PMG CAPSTONE EXAM QUESTIONS WITH
COMPLETE SOLUTIONS
Your team is building a website that will consist of four new pages of content. Your project plan has two
team members work together to deliver one page of content: one will outline page content while the
other does mockups of page layout. Then they will work together to produce the completed page.
Which of the following represents a milestone in your project plan?
A completed page of content
A completed mockup of page layout
A completed outline of page content
A completed project plan
ANSWER IS - A completed page of content
What is the purpose of your project plan?
To identify milestones
To document scope
To keep your project on track
To determine tasks
ANSWER IS - To keep your project on track
You start a new job as a project manager in the private banking industry. You need to have a basic
understanding of topics such as how clients open accounts, back office operations, and how trade
confirmations are verified. Which of the following terms refers to the knowledge you need?
point
Intellectual property
Enterprise learning
Competitive intelligence
Domain knowledge
ANSWER IS - Domain knowledge
When populating your project plan with a set of tasks, when is the best time to hold a group
brainstorming session with team members to help identify tasks? Select all that apply.
After you research your project online
After you review project documentation
,ESTUDY
After brainstorming a task list with senior stakeholders
Before you do any other project work
ANSWER IS - After you review project documentation
After you research your project online
You have gathered information from project documentation and the project team. With this
information, you identified and created a list of tasks for your project plan. What is the next step for
completing your project plan?
Identify points in the project plan where you can evaluate completed work. F
Identify tasks that carry a high risk. (F)
Identify the order in which tasks need to be completed.
Identify tasks that stakeholders have a particular interest in.
ANSWER IS -
Which of the following may indicate a milestone for your project?
A task that has a major impact on the project's overall progress
A task that involves the fewest dependencies (F)
A task that has the highest confidence ratings
A task that your team has the most experience with
ANSWER IS - A task that has a major impact on the project's overall progress
What term refers to a time estimate that only takes into account the actual time it takes to complete a
task?
point
Taskflow duration estimate
Total duration estimate (F)
Effort estimate
Milestone estimate
ANSWER IS -
Which of the measures involved in "three-point" time estimations express how long you hope the task
will take, assuming everything goes as planned?
point
Milestone time estimates (F)
Most likely time estimates
Planning time estimates F
, ESTUDY
Optimistic time estimates
ANSWER IS - Optimistic time estimates
Which of the following circumstances is likely to cause a low confidence rating for a task?
point
It is a task that takes a long time to complete. F
It is a task that was completed quickly during past projects. (F)
It is a task that your team has never done before.
It is a task that involves only one team member.
ANSWER IS - It is a task that your team has never done before.
Which of the following is a good way to bring empathy to a conversation?
point
Listen with curiosity.
Start by clearly stating your position.
Keep the conversation brief.
Keep the conversation focused and on point.
ANSWER IS - Listen with curiosity.
Which of the following is a common quality management tool to help ensure that your project is
delivering quality and producing a desired outcome?
point
Post-mortem reviews F
Cost-benefit analyses
Feedback surveys
Three-point estimating F
ANSWER IS -
What term refers to the requirements and specifications that your product must meet in order to be
considered successful by your stakeholders?
point
Quality management
Quality documentation F
Quality assurance
Quality standards
ANSWER IS -
Voordelen van het kopen van samenvattingen bij Stuvia op een rij:
Verzekerd van kwaliteit door reviews
Stuvia-klanten hebben meer dan 700.000 samenvattingen beoordeeld. Zo weet je zeker dat je de beste documenten koopt!
Snel en makkelijk kopen
Je betaalt supersnel en eenmalig met iDeal, creditcard of Stuvia-tegoed voor de samenvatting. Zonder lidmaatschap.
Focus op de essentie
Samenvattingen worden geschreven voor en door anderen. Daarom zijn de samenvattingen altijd betrouwbaar en actueel. Zo kom je snel tot de kern!
Veelgestelde vragen
Wat krijg ik als ik dit document koop?
Je krijgt een PDF, die direct beschikbaar is na je aankoop. Het gekochte document is altijd, overal en oneindig toegankelijk via je profiel.
Tevredenheidsgarantie: hoe werkt dat?
Onze tevredenheidsgarantie zorgt ervoor dat je altijd een studiedocument vindt dat goed bij je past. Je vult een formulier in en onze klantenservice regelt de rest.
Van wie koop ik deze samenvatting?
Stuvia is een marktplaats, je koop dit document dus niet van ons, maar van verkoper Estudyr. Stuvia faciliteert de betaling aan de verkoper.
Zit ik meteen vast aan een abonnement?
Nee, je koopt alleen deze samenvatting voor €11,77. Je zit daarna nergens aan vast.