OPM H11 Resource Planning
Resource planning = a process that takes sales and operations plan
Processes information in the way of time standards, routings, and other
information on how services or products are produced; and then plans the
input requirements
Materials requirements planning (MRP) = a computerized information system
developed specifically to help manufactures manage dependent demand inventory
and schedule replenishment orders
MRP explosion = a process that converts
the requirements of various final products
into a material requirements plan that
specifies the replenishment schedules of all
the subassemblies, components, and raw
materials needed to produce final products
Dependent demand = the demand for
an item that occurs because the quantity
required varies with the production plans
for other items held in the firm’s inventory
Parent = an product that is manufactured
from one or more components
Component= an item that goes through
one or more operations to be
transformed into or become part of one
or more parents Figuur 1 Parent inventory Figuur 2 Component demand
Master production schedule (MPS) = a part
of the material requirements plan that details how
many end items will be produced within specified
periods of time
In a MPS:
- Sums of quantities must equal sales and
operations plan
- Production quantities must be allocated
efficiently over time
- Capacity limitations and bottlenecks may
the timing and size of MPS quantities
1
, Figuur 3 MPS Process
MPS opstellen:
1. Calculate projected on-hand inventories
2. Determine the timing and size of MPS quantities
- Goal is to maintain a nonnegative projected on-hand
inventory balance
- As shortages in inventory are detected, MPS
quantities should be scheduled to cover them
Available-to-promise (ATP) inventory:
- The quantity of end items that marketing can promise
to deliver on specific dates
- It’s the difference between the customer orders
already booked and the quantity that operations is
planning to produce
Freezing the MPS disallow changes to the near-
term portion of the MPS
Reconciling the MPS with Sales and Operations
Plans
MRP Explosion:
- Bill of materials (BOM) = a record of all the
components of an item, the parent-
component relationship, and the usage
quantities derived from engineering and
process designs
- End items
- Intermediate items
- Subassemblies
- Purchased items
- Part commonality
2
Voordelen van het kopen van samenvattingen bij Stuvia op een rij:
Verzekerd van kwaliteit door reviews
Stuvia-klanten hebben meer dan 700.000 samenvattingen beoordeeld. Zo weet je zeker dat je de beste documenten koopt!
Snel en makkelijk kopen
Je betaalt supersnel en eenmalig met iDeal, creditcard of Stuvia-tegoed voor de samenvatting. Zonder lidmaatschap.
Focus op de essentie
Samenvattingen worden geschreven voor en door anderen. Daarom zijn de samenvattingen altijd betrouwbaar en actueel. Zo kom je snel tot de kern!
Veelgestelde vragen
Wat krijg ik als ik dit document koop?
Je krijgt een PDF, die direct beschikbaar is na je aankoop. Het gekochte document is altijd, overal en oneindig toegankelijk via je profiel.
Tevredenheidsgarantie: hoe werkt dat?
Onze tevredenheidsgarantie zorgt ervoor dat je altijd een studiedocument vindt dat goed bij je past. Je vult een formulier in en onze klantenservice regelt de rest.
Van wie koop ik deze samenvatting?
Stuvia is een marktplaats, je koop dit document dus niet van ons, maar van verkoper lieker. Stuvia faciliteert de betaling aan de verkoper.
Zit ik meteen vast aan een abonnement?
Nee, je koopt alleen deze samenvatting voor €3,99. Je zit daarna nergens aan vast.