Garantie de satisfaction à 100% Disponible immédiatement après paiement En ligne et en PDF Tu n'es attaché à rien
logo-home
ACI Certification / Concrete Flatwork Tech and Flatwork Finisher Exam tested Questions With Correct Reviewed Answers Chapter #1-#10 €12,85   Ajouter au panier

Examen

ACI Certification / Concrete Flatwork Tech and Flatwork Finisher Exam tested Questions With Correct Reviewed Answers Chapter #1-#10

 12 vues  0 fois vendu
  • Cours
  • ACI Flatwork
  • Établissement
  • ACI Flatwork

ACI Certification / Concrete Flatwork Tech and Flatwork Finisher Exam tested Questions With Correct Reviewed Answers Chapter #1-#10 (Ch. 1, #1) It is important that the _______ _______ read and understand project specifications - ANSWER : finishing foreman (Ch. 1, #2) If the crew can ...

[Montrer plus]

Aperçu 4 sur 32  pages

  • 13 août 2024
  • 32
  • 2024/2025
  • Examen
  • Questions et réponses
  • ACI Flatwork
  • ACI Flatwork
avatar-seller
ACI Certification / Concrete
Flatwork Tech and Flatwork
Finisher Exam tested Questions
With Correct Reviewed Answers
Chapter #1-#10

(Ch. 1, #1) It is important that the _______ _______ read
and understand project specifications - ANSWER ✔ :
finishing foreman

(Ch. 1, #2) If the crew can place and finish 100yd^3 (m^3)
of concrete per hour, the producer's rate should be about
____ yd^3(m^3) per hour. - ANSWER ✔ : 100

(Ch 1, #3) True or False: Concrete is sold by the ton. -
ANSWER ✔ : False (sold by volume)

(Ch. 1, #4) Delays in discharging concrete trucks can
result in the concrete being hard to: - ANSWER ✔ :
pump, place, and finish

(Ch. 1, #5)
A) Inch/Pound: For a concrete floor slab that is 6 in. thick,
200ft long, and 100 ft wide you should order ____ yd^3 of
concrete, assuming a 10% waste factor.

,B) Metric: For a concrete floor slab that is 150 mm thick,
60 m long, and 30 m wide you should order ____ m^3 of
concrete, assuming a 10% waste factor. - ANSWER ✔ :
A) 407.41; B) 297

(Ch. 1, #6) When there is room for two concrete trucks
ready to discharge into a pump hopper, placement is
faster because: - ANSWER ✔ : as one truck is finishing,
the other is ready to unload concrete

(Ch. 1, #7) Concrete from a ready mix truck must be
completely discharged within ____ hours after water has
been added at the plant. - ANSWER ✔ : 1.5

(Ch. 1, #8) You can tell when water was added to the
concrete truck by looking at the: - ANSWER ✔ : batch
ticket

(Ch. 1, #9) When concrete for a slab placement will be
discharged from the truck chute, truck arrivals should
usually be spaced about: - ANSWER ✔ : 15 minutes

(Ch. 1, #10) True or False: When finishers get behind
because the concrete is setting faster than expected and
the placing crew is also shorthanded, one solution is
slowing the concrete delivery rate to match worker output.
- ANSWER ✔ : True

(Ch. 1, #11) True or False: In deciding how much
concrete to order for a floor placement, you should

,calculate the number of cubic yards (cubic meters) needed
to fill the forms, then order two or three cubic yards (cubic
meters) less so you don't waste concrete that is not
needed. - ANSWER ✔ : False (Standard is to order 10%
to 15% *more* than measured volume for small orders
and 5 to 10% more than measured volume for large orders
to account for subgrade settlement, uneven subgrade,
spillage, and waste.)

(Ch. 1, #12) The question "What finisher or finishers can
request the addition of water to the concrete truck on
site?" Should be answered at the _________
__________. - ANSWER ✔ : preconstruction conference

(Ch. 2, #1) True or False: Concrete made with portland
cement will set and harden while underwater. - ANSWER
✔ : True

(Ch. 2, #2) If a concrete slab on ground won't be exposed
to sulfates, the cement used is most likely to be: -
ANSWER ✔ : Type I

(Ch. 2, #3) Fly ash may be added to concrete from a fly
ash silo at the batch plant or from a silo containing a
_______ cement. - ANSWER ✔ : portland

(Ch. 2, #4) Most concrete used in slabs on ground has
course aggregate with a maximum size of: - ANSWER ✔ :
0.75 to 1.5 in. (19 to 38 mm.)

, (Ch. 2, #5) True or False: Sand for concrete used in slabs
on ground is easier to finish when it has close to the
largest allowable amount of material passing the No. 50
and No. 100 sieves. - ANSWER ✔ : True

(Ch. 2, #6) True or False: Increasing the amount of sand
in a concrete usually decreases the amount of water
needed to make the concrete workable. - ANSWER ✔ :
False (Too many small particles will *increase* the amount
of water needed to make the concrete workable.)

(Ch. 2, #7) All concrete that will be subject to freezing
when moist or be exposed to deicing salts should contain:
- ANSWER ✔ : an air-entraining agent

(Ch. 2, #8) Strength of normal weight concrete depends
mainly on: - ANSWER ✔ : water-cement ratio

(Ch. 2, #9) True or False: Oversanded concrete mixtures
are likely to produce floors with poor wear resistance and
excessive shrinkage. - ANSWER ✔ : True

(Ch. 2, #10) To minimize shrinkage and reduce cracking
and curling: - ANSWER ✔ : Use as much coarse
aggregate as possible, as little mixing water as possible,
and use aggregates with low shrinkage.

(Ch. 2, #11) Changes in concrete slump most often
represent changes in the amount of ______ in the mixture.
- ANSWER ✔ : water

Les avantages d'acheter des résumés chez Stuvia:

Qualité garantie par les avis des clients

Qualité garantie par les avis des clients

Les clients de Stuvia ont évalués plus de 700 000 résumés. C'est comme ça que vous savez que vous achetez les meilleurs documents.

L’achat facile et rapide

L’achat facile et rapide

Vous pouvez payer rapidement avec iDeal, carte de crédit ou Stuvia-crédit pour les résumés. Il n'y a pas d'adhésion nécessaire.

Focus sur l’essentiel

Focus sur l’essentiel

Vos camarades écrivent eux-mêmes les notes d’étude, c’est pourquoi les documents sont toujours fiables et à jour. Cela garantit que vous arrivez rapidement au coeur du matériel.

Foire aux questions

Qu'est-ce que j'obtiens en achetant ce document ?

Vous obtenez un PDF, disponible immédiatement après votre achat. Le document acheté est accessible à tout moment, n'importe où et indéfiniment via votre profil.

Garantie de remboursement : comment ça marche ?

Notre garantie de satisfaction garantit que vous trouverez toujours un document d'étude qui vous convient. Vous remplissez un formulaire et notre équipe du service client s'occupe du reste.

Auprès de qui est-ce que j'achète ce résumé ?

Stuvia est une place de marché. Alors, vous n'achetez donc pas ce document chez nous, mais auprès du vendeur EWLindy. Stuvia facilite les paiements au vendeur.

Est-ce que j'aurai un abonnement?

Non, vous n'achetez ce résumé que pour €12,85. Vous n'êtes lié à rien après votre achat.

Peut-on faire confiance à Stuvia ?

4.6 étoiles sur Google & Trustpilot (+1000 avis)

72042 résumés ont été vendus ces 30 derniers jours

Fondée en 2010, la référence pour acheter des résumés depuis déjà 14 ans

Commencez à vendre!

Récemment vu par vous


€12,85
  • (0)
  Ajouter