OMIS 635 Test 2 Question and answers already passed OMIS 635 Test 2 What is resource smoothing (or leveling)? - correct answer Involves attempting to even out varying demands on resources by using slack (delaying noncritical activities) to manage resource utilization when resources are ade...

[Montrer plus]

Aperçu 4 sur 36  pages

  • 6 novembre 2024
  • 36
  • 2024/2025
  • Examen
  • Questions et réponses
  • OMIS
  • OMIS
avatar-seller
OMIS 635 Test 2
What is resource smoothing (or leveling)? - correct answer ✔Involves
attempting to even out varying demands
on resources by using slack (delaying noncritical activities) to manage
resource utilization when resources are adequate over the life of the project


What is resource-constrained scheduling? - correct answer ✔The duration of
a project may be increased by delaying the late start of some of its activities if
resources are not adequate to meet peak demands


What are technical or logic constraints? - correct answer ✔Constraints
related to the networked sequence in which project activities must occur


What are physical constraints? - correct answer ✔Activities that cannot occur
in parallel or are affected by contractual or environmental conditions


What are resource constraints? - correct answer ✔The absence, shortage,
or unique interrelationship and interaction characteristics of resources that
require a particular sequencing of project activities
People, materials, equipment


What are the types of project constraints? - correct answer ✔-Technical or
logic
-Physical
-Resource


How do you determine the classification of a problem? - correct answer
✔Using a priority matrix will help determine if the project is time or resource
constrained.

,What is a time-constrained project? - correct answer ✔-Must be completed
by an imposed date


-Require use of leveling techniques that focus
on balancing or smoothing resource demands.


-Use positive slack (delaying noncritical activities) to manage resource
utilization over the duration
of the project.


-Time is fixed, resources are flexible: additional resources are required to
ensure project meets schedule.


What is resource-constrained project? - correct answer ✔-Is one in which the
level of resources available cannot be exceeded.
-Resources are fixed, time is flexible: inadequate resources
will delay the project.


What are limiting assumptions? - correct answer ✔-Splitting activities is not
allowed—once an activity is start, it is carried to completion


-Level of resources used for an activity cannot be changed


What are risk assumptions? - correct answer ✔-Activities with the most slack
pose the least risk.


-Reduction of flexibility does not increase risk.

,-The nature of an activity (easy, complex) doesn't increase risk


What are the advantages of resource demand leveling techniques for time-
constrained projects? - correct answer ✔-Peak resource demands are
reduced


-Resources over the life of the project are reduced


-Fluctuation in resource demand is minimized.


What are the disadvantages of resource demand leveling techniques for time-
constrained projects? - correct answer ✔-Loss of flexibility that occurs from
reducing slack


-Increases in the criticality of all activities


What are the order of heuristics
(rules-of-thumb)? - correct answer ✔1) Minimum slack


2) Smallest (least) duration


3) Lowest activity identification number


What is an EMR project? - correct answer ✔The development of a handheld
electronic medical reference guide to be used by emergency medical
technicians and paramedics

, What is the problem with EMR projects? - correct answer ✔There are only
eight design engineers who can be assigned to the project due to a shortage
of design engineers and commitments to other projects.


What are the impacts of resource-constrained scheduling? - correct answer
✔-Reduces slack; reduces flexibility
-Increases criticality of events
-Increases scheduling complexity
-May make the traditional critical path no longer meaningful
-Can break sequence of events
-May cause parallel activities to become sequential
-Activities with slack may become critical


What is splitting? - correct answer ✔-A scheduling technique for creating a
better project schedule and/or increase resource utilization


-Involves interrupting work on an activity to employ the resource on another
activity, then returning the resource to finish the interrupted work.
-Is feasible when startup and shutdown costs are low.
-Is considered the major reason why projects fail to meet schedule.


What are the benefits of scheduling resources? - correct answer ✔-Leaves
time for consideration of reasonable alternatives:
-Cost-time tradeoffs
-Changes in priorities


-Provides information for time-phased work package budgets to assess:
-Impact of unforeseen events

Les avantages d'acheter des résumés chez Stuvia:

Qualité garantie par les avis des clients

Qualité garantie par les avis des clients

Les clients de Stuvia ont évalués plus de 700 000 résumés. C'est comme ça que vous savez que vous achetez les meilleurs documents.

L’achat facile et rapide

L’achat facile et rapide

Vous pouvez payer rapidement avec iDeal, carte de crédit ou Stuvia-crédit pour les résumés. Il n'y a pas d'adhésion nécessaire.

Focus sur l’essentiel

Focus sur l’essentiel

Vos camarades écrivent eux-mêmes les notes d’étude, c’est pourquoi les documents sont toujours fiables et à jour. Cela garantit que vous arrivez rapidement au coeur du matériel.

Foire aux questions

Qu'est-ce que j'obtiens en achetant ce document ?

Vous obtenez un PDF, disponible immédiatement après votre achat. Le document acheté est accessible à tout moment, n'importe où et indéfiniment via votre profil.

Garantie de remboursement : comment ça marche ?

Notre garantie de satisfaction garantit que vous trouverez toujours un document d'étude qui vous convient. Vous remplissez un formulaire et notre équipe du service client s'occupe du reste.

Auprès de qui est-ce que j'achète ce résumé ?

Stuvia est une place de marché. Alors, vous n'achetez donc pas ce document chez nous, mais auprès du vendeur Academia199. Stuvia facilite les paiements au vendeur.

Est-ce que j'aurai un abonnement?

Non, vous n'achetez ce résumé que pour €12,85. Vous n'êtes lié à rien après votre achat.

Peut-on faire confiance à Stuvia ?

4.6 étoiles sur Google & Trustpilot (+1000 avis)

70073 résumés ont été vendus ces 30 derniers jours

Fondée en 2010, la référence pour acheter des résumés depuis déjà 15 ans

Commencez à vendre!

Récemment vu par vous


€12,85
  • (0)
Ajouter au panier
Ajouté