WGU C176 CompTIA Project+ questions with correct answers
- Course
- Institution
Three-point estimate Correct Answer-(most likely estimate + optimistic estimate + pessimistic estimate)/3 = (40 + 24 + 65)/3 = 43 hours formula for SV (schedule variance) Correct Answer-SV = EV - PV project scope documents Correct Answer-product description, key deliverables, success and acce...