SAFe 6.0 - POPM Exam Questions and Answers 100% Pass
319 views 4 purchases
Course
SAFe POPM
Institution
SAFe POPM
SAFe 6.0 - POPM Exam Questions and Answers 100% Pass
According to SAFe, what is recommended first step of Iteration Planning? - Correct
Answer ️️ -Establish Capacity
What is main objective of System Demo in SAFe? - Correct Answer ️️ -Showcase
completed features to stakeholders
The Prod...
Which of the following is NOT a good practice when working with Epics? - Correct
Answer ✔️✔️-Assigning them to a single team
What is the purpose of the ART (Agile Release Train) in SAFe? - Correct Answer ✔️✔️-
To synchronize the activities of multiple Agile teams
What is one outcome of the Iteration Retrospective? - Correct Answer ✔️✔️-Improvement
items in the Team Backlog
What is the primary purpose of PO Sync? - Correct Answer ✔️✔️-To assess progress of
the Program Increment and adjust scope and priorities as needed.
, What is one anti-pattern related to the System Demo? - Correct Answer ✔️✔️-Team
demos are accepted in place of a System Demon to avoid redundancy
With whom does Product Management collaborate to prioritize Enablers? - Correct
Answer ✔️✔️-System Architect
Which SAFe Core Competency centers on applying Lean and systems thinking to
strategy and investment funding decisions? - Correct Answer ✔️✔️-Lean Portfolio
Management
What is one responsibility of the Product Owner? - Correct Answer ✔️✔️-Prioritizing the
Team Backlog
During PI Planning, Agile Teams estimate user stories using story points. What other
estimation technique is commonly used to estimate the size of Features in SAFe? -
Correct Answer ✔️✔️-T-Shirt Sizing
The Release Train Engineer (RTE) works with the Product Manager to - Correct Answer
✔️✔️-All of the propositions
When explaining why the top 10 features were chosen for PI Planning, which SAFe
Core Value is demonstrated? - Correct Answer ✔️✔️-Transparency
Epics are decomposed into what? - Correct Answer ✔️✔️-Features
Which tool shows dependencies during PI Planning? - Correct Answer ✔️✔️-ART
Planning Board
What is one benefit of capacity allocation? - Correct Answer ✔️✔️-It prevents different
types of backlog items from being compared against another.
The benefits of buying summaries with Stuvia:
Guaranteed quality through customer reviews
Stuvia customers have reviewed more than 700,000 summaries. This how you know that you are buying the best documents.
Quick and easy check-out
You can quickly pay through credit card or Stuvia-credit for the summaries. There is no membership needed.
Focus on what matters
Your fellow students write the study notes themselves, which is why the documents are always reliable and up-to-date. This ensures you quickly get to the core!
Frequently asked questions
What do I get when I buy this document?
You get a PDF, available immediately after your purchase. The purchased document is accessible anytime, anywhere and indefinitely through your profile.
Satisfaction guarantee: how does it work?
Our satisfaction guarantee ensures that you always find a study document that suits you well. You fill out a form, and our customer service team takes care of the rest.
Who am I buying these notes from?
Stuvia is a marketplace, so you are not buying this document from us, but from seller EmilyCharlene. Stuvia facilitates payment to the seller.
Will I be stuck with a subscription?
No, you only buy these notes for $12.49. You're not tied to anything after your purchase.