Garantie de satisfaction à 100% Disponible immédiatement après paiement En ligne et en PDF Tu n'es attaché à rien
Recherché précédemment par vous
NERC CERTIFICATION EXAM TEST BANK | CONTAINS 4 DIFFERENT ALREADY TESTED VERSIONS WITH EXPERT VERIFIED QUESTIONS AND ANSWERS | GUARANTEED PASS| ALREADY GRADED A | LATEST UPDATE | INCLUDES A STUDY GUIDE AND ANSWER KEY AT THE END€17,32
Ajouter au panier
NERC CERTIFICATION EXAM TEST BANK | CONTAINS 4 DIFFERENT ALREADY TESTED VERSIONS WITH EXPERT VERIFIED QUESTIONS AND ANSWERS | GUARANTEED PASS| ALREADY GRADED A | LATEST UPDATE | INCLUDES A STUDY GUIDE AND ANSWER KEY AT THE END
NERC CERTIFICATION EXAM TEST BANK | CONTAINS 4 DIFFERENT
ALREADY TESTED VERSIONS WITH EXPERT VERIFIED QUESTIONS
AND ANSWERS | GUARANTEED PASS| ALREADY GRADED A |
LATEST UPDATE | INCLUDES A STUDY GUIDE AND ANSWER KEY
AT THE END
Accurate. I passed well . value for money indeed
Par: DrReiss • 11 mois de cela
Par: DrReiss • 11 mois de cela
GREAT WORK I PASSED WELL . I highly reccomend
Vendeur
S'abonner
DrMedinaReed
Avis reçus
Aperçu du contenu
NERC CERTIFICA TION EXAM TEST BA NK | CONTAINS 4 DIFFERENT ALREADY TESTED VERSIONS WITH EXPERT VERIFIED QUESTIONS AND ANSWERS | GUARANTEED PASS| ALREADY GRADED A | LATEST UPDATE | INCLUDES A STUDY GUIDE AND ANSWER KEY AT THE END 1. If a 500 kV transmission line with a surge impedance loading of 800 MW is currently loaded at 1400 MW, which of the following events would most likely occur? a. Generator MVAR output would increase b. All system capacitors would trip off -line c. Genera tor MVAR output would decrease d. All automatic reactors would connect to the system a. Generator MVAR output would increase 2. When system conditions are such that emergency procedures are expected to be implemented, which of the following actions should be considered first? a. Shed firm load b. Implement Active Load Management c. Return outaged equipment to service d. Request a voltage reduction c. Return outaged equipment to service 3. If your transmission path is rated for 1200 MW and 1000 MW are sched uled on it, but due to parallel flows the actual flow is 1300 MW, what action should you take? a. Request that a phase shifting transformer be installed b. Reduce interchange transactions impacting the path c. Request all parallel flow to PSEs to increase schedules d. Reduce all commercial customer load b. Reduce interchange transactions impacting the path 4. If your system is MVAR deficient, what action could be implemented to prevent voltage collapse? a. Raise system frequency above 60.5 Hz b. Shed firm load in the deficient area c. Separate from the Interconnection d. Lower transmission voltages b. Shed firm load in the deficient area 5. Which of the following actions can a system operator take in order to maintain stability on the system? a. Request generators to absorb maximum MVAR b. Place all operating limits on dynamic calculation c. Raise system voltages as high as possible, but within their operating parameters d. Reduce voltages on the transmission system c. Raise system voltages as high as possible, but within their operating parameters 6. Which of the following actions should you take if an outage on a neighboring system has caused a violation on your system? a. Open all tie -lines to your neighbo r b. Ask the Reliability Coordinator for assistance c. Shed load to mitigate the violation d. Wait for the neighboring system to contact you b. Ask the Reliability Coordinator for assistance 7. If a SOL or IROL violation occurs due to transfers across the system and it is determined that parallel flows are contributing to the violation, what should the system operator do? a. Place all system capacitors in service b. Reduce system load c. Inform the Reliability Coordinator d. Dump firm load c. Inform the Re liability Coordinator 8. While performing a pre -outage study, you identify that the transmission outage will cause a thermal violation on a parallel path, which of the following actions would be the first one you would implement? a. Shed load to mitigate the concern b. Allow the outage to occur and see what happens c. Reschedule the outage if possible d. Allow the outage to take place as long as no load is lost c. Reschedule the outage if possible 9. Which of the following actions should the system operato r implement first if transmission line limits exceed the facilities emergency limits based on a contingency that has not yet occurred, but their protocols are to respond on a pre -contingency basis? a. Reduce voltages in the area of the violation b. Remove the facility from service c. Curtail any interchange transactions that are curtailable d. Only implement actions if the contingency occurs c. Curtail any interchange transactions that are curtailable 10. If a Reliability Coordinator had to implement any t ype of line loading relief procedures, which of the following entities would they be coordinated with? Pick two. a. Purchasing Selling Entities b. Balancing Authorities c. Transmission Operators d. Load Serving Entities b. Balancing Authorities c. Transmission Operators 11. If a generator is lost in a neighboring Balancing Area, what would the impact be on the BAs transmission tie lines? a. Nothing b. A net increase of MW would come into your BAs system c. A net increase of MW would go out of yo ur BAs system d. They would exceed their emergency limits c. A net increase of MW would go out of your BAs system 12. According to the NERC Glossary, a constrained facility is defined as a transmission facility that is approaching, is at, or is beyond its? a. SOL or IROL b. Normal voltage parameters c. Available Transfer Capability d. Economic operating point a. SOL or IROL 13. How should a Transmission Operator that is affected by or contributing to transmission SOL or IROL limit violations respond to the situation? a. When time permits b. In coordination with other impacted entities c. Independent of all other parties d. Only at the direction of the Reliability Coordinator b. In coordination with other impacted entities 14. If a transmission operator is experiencing a SOL or IROL violation, how long does the entity have to correct the problem? a. 10 minutes b. 20 minutes c. 30 minutes d. 60 minutes c. 30 minutes 15. If your system is experiencing high system loads, high system imports, and transmission facilities loaded to 100%, which of the following situations would make the situation worse? a. Loss of a distribution station b. An internal generator tripping c. A bulk capacitor connecting to the system d. A 500 kV tran smission line returned to service b. An internal generator tripping 16. If a transmission line has a flow of 500 MW and the LODF for a parallel line due to the loss of this line is .25, how many MW will shift to this line if the line relays out of service? a. 50 MW b. 125 MW c. 250 MW d. 500 MW b. 125 MW 17. If a transmission path is congested and it is determined that all curtailable transactions have a 15% affect on the path, how many MW of transactions must be curtailed if 30 MW of relief is needed? a. 15 MW b. 30 MW c. 100 MW d. 200 MW d. 200 MW 18. If a transmission line is violating its emergency thermal limit due to the tripping of a parallel line which of the following is NOT an appropriate action to implement? a. Shift generation b. Implement ALM c. Shed load d. Adjust the thermal ratings
Les avantages d'acheter des résumés chez Stuvia:
Qualité garantie par les avis des clients
Les clients de Stuvia ont évalués plus de 700 000 résumés. C'est comme ça que vous savez que vous achetez les meilleurs documents.
L’achat facile et rapide
Vous pouvez payer rapidement avec iDeal, carte de crédit ou Stuvia-crédit pour les résumés. Il n'y a pas d'adhésion nécessaire.
Focus sur l’essentiel
Vos camarades écrivent eux-mêmes les notes d’étude, c’est pourquoi les documents sont toujours fiables et à jour. Cela garantit que vous arrivez rapidement au coeur du matériel.
Foire aux questions
Qu'est-ce que j'obtiens en achetant ce document ?
Vous obtenez un PDF, disponible immédiatement après votre achat. Le document acheté est accessible à tout moment, n'importe où et indéfiniment via votre profil.
Garantie de remboursement : comment ça marche ?
Notre garantie de satisfaction garantit que vous trouverez toujours un document d'étude qui vous convient. Vous remplissez un formulaire et notre équipe du service client s'occupe du reste.
Auprès de qui est-ce que j'achète ce résumé ?
Stuvia est une place de marché. Alors, vous n'achetez donc pas ce document chez nous, mais auprès du vendeur DrMedinaReed. Stuvia facilite les paiements au vendeur.
Est-ce que j'aurai un abonnement?
Non, vous n'achetez ce résumé que pour €17,32. Vous n'êtes lié à rien après votre achat.