AHJ - Authorities Having Jurisdiction - Correct Answer
✅Protect public health, safety and welfare
Design Team - Correct Answer ✅Address planning issues,
determine design program, identify codes and regulations,
produce procurement and construction documents,
administer construction contract, *provide QA/QC
procedures*
Contractor Team - Correct Answer ✅Entity that constructs a
facility. Uses management abilities to gather labor forces,
subs, and material/product/equipment suppliers
Supplier Team - Correct Answer ✅Furnishes the materials and
products for the facility to be constructed. Fabricator,
Distributor, Manufacturer, Supplier.
,CSI CDT Exam Questions and Answers
(Latest Update 2024)
Facility Life Cycle - Correct Answer ✅The life cycle of a
facility, from concept through construction to use and
eventual deconstruction.
Project Conception
Project Delivery
Design
Construction Documents
Procurement (Bidding/Negotiating/Purchasing)
Construction
Facility Management
Project Conception - Correct Answer ✅Transforms the needs
of owner into clear concept on which project can be designed.
Feasibility Study, Programming, Site Selection, Budgeting.
Project Delivery - Correct Answer ✅Determine delivery
method to be used. Factors - qualifications, experience,
capacity, project extent, time requirements.
,CSI CDT Exam Questions and Answers
(Latest Update 2024)
Design - Correct Answer ✅Two Phases: schematic design and
design development. Deliverables include graphic and written
design documents and estimates of project cost.
Schematic Design - Correct Answer ✅Overall relationships
and functions. Site plan and area, general size/shape/massing
of elements, elevations and exteriors established, conceptual
design criteria identified.
Construction Documents - Correct Answer ✅Defined as the
written and graphic documents prepared or assembled by the
A/E for communicating the project design for construction
and administering the construction contract. Construction
documents include two major types of documents:
Procurement documents and Contract documents.
, CSI CDT Exam Questions and Answers
(Latest Update 2024)
Procurement (Bidding/Negotiating/Purchasing) - Correct
Answer ✅Acceptance of the contractor's bid or negotiated
sum and other conditions will result in award of a contract
and commencement of work.
Construction - Correct Answer ✅Responsibilities:
Contractor - perform work, project coordination, comply with
project documents.
A/E - construction admin, evaluation services, certify
application for payment, final inspection of work.
Owner - provide information, process payments, approve
contract modifications, accept project upon completion.
Facility Management - Correct Answer ✅During occupancy,
owners & facility managers maintain and evaluate the
performance of the project and determine suitability for
continuing use.
Voordelen van het kopen van samenvattingen bij Stuvia op een rij:
Verzekerd van kwaliteit door reviews
Stuvia-klanten hebben meer dan 700.000 samenvattingen beoordeeld. Zo weet je zeker dat je de beste documenten koopt!
Snel en makkelijk kopen
Je betaalt supersnel en eenmalig met iDeal, creditcard of Stuvia-tegoed voor de samenvatting. Zonder lidmaatschap.
Focus op de essentie
Samenvattingen worden geschreven voor en door anderen. Daarom zijn de samenvattingen altijd betrouwbaar en actueel. Zo kom je snel tot de kern!
Veelgestelde vragen
Wat krijg ik als ik dit document koop?
Je krijgt een PDF, die direct beschikbaar is na je aankoop. Het gekochte document is altijd, overal en oneindig toegankelijk via je profiel.
Tevredenheidsgarantie: hoe werkt dat?
Onze tevredenheidsgarantie zorgt ervoor dat je altijd een studiedocument vindt dat goed bij je past. Je vult een formulier in en onze klantenservice regelt de rest.
Van wie koop ik deze samenvatting?
Stuvia is een marktplaats, je koop dit document dus niet van ons, maar van verkoper Allivia. Stuvia faciliteert de betaling aan de verkoper.
Zit ik meteen vast aan een abonnement?
Nee, je koopt alleen deze samenvatting voor €14,52. Je zit daarna nergens aan vast.