NERC Certification Practice Questions and Answers(RATED A+)
- Exam (elaborations) • 1 pages • 2024
-
Available in package deal
-
- $7.99
- + learn more
Which of the following represents a virtual tie-line updated in real time? - ANSWER pseudo-tie 
 
Balancing Areas shall analyze forecasted generation availability and reserve levels, and inform their reliability coordinators of actual or potential generation deficiencies each: - ANSWER day 
 
Balancing authorities that share jointly owned generation must include their share of the unit governor droop response into their respective frequency bias setting if the energy is scheduled as a: - ANSWER ...
-
NERC Test Questions & Answers Correct 100%
- Exam (elaborations) • 2 pages • 2024
- Available in package deal
-
- $8.49
- + learn more
What is the calculation used for determining inadvertent interchange? - Answer Net actual interchange minus net scheduled interchange 
 
Which of the following would be a suitable use for a pseudo-tie? - Answer Accounting for jointly owned generators 
 
Which of the following entities may a Balancing Area provide interchange transaction information to? - Answer PSEs involved in the transaction 
 
Which of the following elements are NOT contained in the interchange transaction TAG? - Answer Cost ...
-
NERC EXAM PREPARATION QUESTIONS WITH CORRECT ANSWERS
- Exam (elaborations) • 2 pages • 2024
- Available in package deal
-
- $9.49
- + learn more
BAAL DOES NOT APPLY - Answer According to BAAL requirements of BAL-001, which of the following statements is true when actual frequency is greater than Scheduled Frequency? 
 
Tie Lines - Answer The ACE equation must include metered data: dynamic schedules, pseudo ties, actual frequency and all__________________ 
 
ACE - Answer A Balancing Authority has a sudden change in demand-supply balance due to a sudden loss of load or generation in their area. The sudden change will be seen instantaneousl...
-
NERC Questions & Answers(RATED A+)
- Exam (elaborations) • 1 pages • 2024
-
Available in package deal
-
- $8.99
- + learn more
What is the calculation used for determining inadvertent interchange? - ANSWER Net actual interchange minus net scheduled interchange 
 
Which of the following would be a suitable use for a pseudo-tie? - ANSWER Accounting for jointly owned generators 
 
Which of the following entities may a Balancing Area provide interchange transaction information to? - ANSWER PSEs involved in the transaction 
 
Which of the following elements are NOT contained in the interchange transaction TAG? - ANSWER Cost ...
-
NERC Transmission Practice Test Questions With Correct Answers
- Exam (elaborations) • 2 pages • 2024
- Available in package deal
-
- $8.99
- + learn more
Which type of relay operates on the premise of comparing the flow in and out of the area of protection? - Answer Differential relay 
 
Underfrequency load shedding is set-up so that which of the following does NOT occur? - Answer Uncontrolled separation 
 
Who is responsible to make sure that the operation of voltage control equipment is coordinated with other impacted entities? - Answer Transmission Operator 
 
The coordination of voltage schedules by system operators would be utilized to reduc...
Fear of missing out? Then don’t!
-
NERC Certification Practice Questions With Correct Answers
- Exam (elaborations) • 1 pages • 2024
- Available in package deal
-
- $7.99
- + learn more
Which of the following represents a virtual tie-line updated in real time? - Answer pseudo-tie 
 
Balancing Areas shall analyze forecasted generation availability and reserve levels, and inform their reliability coordinators of actual or potential generation deficiencies each: - Answer day 
 
Balancing authorities that share jointly owned generation must include their share of the unit governor droop response into their respective frequency bias setting if the energy is scheduled as a: - Answer ...
-
NERC Balancing, Interchange & Transmission Operator Exam Questions With Correct Answers
- Exam (elaborations) • 1 pages • 2024
- Available in package deal
-
- $7.99
- + learn more
If a Balancing Authority cannot comply with the Control Performance or Disturbance Control Standards, it shall implement what remedies to do so? (EOP-002 R6) - Answer Load all available Generating Capacity 
Deploy all Available Operating Reserves 
Interrupt interruptible loads & Exports 
Request emergency assistance from other BA's 
Declare an EE through it's RC 
Reduce load 
 
If a BA cannot comply with CPS and DCS and has implemented all remedies but is still energy deficient what should it ...
-
NERC Certification Exam With 100% Correct Answers 2023/2024
- Exam (elaborations) • 18 pages • 2024
-
- $9.99
- + learn more
NERC Certification Exam With 100% Correct Answers 2023/2024 
 
True/False 
 
According to the NERC Functional Model, there is no difference between the function and the entity. 
 
A) True 
B) False - Correct Answer-B) False 
 
True/False 
 
Analysis type questions are designed to be the least complex from a human cognitive process. 
 
A) True 
B) False - Correct Answer-B) False