100% satisfaction guarantee Immediately available after payment Both online and in PDF No strings attached
logo-home
Test Bank For Information Technology Project Management, 9th Edition, Kathy Schwalbe $15.49
Add to cart

Exam (elaborations)

Test Bank For Information Technology Project Management, 9th Edition, Kathy Schwalbe

 63 views  2 purchases

Test Bank For Information Technology Project Management, 9th Edition, Kathy Schwalbe/ 35. Which knowledge area involves defining and managing all the work required to complete the project successfully? a. Project resource management b. Project scope management c. Project time management...

[Show more]

Preview 4 out of 305  pages

  • May 19, 2022
  • 305
  • 2024/2025
  • Exam (elaborations)
  • Questions & answers
book image

Book Title:

Author(s):

  • Edition:
  • ISBN:
  • Edition:
All documents for this subject (19)
avatar-seller
Sirih
TEST BANK FOR INFORMATION
TECHNOLOGY PROJECT
MANAGEMENT,
9TH EDITION, KATHY SCHWALBE

, Chapter 1. Introduction to Project Management


True / False


1. Until the 1980s, project management primarily focused on providing schedule and resource data to top management in
the military, computer, and construction industries. a. True
b. False
ANSWER: True
RATIONALE: Feedback: Until the 1980s, project management primarily focused on providing schedule and
resource data to top management in the military, computer, and construction industries.
Today’s project management involves much more, and people in every industry and every
country manage projects.
POINTS: 1
DIFFICULTY: Difficulty: Easy
REFERENCES: p.2
QUESTION TYPE: True / False
HAS VARIABLES: False
LEARNING OBJECTIVES: INFO.SCHW.14.1 - LO: 1-1
NATIONAL STANDARDS: United States - BUSPROG: - Comprehension
TOPICS: Introduction
KEYWORDS: Bloom's: Knowledge
DATE CREATED: 4/27/2018 2:53 PM
DATE MODIFIED: 4/27/2018 2:53 PM



2. A difference between operations and projects is that operations end when their objectives have been reached, whereas
projects do not. a. True
b. False
ANSWER: False
RATIONALE: Feedback: Projects are different from operations in that they end when their objectives have
been reached or the project has been terminated.
POINTS: 1
DIFFICULTY: Difficulty: Moderate
REFERENCES: p.4
QUESTION TYPE: True / False
HAS VARIABLES: False

,LEARNING OBJECTIVES: INFO.SCHW.14.2 - LO: 1-2
NATIONAL STANDARDS: United States - BUSPROG: Analytic
TOPICS: What is a Project?
KEYWORDS: Bloom's: Comprehension
DATE CREATED: 4/27/2018 2:53 PM
DATE MODIFIED: 4/27/2018 2:53 PM



3. Every project should have a well-defined objective.
a. True
b. False
ANSWER: True
RATIONALE: Feedback: A project has a unique purpose. Every project should have a well-defined
objective.
POINTS: 1
DIFFICULTY: Difficulty: Easy
REFERENCES: p.6
QUESTION TYPE: True / False
HAS VARIABLES: False
LEARNING OBJECTIVES: INFO.SCHW.14.2 - LO: 1-2
NATIONAL STANDARDS: United States - BUSPROG: - Comprehension
TOPICS: What is a Project?
KEYWORDS: Bloom's: Knowledge
DATE CREATED: 4/27/2018 2:53 PM
DATE MODIFIED: 4/27/2018 2:53 PM



4. Projects should be developed in increments.
a. True
b. False
ANSWER: True
RATIONALE: Feedback: A project is developed using progressive elaboration. Projects are often defined
broadly when they begin, and as time passes, the specific details of the project become
clearer. Therefore, projects should be developed in increments.
POINTS: 1
DIFFICULTY: Difficulty: Easy
REFERENCES: p.6
QUESTION TYPE: True / False

, HAS VARIABLES: False
LEARNING OBJECTIVES: INFO.SCHW.14.2 - LO: 1-2
NATIONAL STANDARDS: United States - BUSPROG: - Comprehension
TOPICS: What is a Project?
KEYWORDS: Bloom's: Knowledge
DATE CREATED: 4/27/2018 2:53 PM
DATE MODIFIED: 4/27/2018 2:53 PM



5. A project manager’s primary role is to provide the funding for a
project. a. True
b. False
ANSWER: False
RATIONALE: Feedback: A project sponsor usually provides the direction and funding for a project.
POINTS: 1
DIFFICULTY: Difficulty: Easy
REFERENCES: p.7
QUESTION TYPE: True / False
HAS VARIABLES: False
LEARNING OBJECTIVES: INFO.SCHW.14.2 - LO: 1-2
NATIONAL STANDARDS: United States - BUSPROG: - Comprehension
TOPICS: What is a Project?
KEYWORDS: Bloom's: Knowledge
DATE CREATED: 4/27/2018 2:53 PM
DATE MODIFIED: 4/27/2018 2:53 PM



6. One of the main reasons why project management is challenging is
because of the factor of uncertainty. a. True
b. False
ANSWER: True
RATIONALE: Feedback: A project involves uncertainty. Every project is unique and thus it is sometimes
difficult to define its objectives clearly, estimate how long it will take to complete, or
determine how much it will cost. This uncertainty is one of the main reasons project
management is so challenging.
POINTS: 1
DIFFICULTY: Difficulty: Moderate
REFERENCES: p.7

The benefits of buying summaries with Stuvia:

Guaranteed quality through customer reviews

Guaranteed quality through customer reviews

Stuvia customers have reviewed more than 700,000 summaries. This how you know that you are buying the best documents.

Quick and easy check-out

Quick and easy check-out

You can quickly pay through credit card or Stuvia-credit for the summaries. There is no membership needed.

Focus on what matters

Focus on what matters

Your fellow students write the study notes themselves, which is why the documents are always reliable and up-to-date. This ensures you quickly get to the core!

Frequently asked questions

What do I get when I buy this document?

You get a PDF, available immediately after your purchase. The purchased document is accessible anytime, anywhere and indefinitely through your profile.

Satisfaction guarantee: how does it work?

Our satisfaction guarantee ensures that you always find a study document that suits you well. You fill out a form, and our customer service team takes care of the rest.

Who am I buying these notes from?

Stuvia is a marketplace, so you are not buying this document from us, but from seller Sirih. Stuvia facilitates payment to the seller.

Will I be stuck with a subscription?

No, you only buy these notes for $15.49. You're not tied to anything after your purchase.

Can Stuvia be trusted?

4.6 stars on Google & Trustpilot (+1000 reviews)

53920 documents were sold in the last 30 days

Founded in 2010, the go-to place to buy study notes for 14 years now

Start selling
$15.49  2x  sold
  • (0)
Add to cart
Added