDS - describes as a system of components

Outline specifications - answer an abbreviated set of specification requirements
normally included with schematic design or design development documents. Bassi for
revising estimates of cost/schedule value - Record decisions

shop drawing - answer not a contract document - repared by contractor /
sub/equipment supplier and show how an aspect of the work is to be fabricated and
installed

methods of specifying - answer Descriptive, performance, reference standards,
proprietary

Descriptive Specification - answer detailed description of required properties of
product. A/E responsible for determination of desired performance criteria

Performance Specifications - answer required result with criteria for verifying
compliance

Proprietary specifications - answer identify the desired manufacture or unique
characteristic

closed vs open proprietary specification - answer

Two types of bonds - answer performance bond and payment bond

When are bonds expected to be delievered? - answer To the owner when the
contractor delivers the executed owner-contractor agreements

What are bonds - answer They are not insurance

What protects the owner against mechanics liens? - answer Payment bond

What protects suppliers and subs against nonpayment? - answer Payment bond

Surety bond - answer AKA contract bond

, Performance Bond - answer guaranty that if the contractor fails to perform, the surety
will either complete the contract or provide sufficient funds up to the penalty sum for
such completion

Other bonds in addition to performance and payment bonds - answer maintenance
bonds, lien bonds, retainage bonds (alternative to retainage), license and permit bonds
(from AHJs)

Who is responsible for coordinating work to be completed under separate contracts? -
answer Owner

Preliminary schedules must be submitted at least 10 days after the effective date of the
contract - answer According to many general standard conditions - ConsensusDocs
doesn't have this requirement

Two most frequently used schedule formats - answer critical path method (CPM)
bar chart

Approval for schedule by contractor - answer A/E reviews for compliance with
contracts - Owner determines if it meets requirements - In some contracts, schedule
revisions are allowed only by change order

Comprehensive schedule AKA project schedule - answer often a critical path
schedule beginning with the inception of the project and concludes with final acceptance

schedule of values - answer complements the progress schedule
identifies how all the costs int he project are apportioned

A/E can request supporting documentation from contractor when thee is a disagreement
on the proportionate value of items of work

Change orders are usually added to schedule of values

What records does the A/E maintain? - answer field observation reports
documentation of non-confirming work
correspondence
meeting minutes
communication reports
submittals
test reports
payment requests and certifications
schedule
requests for interpretation, clarification or information
proposal requests or change order requests
contract document modifications

Los beneficios de comprar resúmenes en Stuvia estan en línea:

Garantiza la calidad de los comentarios

Garantiza la calidad de los comentarios

Compradores de Stuvia evaluaron más de 700.000 resúmenes. Así estas seguro que compras los mejores documentos!

Compra fácil y rápido

Compra fácil y rápido

Puedes pagar rápidamente y en una vez con iDeal, tarjeta de crédito o con tu crédito de Stuvia. Sin tener que hacerte miembro.

Enfócate en lo más importante

Enfócate en lo más importante

Tus compañeros escriben los resúmenes. Por eso tienes la seguridad que tienes un resumen actual y confiable. Así llegas a la conclusión rapidamente!

Preguntas frecuentes

What do I get when I buy this document?

You get a PDF, available immediately after your purchase. The purchased document is accessible anytime, anywhere and indefinitely through your profile.

100% de satisfacción garantizada: ¿Cómo funciona?

Nuestra garantía de satisfacción le asegura que siempre encontrará un documento de estudio a tu medida. Tu rellenas un formulario y nuestro equipo de atención al cliente se encarga del resto.

Who am I buying this summary from?

Stuvia is a marketplace, so you are not buying this document from us, but from seller jopewa. Stuvia facilitates payment to the seller.

Will I be stuck with a subscription?

No, you only buy this summary for 17,44 €. You're not tied to anything after your purchase.

Can Stuvia be trusted?

4.6 stars on Google & Trustpilot (+1000 reviews)

45,681 summaries were sold in the last 30 days

Founded in 2010, the go-to place to buy summaries for 14 years now

Empieza a vender
17,44 €  1x  vendido
  • (0)
  Añadir