TEST BANK FOR PMI (PMP) EXAM 6TH EDITION PMBOK (COMPLETE SOLUTION)
TEST BANK FOR PMI (PMP) EXAM 6TH EDITION PMBOK (COMPLETE SOLUTION) QUESTION 1 An element of the project scope statement is: A. Acceptance criteria. B. A stakeholder list. C. A summary budget, D. High-level risks. Correct Answer: A QUESTION 2 Which document describes the necessary information to determine if a project is worth the required investment? A. Cost baseline B. Service level agreement C. Memorandum of understanding D. Business case Correct Answer: D