ISA 387 Chapter 3 Quiz | Answered with complete solutions A Gantt chart can simplify a complex project by combining several activities into a task _____ that contains subsidiary tasks. bar network group hierarchy A _____ involves breaking a project down into a series of smaller tasks. value brea...
A Gantt chart can simplify a complex project by combining several activities into a task
_____ that contains subsidiary tasks.
bar
network
group
hierarchy
A _____ involves breaking a project down into a series of smaller tasks.
value breakdown structure (VBS)
concept breakdown structure (CBS)
risk breakdown structure (RBS)
work breakdown structure (WBS)
When maintaining schedules, if enough _____ and frequent checkpoints exist, problems
will be detected rapidly.
milestones
viewports
activity diagrams
data flow diagrams
A _____ is a proactive effort to anticipate a risk and describe an action plan to deal with
it.
risk balance plan
risk response plan
risk management plan
risk identification plan
Critical time is the amount of time that the task could be late without pushing back the
completion date of the entire project.
True
False
False (Slack time is the amount of time that the task could be late without pushing back
the completion date of the entire project.)
A(n) _____ is a condition, restriction, or requirement that the system must satisfy.
Progress reports may be given verbally to immediate supervisors, management, and
users.
True
False
False (Although a progress report might be given verbally to an immediate supervisor,
reports to management and users usually are written.)
In most systems analysis tasks, time and people are interchangeable.
False
True
A project manager should never develop time and cost estimates based on the
resources used for previously developed information systems.
True
False
False (A project manager can develop time and cost estimates based on the resources
used for similar, previously developed information systems.)
Weight is an importance value that is added to each duration estimate.
True
False
Generally, systems analysts review the work of other systems analysts, and
programmers review the work of other programmers, as a form of peer review, in
structured walk-throughs.
True
False
Project managers always must be aware of the _____, so they can monitor the vital
tasks and keep a project on track.
Les clients de Stuvia ont évalués plus de 700 000 résumés. C'est comme ça que vous savez que vous achetez les meilleurs documents.
L’achat facile et rapide
Vous pouvez payer rapidement avec iDeal, carte de crédit ou Stuvia-crédit pour les résumés. Il n'y a pas d'adhésion nécessaire.
Focus sur l’essentiel
Vos camarades écrivent eux-mêmes les notes d’étude, c’est pourquoi les documents sont toujours fiables et à jour. Cela garantit que vous arrivez rapidement au coeur du matériel.
Foire aux questions
Qu'est-ce que j'obtiens en achetant ce document ?
Vous obtenez un PDF, disponible immédiatement après votre achat. Le document acheté est accessible à tout moment, n'importe où et indéfiniment via votre profil.
Garantie de remboursement : comment ça marche ?
Notre garantie de satisfaction garantit que vous trouverez toujours un document d'étude qui vous convient. Vous remplissez un formulaire et notre équipe du service client s'occupe du reste.
Auprès de qui est-ce que j'achète ce résumé ?
Stuvia est une place de marché. Alors, vous n'achetez donc pas ce document chez nous, mais auprès du vendeur Jumuja. Stuvia facilite les paiements au vendeur.
Est-ce que j'aurai un abonnement?
Non, vous n'achetez ce résumé que pour €15,10. Vous n'êtes lié à rien après votre achat.