CFCM Study Guide: FULL TEST QUESTIONS & ANSWERS(GRADED A+)

 4 vues  0 fois vendu
  • Cours
  • CFCM Stu
  • Établissement
  • CFCM Stu

Which of the following statements is NOT true? a. The government encourages the maximum practicable commercial use of inventions made under government contracts. b. The government recognizes rights in data developed at private expense, and limits its demands for delivery of that data. c. The g...

[Montrer plus]

Aperçu 4 sur 51  pages

  • 8 octobre 2024
  • 51
  • 2024/2025
  • Examen
  • Questions et réponses
  • CFCM Stu
  • CFCM Stu
avatar-seller
CFCM Study Guide: FULL TEST QUESTIONS &
ANSWERS(GRADED A+)


Which of the following statements is NOT true?



a. The government encourages the maximum practicable commercial use of inventions made under
government contracts.

b. The government recognizes rights in data developed at private expense, and limits its demands for
delivery of that data.

c. The government requires that contractors obtain permission from copyright owners before
including copyrighted works, owned by others, in data to be delivered to the government.

d. Generally, the government will refuse to award a contract on the grounds that the prospective
contractor may infringe a patent. - ANSWERd. Generally, the government will refuse to award a
contract on the grounds that the prospective contractor may infringe a patent.



FAR 27.102



Performance and payment bonds are required or may be required for



a. construction contracts and services and supply contracts exceeding $2,000.

b. construction contracts exceeding $150,000.

c. any contract for services,

d. construction contracts exceeding $150,000 and services and supply contracts exceeding the SAT
when necessary to protect the governments interests. - ANSWERd. construction contracts exceeding
$150,000 and services and supply contracts exceeding the SAT when necessary to protect the
governments interests.



FAR 28.102-1(a), 28.103-1(a), 28.103-2(a)



Cost Accounting Standards Board rules and regulations apply to



a. negotiated contracts and subcontracts.

,b. sealed bid contracts.

c. contracts with small business concerns.

d. bridge contracts. - ANSWERa. negotiated contracts and subcontracts.



FAR 30.201-5



Which of the following statements about advance agreements is NOT true?



a. Advance agreements may only be negotiated with a particular contractor for a single contract.

b. Advance agreements may be negotiated either before or during a contract.

c. The agreement must be in writing.

d. The agreements must be incorporated into applicable current and future contracts. - ANSWERa.
Advance agreements may only be negotiated with a particular contractor for a single contract.



FAR 31.109



A cost is reasonable if, in its nature and amount, it does not exceed that which would be



a. incurred by a prudent person in the conduct of competitive business.

b. accrued by a prudent person in the conduct of competitive business.

c. determined to be allowable by the CO.

d. determined to be allocable by the CO. - ANSWERa. incurred by a prudent person in the conduct of
competitive business.



FAR 31.201-3



What definition best describes alternative dispute resolution?



a. Procedures used to resolve issues in controversy.

b. Procedures voluntarily used to resolve issues in controversy.

c. Procedures used for asserting and resolving claims.

,d. Procedures voluntarily used for asserting and resolving claims. - ANSWERb. Procedures voluntarily
used to resolve issues in controversy.



FAR 33.214



The government's policy is to try to resolve all contractual issues in controversy by



a. mutual agreement at the CO's level.

b. bilateral agreement at the CO's level.

c. mutual agreement at a level above the CO.

d. unilateral agreement at the CO's level. - ANSWERa. mutual agreement at the CO's level.



FAR 33.204



After receiving the GAO's written notice that a protest has been filed, an agency must give notice



a. of the protest to the contractor or all parties who appear to have a reasonable prospect of
receiving an award.

b. of the protest only to the prime contractor performing the work.

c. of the protest to all parties who appear to have a reasonable prospect of receiving award and
begin compiling the information necessary to report to the GAO.

d. through a government-wide point of entry (GPE). - ANSWERa. of the protest to the contractor or
all parties who appear to have a reasonable prospect of receiving an award.



FAR 33.104



Does a $75,000 claim resulting from a reduction of $350,000 and an increase of $275,000 require
certification?



a. No, because the claimed amount is less than $100,000.

b. Yes, because the aggregate value of the claim exceeds $100,000.

c. No, because the claimed amount is less than $500,000.

, d. Yes, because the aggregate value of the claim exceeds $500,000. - ANSWERb. Yes, because the
aggregate value of the claim exceeds $100,000.



FAR 33.207(d)



Protests may be filed with



a. either the agency or the GAO.

b. the agency, the GAO, or the U.S. Court of Claims.

c. either the contracting officer or the U.S. Court of Federal Claims.

d. Small Claims Court for awards under the SAT. - ANSWERb. the agency, the GAO, or the U.S. Court
of Claims.



FAR 33.102



Who can authorize continued performance in the face of a protest after award?



a. the chief of the contracting office

b. the CO, provided his findings are documented in the file.

c. the head of the contracting activity.

d. the commanding officers. - ANSWERc. the head of the contracting activity.



FAR 33.104(c)(2)



The CO shall consider all protests and seek legal advice



a. only if protests are received after award and filed directly with the agency.

b. only if the protest is received after award and filed directly with the GAO.

c. whether protests are submitted before or after award.

d. whether protests are submitted before or after award and whether filed directly with the GAO, the
U.S Court of Claims, or the agency. - ANSWERd. whether protests are submitted before or after
award and whether filed directly with the GAO, the U.S Court of Claims, or the agency.

Les avantages d'acheter des résumés chez Stuvia:

Qualité garantie par les avis des clients

Qualité garantie par les avis des clients

Les clients de Stuvia ont évalués plus de 700 000 résumés. C'est comme ça que vous savez que vous achetez les meilleurs documents.

L’achat facile et rapide

L’achat facile et rapide

Vous pouvez payer rapidement avec iDeal, carte de crédit ou Stuvia-crédit pour les résumés. Il n'y a pas d'adhésion nécessaire.

Focus sur l’essentiel

Focus sur l’essentiel

Vos camarades écrivent eux-mêmes les notes d’étude, c’est pourquoi les documents sont toujours fiables et à jour. Cela garantit que vous arrivez rapidement au coeur du matériel.

Foire aux questions

Qu'est-ce que j'obtiens en achetant ce document ?

Vous obtenez un PDF, disponible immédiatement après votre achat. Le document acheté est accessible à tout moment, n'importe où et indéfiniment via votre profil.

Garantie de remboursement : comment ça marche ?

Notre garantie de satisfaction garantit que vous trouverez toujours un document d'étude qui vous convient. Vous remplissez un formulaire et notre équipe du service client s'occupe du reste.

Auprès de qui est-ce que j'achète ce résumé ?

Stuvia est une place de marché. Alors, vous n'achetez donc pas ce document chez nous, mais auprès du vendeur ClassRep2. Stuvia facilite les paiements au vendeur.

Est-ce que j'aurai un abonnement?

Non, vous n'achetez ce résumé que pour €13,55. Vous n'êtes lié à rien après votre achat.

Peut-on faire confiance à Stuvia ?

4.6 étoiles sur Google & Trustpilot (+1000 avis)

80364 résumés ont été vendus ces 30 derniers jours

Fondée en 2010, la référence pour acheter des résumés depuis déjà 14 ans

Commencez à vendre!

Récemment vu par vous


€13,55
  • (0)
  Ajouter