100% de satisfacción garantizada Inmediatamente disponible después del pago Tanto en línea como en PDF No estas atado a nada
logo-home
PJM Generator Exams Pack | Questions & 100% Correct Answers (Verified) | Latest Update | Grade A+ $28.49   Añadir al carrito

Lote

PJM Generator Exams Pack | Questions & 100% Correct Answers (Verified) | Latest Update | Grade A+

PJM Generator Exams Pack | Questions & 100% Correct Answers (Verified) | Latest Update | Grade A+

16 artículos

Generator operational requirements: PJM Manual 14 Exam | Questions & 100% Correct Answers (Verified) | Latest Update | Grade A+

(0)
$10.49

True or false? The interconnection coordination project manager coordinates the activities of PJM internal coordination and the generation owner to complete the generator markets and operations activities : True True or false? In the event that a local geography name has already been used in ...

Ver ejemplo

PJM Generation Dispatcher Exam | Questions & 100% Correct Answers (Verified) | Latest Update | Grade A+

(0)
$9.99

An EXCITER on a traditional generator does what? : Voltage regulation (AVR) if you change the excitation current, you change the voltage. ECO Min, ECO Max, and EMERG Max are genrator _________________. : Limits When synchronizing to the interconnection, what needs to be synchronized? : Freque...

Ver ejemplo

PJM Generator Exam | Questions & 100% Correct Answers (Verified) | Latest Update | Grade A+

(0)
$9.99

The purpose of the Deploy All Resources Action is to instruct all generating resources to be on line and at full output _________ : immediately upon receipt of dispatch instruction A Heavy Load Voltage Schedule Warning has been issued for the PJM RTO. Generation Operators should: : Ensure all...

Ver ejemplo

PJM Generation Dispatcher Sample Exam | Questions & 100% Correct Answers (Verified) | Latest Update | Grade A+

(0)
$10.49

Real time transmission constraints or contingencies may be alleviated with generators operating : A. below 60 hertz B. on a new price curve C. on a new cost curve D. off cost ( out of merit) : D. off cost ( out of merit ) Monitoring LMP may give insights into : A. system constraints B. sys...

Ver ejemplo

PJM Generation Cert Exam | Questions & 100% Correct Answers (Verified) | Latest Update | Grade A+

(0)
$14.39

Actions in low voltage alert? : Review transmission & generation outages Request reactive reserve check Heavy load voltage schedule warning purpose is to have members prepare far max support of voltages on the? : Bulk Power System Manual load dump warning & reduction of Non-critical plant loa...

Ver ejemplo

PJM Practice Exam | Questions & 100% Correct Answers (Verified) | Latest Update | Grade A+

(0)
$14.29

A Heavy Load Voltage Schedule Warning is typically issued ___ prior to actual implementation. : c. 4 hours The following would be considered non-critical plant load (Select 2) : A. Office Area Air Conditioners C. Lighting During a Cold Weather Alert, PJM will take which of the actions : D. A...

Ver ejemplo

PJM Sample Test Review Exam | Questions & 100% Correct Answers (Verified) | Latest Update | Grade A

(0)
$12.39

Real time transmission constraints or contingencies may be alleviated with generators operating ______________ : off cost out of merit. Monitoring ___________ may give insights into system constraints. : Monitoring LMP's PJM calls for _____________ reserves to recover ace so that tie line sch...

Ver ejemplo

PJM Generation Operation Exam | Questions & 100% Correct Answers (Verified) | Latest Update | Grade A+

(0)
$9.99

Control center facilities must have a minimum of how many days of fuel for the backup generator? : 5 days If PJM ACE shows overgeneration, actual imports are: : Less than scheduled Who should a generator contact at PJM to clear an outage ticket? : Master Coordinator To correct for a slow or ...

Ver ejemplo

PJM Practice Exam | Questions & 100% Correct Answers (Verified) | Latest Update | Grade A+

(0)
$9.99

Real time transmission constraints or contingencies may be alleviated with generators operating________. A. below 60 Hz. B. on a new price curve. C. on a new cost curve. D. off cost (out of merit). : off cost (out of merit) What is the minimum size for a solar park to be required to have real ...

Ver ejemplo

PJM Exam | Questions & 100% Correct Answers (Verified) | Latest Update | Grade A+

(0)
$12.99

What is the threshold for having a satellite phone? : 500 MW How often is reactive testing completed? : 5 years Which of the following would NOT be a cause for a sudden deviation in the balancing area ACE? 1) Incorrect interchange number 2) Loss of a tie-line RTU 3) Loss of internal load 4...

Ver ejemplo

PJM Exam | Questions & 100% Correct Answers (Verified) | Latest Update | Grade A+

(0)
$12.49

During reactive testing, which entity must give approval to change an approved voltage schedule? PJM, TOP, MOC, GO : TO Generation available within 10 minutes for offline reserve units: Quick-start (hydro), manual, operating, supplemental : Quick-start (hydro) Minimum MVARs for an individua...

Ver ejemplo

PJM Generator Operator Capacity Emergencies Exam | Questions & 100% Correct Answers (Verified) | Latest Update | Grade A+

(0)
$10.39

Unit Startup Notification Alert : Place generating units into a state of readiness (able to be brought online with 48 hours); when a reliability assessment determines long lead time generation is needed for a future period; roughly 6 days prior to day needed Maximum Generation/Load Management ...

Ver ejemplo

PJM Transmission Exam | Questions & 100% Correct Answers (Verified) | Latest Update | Grade A+

(0)
$13.49

During System Restoration, what is the optimal Frequency Range? : 59.75 - 61 Hz The 500 kV system has normal bus voltages between? : 500 to 550 kV When Connecting 2 islands, the operator must match? : Voltage, Phase Angle and Frequency What are the Minimum Source Requirements for a 500kV line?...

Ver ejemplo

PJM Test Exam | Questions & 100% Correct Answers (Verified) | Latest Update | Grade A+

(0)
$13.49

Which of the following balancing control modes is used by PJM under normal operations? : Tie-Line Bias Which of the following influences does PJM consider when performing their system load forecast? : Weather Conditions & Day of the Week All of the following are limits that must be submitted...

Ver ejemplo

PJM Generation Dispatch Exam | Questions & 100% Correct Answers (Verified) | Latest Update | Grade A+

(0)
$15.29

Which of the following statements is correct concerning PJM assuming frequency control of the restoration process? A) PJM assumes control once an external transmission tie has been established. B) Once an Area Control Error can be calculated, PJM will assume control. C) Whenever it becomes too ...

Ver ejemplo

Ultimate PJM Generation Exam Review | Questions & 100% Correct Answers (Verified) | Latest Update | Grade A+

(0)
$9.99

What is an ISO/RTO responsible for? : -Grid operations -Reliability -Transmission service Is an ISO/RTO is independent from: : -market participants -governance structure Does an ISO/RTO posses operational authority? : Yes PJM as an RTO Functions: : - Administer tariff - Administer regiona...

Ver ejemplo
Ver todos
avatar-seller

Los beneficios de comprar resúmenes en Stuvia estan en línea:

Garantiza la calidad de los comentarios

Garantiza la calidad de los comentarios

Compradores de Stuvia evaluaron más de 700.000 resúmenes. Así estas seguro que compras los mejores documentos!

Compra fácil y rápido

Compra fácil y rápido

Puedes pagar rápidamente y en una vez con iDeal, tarjeta de crédito o con tu crédito de Stuvia. Sin tener que hacerte miembro.

Enfócate en lo más importante

Enfócate en lo más importante

Tus compañeros escriben los resúmenes. Por eso tienes la seguridad que tienes un resumen actual y confiable. Así llegas a la conclusión rapidamente!

Preguntas frecuentes

What do I get when I buy this document?

You get a PDF, available immediately after your purchase. The purchased document is accessible anytime, anywhere and indefinitely through your profile.

100% de satisfacción garantizada: ¿Cómo funciona?

Nuestra garantía de satisfacción le asegura que siempre encontrará un documento de estudio a tu medida. Tu rellenas un formulario y nuestro equipo de atención al cliente se encarga del resto.

Who am I buying this summary from?

Stuvia is a marketplace, so you are not buying this document from us, but from seller MASTER01. Stuvia facilitates payment to the seller.

Will I be stuck with a subscription?

No, you only buy this summary for $28.49. You're not tied to anything after your purchase.

Can Stuvia be trusted?

4.6 stars on Google & Trustpilot (+1000 reviews)

45,681 summaries were sold in the last 30 days

Founded in 2010, the go-to place to buy summaries for 14 years now

Empieza a vender

Vistos recientemente


$190.14 $28.49
  • (0)
  Añadir