Werkcollege aantekeningen Financial and project management (440026-B-6) The Basics of financial management-exercises, ISBN: 9789001889234 €6,49   In winkelwagen

College aantekeningen

Werkcollege aantekeningen Financial and project management (440026-B-6) The Basics of financial management-exercises, ISBN: 9789001889234

1 beoordeling
 42 keer bekeken  6 keer verkocht

Complete uitwerking van de werkcolleges van het van zowel het project management als het financial management gedeelte.

Voorbeeld 3 van de 23  pagina's

  • 5 april 2023
  • 23
  • 2022/2023
  • College aantekeningen
  • J. berns, t. buyl, r. kenda, oerlemans, waveren,
  • Alle colleges
book image

Titel boek:

Auteur(s):

  • Uitgave:
  • ISBN:
  • Druk:
Alle documenten voor dit vak (4)

1  beoordeling

review-writer-avatar

Door: janssennina04 • 4 maanden geleden

avatar-seller
emmahamm
WC Financial and project management




Workshop Financial and project
management
PM - Workshop 1 1
FM - Workshop 1 11
FM - Workshop 2 15




0

, WC Financial and project management



PM - Workshop 1
1. Provide a definition of “project”.
→ an individual or collaborative enterprise that is carefully planned to achieve a particular aim.

2. Project-based organizations are well-suited for achieving economies of scale?
a) True b) False
→ project is more about providing a unique service/product

3. Which of the examples below can be characterized as project?
a) Building a bridge across river Lek.
b) Preparing a new personal loan package at ABN AMRO.
c) Restructuring the company’s internet page due to legislative changes.
d) All of the above.

4. In the implementation and termination phase of a temporary project the efforts of
project members are typically the highest.
a) True b) False

5. During which stage of the project has a project manager the most influence?
a) Before the project starts.
b) During the planning process.
c) During the execution of the work.
d) During the closing processes.
→ keep it in the general sense. During the last phases: administrative part. Hre the project
manager has the most influence.



6.
a) True b) False
→ what is actually done, compared to what was the plan

7. Which are the three important factors for the success of a project, also known as “the
triple constraint”?
a) Environment, Resources, Time
b) Cost, Time, Quality
c) Specifications, People, Cost
d) Quality, Resources, Stakeholder relations

8. The three important factors for the success of a project play a crucial role in the
project priority matrix?
a) True b) False




1

, WC Financial and project management


9. Having at least two bosses is a disadvantage of …
a) functional organization model.
b) pure project organization model.
c) matrix organization model.
d) flat organization model.
→ d doesn’t exist double management problem is in general problem of matrix

10. Within a functional organization a project manager has…
a) high to ultimate authority.
b) authority to assign resources.
c) minimal to no authority.
d) authority to recommend resources.
→ above project manager: another boss, the functional manager. This one has high to ultimate
authority
!! keep the roles separate. The project manager CAN be functional, but 2 diff. roles

11. Which of the following characteristics is not in line with the project-based
organization (PBO)?
a) It is not appropriate for complex, not routine tasks.
b) Employees are highly loyal.
c) It promotes high flexibility.
d) Organizational learning might deteriorate.

12. Stakeholder influence is …
a) high during the overall project life cycle.
b) lowest at the end of a project life cycle.
c) highest at the start of a project life cycle.
d) lowest at the start of a project life cycle.
→ the further you go with the project, the more costly it will get to implement any changes

13. The “kick-off” meeting is …
a) held before the project charter is set up.
b) important to provide an overview and basic rules of the project.
c) a repetitive event.
d) All of the above is true.
→ everyone comes together, meet each other.
1 incorrect. It is held after the project charter is set up
3 incorrect. Only one time, at beginning

14. Complete the sentence by selecting the correct option: During the project
mobilization phase, …
a) all lessons learned are documented.
b) different deliverable options are evaluated.
c) all stakeholders are informed about the project.


2

Voordelen van het kopen van samenvattingen bij Stuvia op een rij:

Verzekerd van kwaliteit door reviews

Verzekerd van kwaliteit door reviews

Stuvia-klanten hebben meer dan 700.000 samenvattingen beoordeeld. Zo weet je zeker dat je de beste documenten koopt!

Snel en makkelijk kopen

Snel en makkelijk kopen

Je betaalt supersnel en eenmalig met iDeal, creditcard of Stuvia-tegoed voor de samenvatting. Zonder lidmaatschap.

Focus op de essentie

Focus op de essentie

Samenvattingen worden geschreven voor en door anderen. Daarom zijn de samenvattingen altijd betrouwbaar en actueel. Zo kom je snel tot de kern!

Veelgestelde vragen

Wat krijg ik als ik dit document koop?

Je krijgt een PDF, die direct beschikbaar is na je aankoop. Het gekochte document is altijd, overal en oneindig toegankelijk via je profiel.

Tevredenheidsgarantie: hoe werkt dat?

Onze tevredenheidsgarantie zorgt ervoor dat je altijd een studiedocument vindt dat goed bij je past. Je vult een formulier in en onze klantenservice regelt de rest.

Van wie koop ik deze samenvatting?

Stuvia is een marktplaats, je koop dit document dus niet van ons, maar van verkoper emmahamm. Stuvia faciliteert de betaling aan de verkoper.

Zit ik meteen vast aan een abonnement?

Nee, je koopt alleen deze samenvatting voor €6,49. Je zit daarna nergens aan vast.

Is Stuvia te vertrouwen?

4,6 sterren op Google & Trustpilot (+1000 reviews)

Afgelopen 30 dagen zijn er 79223 samenvattingen verkocht

Opgericht in 2010, al 14 jaar dé plek om samenvattingen te kopen

Start met verkopen
€6,49  6x  verkocht
  • (1)
  Kopen