CCO practice test questions with 100% correct answers 2024/2025 Before crane erection can begin what must be available? - ANSWERSsurface that is firm, drained and graded OSHA 29 CFR 1926.1407 Power Line Safety, Option 1 requires what? - ANSWERSPower lines are de-energize and grounded Before work can begin for a newly erected tower crane what must be done before the crane can begin working? - ANSWERSset load motion limits and safety devices What type of attachment system is used to hold a personnel platform to the crane hook? - ANSWERSMaster link attachment or safety type shackle When should a personnel platform be used? - ANSWERSThere is no other safe way to perform the task OSHA, Cranes and Derricks working in Construction is under what regulation? - ANSWERSOSHA 29 CFR 1926.550 What is the Safety Factor for suspended platform and shackles? - ANSWERS5 to 1 What ASME Standard applies to personnel platforms? - ANSWERSB 30.23 Annual inspection records must be kept for how long? - ANSWERS12 months What ASME Standard applies to Tower Cranes? - ANSWERSB 30.3 Expendable tower base, the tolerance for "plumb" is? - ANSWERS¼ - 10ft.

Meer zien Lees minder
Instelling
CCO Practice
Vak
CCO practice









Oeps! We kunnen je document nu niet laden. Probeer het nog eens of neem contact op met support.

Geschreven voor

Instelling
CCO practice
Vak
CCO practice

Documentinformatie

Geüpload op
20 september 2024
Aantal pagina's
5
Geschreven in
2024/2025
Type
Tentamen (uitwerkingen)
Bevat
Vragen en antwoorden

Onderwerpen

Voorbeeld van de inhoud

CCO practice test questions with 100%
correct answers 2024/2025

Before crane erection can begin what must be available? - ANSWERSsurface that is firm, drained and
graded



OSHA 29 CFR 1926.1407 Power Line Safety, Option 1 requires what? - ANSWERSPower lines are de-
energize and grounded



Before work can begin for a newly erected tower crane what must be done before the crane can begin
working? - ANSWERSset load motion limits and safety devices



What type of attachment system is used to hold a personnel platform to the crane hook? -
ANSWERSMaster link attachment or safety type shackle



When should a personnel platform be used? - ANSWERSThere is no other safe way to perform the task



OSHA, Cranes and Derricks working in Construction is under what regulation? - ANSWERSOSHA 29 CFR
1926.550



What is the Safety Factor for suspended platform and shackles? - ANSWERS5 to 1



What ASME Standard applies to personnel platforms? - ANSWERSB 30.23



Annual inspection records must be kept for how long? - ANSWERS12 months



What ASME Standard applies to Tower Cranes? - ANSWERSB 30.3



Expendable tower base, the tolerance for "plumb" is? - ANSWERS¼ - 10ft.

, Free standing Hammerhead tower crane mast will be "plumbed" to a tolerance of - ANSWERS1 inch=
40ft.



Before crane components are erected they shall be: - ANSWERSVisually inspected for damage from
shipping and handling



Where would the insulating link device be attached? - ANSWERSAttached or installed at the end of load
line and the load



Annual/comprehensive inspection must include the qualified person to perform what? -
ANSWERSFunctional motion testing of the equipment



Rail buffers or rail stops must be placed how far from the end of the travel tracks? - ANSWERS3 ft



Internal climbing crane must be plumbed by using what to hold crane in position? - ANSWERSWedges



What is the maximum rate of wind speed allowed to climb a tower crane? - ANSWERS20 mph



during erection or dismantling operations, who must always be present? - ANSWERSAD director



How many wraps shall remain on the hoist drum according to the Tower Crane Reference Manual? -
ANSWERS3 wraps on the hoist drum



Personnel Platform must be Proof Tested each day before use, how much weight is used and how long
must the test last for? - ANSWERS125% and hold for 5 minutes



OSHA 1926.1407 power line requirements for 1000kv are? - ANSWERSRemain 20' or more from lines



Standing rope or pendant lines must have the following minimum design factor of? - ANSWERS3:1
€7,51
Krijg toegang tot het volledige document:

100% tevredenheidsgarantie
Direct beschikbaar na je betaling
Lees online óf als PDF
Geen vaste maandelijkse kosten


Ook beschikbaar in voordeelbundel

Maak kennis met de verkoper

Seller avatar
De reputatie van een verkoper is gebaseerd op het aantal documenten dat iemand tegen betaling verkocht heeft en de beoordelingen die voor die items ontvangen zijn. Er zijn drie niveau’s te onderscheiden: brons, zilver en goud. Hoe beter de reputatie, hoe meer de kwaliteit van zijn of haar werk te vertrouwen is.
Bensuda Oxford University
Volgen Je moet ingelogd zijn om studenten of vakken te kunnen volgen
Verkocht
839
Lid sinds
3 jaar
Aantal volgers
445
Documenten
21262
Laatst verkocht
1 dag geleden
ECONOMICS,NURSING,BIOLOGY AND ALL REVISION MATERIALS

DEDICATED TO PROVIDE YOU WITH THE BEST LEARNING MATERIALS THAT WILL IMPROVE YOUR GRADES ,WELCOME TO ALIZGRADES AND LETS DO IT TOGETHER!!! GOODLUCK!!!!!!!

3,7

157 beoordelingen

5
73
4
24
3
25
2
11
1
24

Recent door jou bekeken

Waarom studenten kiezen voor Stuvia

Gemaakt door medestudenten, geverifieerd door reviews

Kwaliteit die je kunt vertrouwen: geschreven door studenten die slaagden en beoordeeld door anderen die dit document gebruikten.

Niet tevreden? Kies een ander document

Geen zorgen! Je kunt voor hetzelfde geld direct een ander document kiezen dat beter past bij wat je zoekt.

Betaal zoals je wilt, start meteen met leren

Geen abonnement, geen verplichtingen. Betaal zoals je gewend bent via iDeal of creditcard en download je PDF-document meteen.

Student with book image

“Gekocht, gedownload en geslaagd. Zo makkelijk kan het dus zijn.”

Alisha Student

Veelgestelde vragen