1. The method of computation of Contractor's overhead and profits for Change Order prices, where both 
additions and deletions are involved, is found in the: 
a) Agreement. 
b) Conditions of the Contract. 
c) Division 01. 
d) Instructions to Bidders. - b) Conditions of the Contract. 
2. General Req...
Preview 3 out of 23 pages
Add to cart1. The method of computation of Contractor's overhead and profits for Change Order prices, where both 
additions and deletions are involved, is found in the: 
a) Agreement. 
b) Conditions of the Contract. 
c) Division 01. 
d) Instructions to Bidders. - b) Conditions of the Contract. 
2. General Req...
The method of computation of Contractor's overhead and profits for Change Order prices, where both 
additions and deletions are involved, is found in the: - conditions of the contract 
General Requirements are part of: - Specifications 
The three essential considerations in the evaluation of a prod...
Preview 2 out of 13 pages
Add to cartThe method of computation of Contractor's overhead and profits for Change Order prices, where both 
additions and deletions are involved, is found in the: - conditions of the contract 
General Requirements are part of: - Specifications 
The three essential considerations in the evaluation of a prod...
2x sold
Select the entity which is generally assigned the following duties and responsibilities by the Conditions of 
the Contract: Protection of job site workers and stored materials. 
A - Architect/Engineer 
B - Owner 
C - Contractor 
D - Varies, as stated in the Supplementary Conditions 
E - None of the ...
Preview 4 out of 65 pages
Add to cartSelect the entity which is generally assigned the following duties and responsibilities by the Conditions of 
the Contract: Protection of job site workers and stored materials. 
A - Architect/Engineer 
B - Owner 
C - Contractor 
D - Varies, as stated in the Supplementary Conditions 
E - None of the ...
Which of these documents, might we find in the Project Manual but they are not contract documents? 
A. The Agreement 
B. Procurement Requirements 
C. Addendum 
D. Supplemental Conditions - B 
Before a model building code can become the building code for a jurisdiction, it has to be adopted by? 
A. A...
Preview 3 out of 17 pages
Add to cartWhich of these documents, might we find in the Project Manual but they are not contract documents? 
A. The Agreement 
B. Procurement Requirements 
C. Addendum 
D. Supplemental Conditions - B 
Before a model building code can become the building code for a jurisdiction, it has to be adopted by? 
A. A...
Stuvia customers have reviewed more than 700,000 summaries. This how you know that you are buying the best documents.
You can quickly pay through credit card or Stuvia-credit for the summaries. There is no membership needed.
Your fellow students write the study notes themselves, which is why the documents are always reliable and up-to-date. This ensures you quickly get to the core!
You get a PDF, available immediately after your purchase. The purchased document is accessible anytime, anywhere and indefinitely through your profile.
Our satisfaction guarantee ensures that you always find a study document that suits you well. You fill out a form, and our customer service team takes care of the rest.
Stuvia is a marketplace, so you are not buying this document from us, but from seller AmazingGrace. Stuvia facilitates payment to the seller.
No, you only buy these notes for $35.49. You're not tied to anything after your purchase.
4.6 stars on Google & Trustpilot (+1000 reviews)
66579 documents were sold in the last 30 days
Founded in 2010, the go-to place to buy study notes for 14 years now