Examen
Practice questions for the NERC exam with correct answers
- Grado
- Institución
b. NERC Operating Committee CORRECT ANSWER What group can approve a change in the Disturbance Recovery Period for an Interconnection? a. NERC Interconnection Working Group b. NERC Operating Committee c. NERC Regional Council d. NERC Disturbance Analysis Working Group c. Check targets and...