100% tevredenheidsgarantie Direct beschikbaar na je betaling Lees online óf als PDF Geen vaste maandelijkse kosten 4.2 TrustPilot
logo-home
Tentamen (uitwerkingen)

OMIS 635 Test 2 Question and answers already passed

Beoordeling
-
Verkocht
-
Pagina's
36
Cijfer
A+
Geüpload op
06-11-2024
Geschreven in
2024/2025

OMIS 635 Test 2 Question and answers already passed OMIS 635 Test 2 What is resource smoothing (or leveling)? - correct answer Involves attempting to even out varying demands on resources by using slack (delaying noncritical activities) to manage resource utilization when resources are adequate over the life of the project What is resource-constrained scheduling? - correct answer The duration of a project may be increased by delaying the late start of some of its activities if resources are not adequate to meet peak demands What are technical or logic constraints? - correct answer Constraints related to the networked sequence in which project activities must occur What are physical constraints? - correct answer Activities that cannot occur in parallel or are affected by contractual or environmental conditions What are resource constraints? - correct answer The absence, shortage, or unique interrelationship and interaction characteristics of resources that require a particular sequencing of project activities People, materials, equipment What are the types of project constraints? - correct answer -Technical or logic -Physical -Resource

Meer zien Lees minder
Instelling
OMIS
Vak
OMIS











Oeps! We kunnen je document nu niet laden. Probeer het nog eens of neem contact op met support.

Geschreven voor

Instelling
OMIS
Vak
OMIS

Documentinformatie

Geüpload op
6 november 2024
Aantal pagina's
36
Geschreven in
2024/2025
Type
Tentamen (uitwerkingen)
Bevat
Vragen en antwoorden

Onderwerpen

Voorbeeld van de inhoud

OMIS 635 Test 2
What is resource smoothing (or leveling)? - correct answer ✔Involves
attempting to even out varying demands
on resources by using slack (delaying noncritical activities) to manage
resource utilization when resources are adequate over the life of the project


What is resource-constrained scheduling? - correct answer ✔The duration of
a project may be increased by delaying the late start of some of its activities if
resources are not adequate to meet peak demands


What are technical or logic constraints? - correct answer ✔Constraints
related to the networked sequence in which project activities must occur


What are physical constraints? - correct answer ✔Activities that cannot occur
in parallel or are affected by contractual or environmental conditions


What are resource constraints? - correct answer ✔The absence, shortage,
or unique interrelationship and interaction characteristics of resources that
require a particular sequencing of project activities
People, materials, equipment


What are the types of project constraints? - correct answer ✔-Technical or
logic
-Physical
-Resource


How do you determine the classification of a problem? - correct answer
✔Using a priority matrix will help determine if the project is time or resource
constrained.

,What is a time-constrained project? - correct answer ✔-Must be completed
by an imposed date


-Require use of leveling techniques that focus
on balancing or smoothing resource demands.


-Use positive slack (delaying noncritical activities) to manage resource
utilization over the duration
of the project.


-Time is fixed, resources are flexible: additional resources are required to
ensure project meets schedule.


What is resource-constrained project? - correct answer ✔-Is one in which the
level of resources available cannot be exceeded.
-Resources are fixed, time is flexible: inadequate resources
will delay the project.


What are limiting assumptions? - correct answer ✔-Splitting activities is not
allowed—once an activity is start, it is carried to completion


-Level of resources used for an activity cannot be changed


What are risk assumptions? - correct answer ✔-Activities with the most slack
pose the least risk.


-Reduction of flexibility does not increase risk.

,-The nature of an activity (easy, complex) doesn't increase risk


What are the advantages of resource demand leveling techniques for time-
constrained projects? - correct answer ✔-Peak resource demands are
reduced


-Resources over the life of the project are reduced


-Fluctuation in resource demand is minimized.


What are the disadvantages of resource demand leveling techniques for time-
constrained projects? - correct answer ✔-Loss of flexibility that occurs from
reducing slack


-Increases in the criticality of all activities


What are the order of heuristics
(rules-of-thumb)? - correct answer ✔1) Minimum slack


2) Smallest (least) duration


3) Lowest activity identification number


What is an EMR project? - correct answer ✔The development of a handheld
electronic medical reference guide to be used by emergency medical
technicians and paramedics

, What is the problem with EMR projects? - correct answer ✔There are only
eight design engineers who can be assigned to the project due to a shortage
of design engineers and commitments to other projects.


What are the impacts of resource-constrained scheduling? - correct answer
✔-Reduces slack; reduces flexibility
-Increases criticality of events
-Increases scheduling complexity
-May make the traditional critical path no longer meaningful
-Can break sequence of events
-May cause parallel activities to become sequential
-Activities with slack may become critical


What is splitting? - correct answer ✔-A scheduling technique for creating a
better project schedule and/or increase resource utilization


-Involves interrupting work on an activity to employ the resource on another
activity, then returning the resource to finish the interrupted work.
-Is feasible when startup and shutdown costs are low.
-Is considered the major reason why projects fail to meet schedule.


What are the benefits of scheduling resources? - correct answer ✔-Leaves
time for consideration of reasonable alternatives:
-Cost-time tradeoffs
-Changes in priorities


-Provides information for time-phased work package budgets to assess:
-Impact of unforeseen events
€12,35
Krijg toegang tot het volledige document:

100% tevredenheidsgarantie
Direct beschikbaar na je betaling
Lees online óf als PDF
Geen vaste maandelijkse kosten


Ook beschikbaar in voordeelbundel

Maak kennis met de verkoper

Seller avatar
De reputatie van een verkoper is gebaseerd op het aantal documenten dat iemand tegen betaling verkocht heeft en de beoordelingen die voor die items ontvangen zijn. Er zijn drie niveau’s te onderscheiden: brons, zilver en goud. Hoe beter de reputatie, hoe meer de kwaliteit van zijn of haar werk te vertrouwen is.
Academia199 Chamberlain College Of Nursing
Volgen Je moet ingelogd zijn om studenten of vakken te kunnen volgen
Verkocht
350
Lid sinds
3 jaar
Aantal volgers
208
Documenten
19011
Laatst verkocht
1 week geleden

3,9

50 beoordelingen

5
27
4
6
3
7
2
3
1
7

Recent door jou bekeken

Waarom studenten kiezen voor Stuvia

Gemaakt door medestudenten, geverifieerd door reviews

Kwaliteit die je kunt vertrouwen: geschreven door studenten die slaagden en beoordeeld door anderen die dit document gebruikten.

Niet tevreden? Kies een ander document

Geen zorgen! Je kunt voor hetzelfde geld direct een ander document kiezen dat beter past bij wat je zoekt.

Betaal zoals je wilt, start meteen met leren

Geen abonnement, geen verplichtingen. Betaal zoals je gewend bent via iDeal of creditcard en download je PDF-document meteen.

Student with book image

“Gekocht, gedownload en geslaagd. Zo makkelijk kan het dus zijn.”

Alisha Student

Veelgestelde vragen