PRM3701 ASSESSMENT 7 2024 SEMESTER 2. One who endorses and lends political support for the completion of a specific project is known as the a. Project manager b. CEO c. Project sponsor d. Project lead e. Sacred cow 2,71 €   Ajouter au panier

Examen

PRM3701 ASSESSMENT 7 2024 SEMESTER 2. One who endorses and lends political support for the completion of a specific project is known as the a. Project manager b. CEO c. Project sponsor d. Project lead e. Sacred cow

1 vérifier
 24 vues  4 fois vendu
  • Cours
  • Établissement
  • Book

PRM3701 ASSESSMENT 7 2024 SEMESTER 2. One who endorses and lends political support for the completion of a specific project is known as the a. Project manager b. CEO c. Project sponsor d. Project lead e. Sacred cow

Aperçu 4 sur 547  pages

  • 12 octobre 2024
  • 547
  • 2024/2025
  • Examen
  • Questions et réponses

1  vérifier

review-writer-avatar

Par: mtmmushwana • 2 semaines de cela

reply-writer-avatar

Par: BMZAcademy • 2 semaines de cela

Thank you mtmmushwana for the review, tell us if you need anything more about the assignment or the module or any other modules please get in touch through the provided details

avatar-seller
BMZ ACADEMY




BMZ ACADEMY




@061 262 1185/068 053 8213



BMZ ACADEMY 061 262 1185/068 053 8213

,Assessment 7 https://mymodules.dtls.unisa.ac.za/mod/quiz/attempt.php?attempt=23




PRM3701-24-S2  Welcome Message  Assessment 7

QUIZ




Question 1

Not yet answered

Marked out of 1.00




Match the six elements on the recommended project scope checklist to the de�nition of each element.


Project objective The �rst step pf a project scope

Deliverables The expected measurable outputs over the life of a project

Milestones Major segments of work

Technical requirements To ensure proper performance

Limits and exclusions Failure to de�ne can lead to false expectations

Reviews with customers Completion of the scope checklist




Question 2

Not yet answered

Marked out of 1.00




This question is not for marks.
In terms of project management, what is a deliverable and give an example.


Answer: referes to the expected measurable outputs over the life of a project, for example a completed laptop




Question 3

Not yet answered

Marked out of 1.00




SWOT Analysis is used to aid in strategic planning


True

False




1 of 7 10/12/2024, 6:48

,Assessment 7 https://mymodules.dtls.unisa.ac.za/mod/quiz/attempt.php?attempt=23


Question 4

Not yet answered

Marked out of 1.00




One who endorses and lends political support for the completion of a speci�c project is known as the


a. Project manager

b. CEO

c. Project sponsor

d. Project lead

e. Sacred cow

Clear my choice




Question 5

Not yet answered

Marked out of 1.00




Which dimension of project management centers on creating a temporary social system within a larger organizational
environment that combines the talents of a divergent set of professionals working to complete the project?



Select one:
a. Communication

b. Sociocultural

c. Social

d. Technical

e. Scheduling

Clear my choice




Question 6

Not yet answered

Marked out of 1.00




Which of the following is not a bene�t of Earned Value Management?


a. Measures accomplishments against plan and deliverables.

b. Provides a method for tracking directly to a problem work package and organization unit responsible.

c. Enables the project manager to ascertain problem paths within the project network and when the critical path is
underperforming.

d. Alerts all stakeholders to early identi�cation of problems and allows for quick, proactive corrective action.

e. Provides for accountability over individual portions of the overall budget for each organization unit.

Clear my choice




2 of 7 10/12/2024, 6:48

,Assessment 7 https://mymodules.dtls.unisa.ac.za/mod/quiz/attempt.php?attempt=23


Question 7

Not yet answered

Marked out of 1.00




. In the Snapshot from Practice in your textbook, the results of analyzing the Katrina hurricane resulted in a new evaluation plan
from:


a. The state legislature

b. The governor of Louisiana




c. The city of New Orleans

d. The Red Cross

Clear my choice




Question 8

Not yet answered

Marked out of 1.00




Which part of the audit report examines in detail the underlying causes of problems, issues, and successes relative to the
project and includes concise, factual review statements of the project?


a. Classi�cation

b. Analysis

c. Recommendations

d. Lessons learned

e. Appendix

Clear my choice




Question 9

Not yet answered

Marked out of 1.00




Research consistently points out that project success is strongly affected by the degree to which a project has the support of
top management. The following are ways a project manager can manage upward relationships EXCEPT


a. never ignore the chains of command.

b. prove loyalty
c. pick the optimum time to appeal to top management.

d. consistently follow through on requests.

e. accept profound differences in perspective and become skilled at the art of persuading superiors.

Clear my choice




3 of 7 10/12/2024, 6:48

Les avantages d'acheter des résumés chez Stuvia:

Qualité garantie par les avis des clients

Qualité garantie par les avis des clients

Les clients de Stuvia ont évalués plus de 700 000 résumés. C'est comme ça que vous savez que vous achetez les meilleurs documents.

L’achat facile et rapide

L’achat facile et rapide

Vous pouvez payer rapidement avec iDeal, carte de crédit ou Stuvia-crédit pour les résumés. Il n'y a pas d'adhésion nécessaire.

Focus sur l’essentiel

Focus sur l’essentiel

Vos camarades écrivent eux-mêmes les notes d’étude, c’est pourquoi les documents sont toujours fiables et à jour. Cela garantit que vous arrivez rapidement au coeur du matériel.

Foire aux questions

Qu'est-ce que j'obtiens en achetant ce document ?

Vous obtenez un PDF, disponible immédiatement après votre achat. Le document acheté est accessible à tout moment, n'importe où et indéfiniment via votre profil.

Garantie de remboursement : comment ça marche ?

Notre garantie de satisfaction garantit que vous trouverez toujours un document d'étude qui vous convient. Vous remplissez un formulaire et notre équipe du service client s'occupe du reste.

Auprès de qui est-ce que j'achète ce résumé ?

Stuvia est une place de marché. Alors, vous n'achetez donc pas ce document chez nous, mais auprès du vendeur BMZAcademy. Stuvia facilite les paiements au vendeur.

Est-ce que j'aurai un abonnement?

Non, vous n'achetez ce résumé que pour 2,71 €. Vous n'êtes lié à rien après votre achat.

Peut-on faire confiance à Stuvia ?

4.6 étoiles sur Google & Trustpilot (+1000 avis)

84669 résumés ont été vendus ces 30 derniers jours

Fondée en 2010, la référence pour acheter des résumés depuis déjà 14 ans

Commencez à vendre!
2,71 €  4x  vendu
  • (1)
  Ajouter