WGU C783 PROJECT MANAGEMENT EXAM LATEST COMPLETE 350 QUESTIONS AND DETAILED CORRECT ANSWERS ALREADY GRADED A+

Preview 4 out of 77  pages

  • August 6, 2024
  • 77
  • 2024/2025
  • Exam (elaborations)
  • Questions & answers
  • wgu c783
  • WGU C783 PROJECT MANAGEMENT.
  • WGU C783 PROJECT MANAGEMENT.
avatar-seller
STUVIAGRADES
Page 1 of 77




WGU C783 PROJECT MANAGEMENT EXAM LATEST 2024-
2025 COMPLETE 350 QUESTIONS AND DETAILED CORRECT
ANSWERS ALREADY GRADED A+
WGU C783 Project Management EXAM A

Which element of the scope statement documents the process and criteria you'll use to
determine whether deliverables are complete and satisfactory? - ANSWER-Success criteria,
otherwise known as acceptance criteria.




Name the purpose of the scope management plan. - ANSWER-It documents the procedures for
preparing the project scope statement, in other words, the WBS; defines how the deliverables
will be verified; and describes the process for controlling scope change requests.




Name the four types of project endings. - ANSWER-Starvation, integration, extinction and
addition.




This component of the scope statement documents the deliverables or items that will not be
included in the project. - ANSWER-Exclusions




Before assembling the project team, what needs must the project manager assess first? -
ANSWER-Skills required by team members.




1

,Page 2 of 77


Name the two significant processes you'll perform within the human-resources planning
process. - ANSWER-Organizational planning and staff acquisition




This process is where you'll choose team members or organizations who will work on the
project. - ANSWER-Staff acquisition.




What are the triple constraints according to CompTIA? - ANSWER-Time, cost and quality




Name the major elements of a scope document. - ANSWER-product description, key
deliverables, success and acceptance criteria, key performance indicators, exclusions,
assumptions, and constraints.




Performing this function on key deliverables results in the WBS. - ANSWER-Decomposition




An activity that cannot start until its predecessor has concluded is said to have what type of
logical relationship? - ANSWER-Finish-to-start




Name the estimating technique that bases estimates on past projects of similar size and scope.
- ANSWER-Analogous estimating.




What is the first step in examining a scope deviation request? - ANSWER-Identify the cause.


2

,Page 3 of 77




What is the most often used logical relationship? - ANSWER-Finish-to-start




Three point estimates use which three estimates to calculate the average estimate? - ANSWER-
Most likely, pessimistic, and optimistic




Placing activities into a logical sequence and determining their dependencies is called what? -
ANSWER-Activity sequencing




Describe float. - ANSWER-The difference in the length of time between the early start and late
start or the early finish and late finish of an activity on the project.




What type of scheduling chart represents task duration on a timeline and typically displays
dependencies? - ANSWER-Gantt




Name the two types of schedule formats used on most projects. - ANSWER-Gantt charts and
milestone charts.

Name the steps in validating a project. - ANSWER-Validate the business case, and then identify
and analyze stakeholders.




3

, Page 4 of 77


Name the 9 knowledge areas outlined in the PMBOK Guide. - ANSWER-Scope, time, cost,
quality, human resources, communications, risk, procurement and integration management




Name the steps in validating a business case. - ANSWER-feasibility study, justification, and
alignment to the strategic plan




In which project process group is the project charter document created? - ANSWER-Initiating




Name the project process group that begins when the project charter is approved - ANSWER-
Planning




This system assures the project doesn't deviate from the planned requirements. - ANSWER-
Change control system




Name the term that describes processes that are repeated. - ANSWER-Iterative




What type of requirement describes the elements required for a business process? - ANSWER-
Business requirements




What should come first, the project scope or the project charter? - ANSWER-The project
charter.


4

The benefits of buying summaries with Stuvia:

Guaranteed quality through customer reviews

Guaranteed quality through customer reviews

Stuvia customers have reviewed more than 700,000 summaries. This how you know that you are buying the best documents.

Quick and easy check-out

Quick and easy check-out

You can quickly pay through credit card or Stuvia-credit for the summaries. There is no membership needed.

Focus on what matters

Focus on what matters

Your fellow students write the study notes themselves, which is why the documents are always reliable and up-to-date. This ensures you quickly get to the core!

Frequently asked questions

What do I get when I buy this document?

You get a PDF, available immediately after your purchase. The purchased document is accessible anytime, anywhere and indefinitely through your profile.

Satisfaction guarantee: how does it work?

Our satisfaction guarantee ensures that you always find a study document that suits you well. You fill out a form, and our customer service team takes care of the rest.

Who am I buying these notes from?

Stuvia is a marketplace, so you are not buying this document from us, but from seller STUVIAGRADES. Stuvia facilitates payment to the seller.

Will I be stuck with a subscription?

No, you only buy these notes for $20.99. You're not tied to anything after your purchase.

Can Stuvia be trusted?

4.6 stars on Google & Trustpilot (+1000 reviews)

72349 documents were sold in the last 30 days

Founded in 2010, the go-to place to buy study notes for 14 years now

Start selling
$20.99
  • (0)
  Add to cart