Summary MGT3035 W4.docx MGT3035 Week 4 Project MGT3035 South University The Project Management Body of Knowledge (PMBOK) describes the critical path as œthe sequence of scheduled activities that determine the duration of a project. The critical path is by f€6,90
In winkelwagen
Summary MGT3035 W4.docx MGT3035 Week 4 Project MGT3035 South University The Project Management Body of Knowledge (PMBOK) describes the critical path as œthe sequence of scheduled activities that determine the duration of a project. The critical path is by f
1 keer bekeken 0 aankoop
Vak
UAGC
Instelling
Ashford University
MGT3035 W MGT3035 Week 4 Project MGT3035 South University The Project Management Body of Knowledge (PMBOK) describes the critical path as œthe sequence of scheduled activities that determine the duration of a project. The critical path is by far the most intensive sequence of responsibiliti...
mgt3035 w4docx mgt3035 week 4 project mgt3035 south university the project management body of knowledge pmbok describes the critical path as œthe sequence of scheduled activities that determin
Geschreven voor
Ashford University
UAGC
Alle documenten voor dit vak (718)
Verkoper
Volgen
helperatsof1
Ontvangen beoordelingen
Voorbeeld van de inhoud
MGT3035
Week 4 Project
MGT3035
South University
The Project Management Body of Knowledge (PMBOK) describes the critical path as “the
sequence of scheduled activities that determine the duration of a project.” The critical path is by
far the most intensive sequence of responsibilities within a project plan that must be completed
on time for the project to meet its projected deadline. There should not be any delay during any
of the tasks given in the critical path, if there is a delay this could cause the whole project to fall
behind. Many projects include only one critical path, but some unique projects utilize multiple
critical paths.
The critical path method is a project management technique that is used to find events on
the critical path. The critical path method is a unique approach to project scheduling where the
project is broken into several different work tasks, displays them in a flow chart, and then
determines how long the project is to continue based on estimations. This methodology
identifies tasks that are critical to complete to ensure the project is completed in a timely manner.
The network diagram’s critical path is B, E, G; the project will take 23 days to finish.
There are several techniques used to determine probabilities of project completion, one of
these is a simulation technique called Monte Carlo simulation. This simulation helps is used to
predict the probability of different outcomes when random variables are added, this helps
discover the probability of risk during a project. The Monte Carlo method applied to a single
variable ensures that the amount obtained is taken from the population described by the
variable’s population distribution.
Voordelen van het kopen van samenvattingen bij Stuvia op een rij:
Verzekerd van kwaliteit door reviews
Stuvia-klanten hebben meer dan 700.000 samenvattingen beoordeeld. Zo weet je zeker dat je de beste documenten koopt!
Snel en makkelijk kopen
Je betaalt supersnel en eenmalig met iDeal, creditcard of Stuvia-tegoed voor de samenvatting. Zonder lidmaatschap.
Focus op de essentie
Samenvattingen worden geschreven voor en door anderen. Daarom zijn de samenvattingen altijd betrouwbaar en actueel. Zo kom je snel tot de kern!
Veelgestelde vragen
Wat krijg ik als ik dit document koop?
Je krijgt een PDF, die direct beschikbaar is na je aankoop. Het gekochte document is altijd, overal en oneindig toegankelijk via je profiel.
Tevredenheidsgarantie: hoe werkt dat?
Onze tevredenheidsgarantie zorgt ervoor dat je altijd een studiedocument vindt dat goed bij je past. Je vult een formulier in en onze klantenservice regelt de rest.
Van wie koop ik deze samenvatting?
Stuvia is een marktplaats, je koop dit document dus niet van ons, maar van verkoper helperatsof1. Stuvia faciliteert de betaling aan de verkoper.
Zit ik meteen vast aan een abonnement?
Nee, je koopt alleen deze samenvatting voor €6,90. Je zit daarna nergens aan vast.