General Conditions - answer✔What is not included in the technical specification?
•contract
•specifications
•contract drawings - answer✔Bid documents include?
General Conditions - answer✔Codes, standards, Authority Having Jurisdiction (AHJ), clean-up,
safety requirements, barricades, fencing, insurance and bond requirements, ect.
Supplementary Conditions - answer✔Addendums, time schedules, working days allowed, delay
agreements, payment schedules
Construction Specifications Institute (CSI) - answer✔Specifications typically use what format?
Contractors - answer✔Construction manager concept is when the owner contracts with the
construction manager who oversees ____________ working on the project
Design-Build Concept - answer✔Sometimes referred to as a turn-key type agreement or
contract?
general contractor - answer✔Multiple Prime Contractor Method has the intent is eliminate the
middleman __________ __________.
•architectural/structural contractor
•mechanical contractor
•electrical contractor - answer✔Multiple prime contractor method involve more than one
prime contractor which consist of?
1|Page
, ©THESTAR EXAM SOLUTIONS 2024/2025
ALL RIGHTS RESERVED.
•federal government
•general services administration (GSA)
•large companies - answer✔Who commonly uses the multiple prime contractor method?
Owner, architect, general contractor, subcontractor - answer✔Traditional method contract
uses the typical chain of command which is?
•open bid method
•bid-by invitation procedure
•direct contractor selection - answer✔General contractors can be chosen in a number of
different ways which is?
General category and supplementary conditions - answer✔Contract conditions is divided into
two categories which is?
Addendum - answer✔Changes to the contract or other modifications.
•up-front payments
•progress payments
•lump sum - answer✔Types of payment schedules are?
Bidding requirements, sample forms, conditions of the contract and specifications, including
general conditions and supplementary conditions - answer✔What comprises the project
manual?
•contract itself
•contract conditions
•specifications
•drawings - answer✔Contract documents include:
Preliminary, bid, approval, construction, as-built - answer✔Drawings have different stages
which are?
Request for proposal (RFP) - answer✔Oftentimes a project will begin with a _________.
•certified value specialist
•owner's representatives
•designers and consultants