AIC Exam with Detailed Answers. What would be the most appropriate means for the contractor to communicate to the project owner an unforeseen condition not identified in the soils report? A. Document the issue in the job diary B. Issue a jobsite memorandum C. Draft a construction report D. Write a formal business letter - CORRECT ANSWER D When is the best time to distribute the working agenda to the participants of a meeting? A. As a follow-up to the meeting B. At the beginning of the meeting C. About one day after the meeting D. About one day prior to the meeting - CORRECT ANSWER D The contractor has tasked his project engineer with developing an agenda for a preconstruction meeting with the architect and owner. The project engineer has received numerous emails and RFIs from subcontractors and vendors requesting a wide range of information. Which document is most appropriate to distinguish between appropriate topics for the meeting and topics better addressed through other means? A. General conditions B. General requirements C. Technical specifications D. Supplementary conditions - CORRECT ANSWER B What is the best time to distribute the meeting minutes to the participants? A. At the beginning of the meeting B. About one day after the meeting C. About one hour prior to the meeting D. About one day prior to the meeting - CORRECT ANSWER B Which of the following statements is true about the use of texting as a means of communicating in the construction industry? A. A means of easily and effectively documenting communication B. Appropriate for clarifying but not for formal direction C. Should be completely avoided in construction D. Acceptable for communication if specifically allowed in the contract - CORRECT ANSWER B A subcontractor identifies a significant discrepancy between the architectural and structural drawings. The subcontractor immediately meets with the general contractor at their construction trailer to discuss the discrepancy. The general contractor agrees that this could be a significant change depending on which of the drawings describes the designer's intent. Which of the following actions is the most appropriate in this situation? A. Draft a change order proposal and arrange a meeting with the design team and owner to resolve the conflict. B. Draft an RFI that describes the discrepancy in detail and submit it to the architect immediately. C. Send a short text alerting the design team of the issue and discuss the discrepancy in detail at the next meeting. D. Email the engineer of record to collect relevant background information and follow up with a formal RFI to the architect - CORRECT ANSWER B What are the leadership skills needed to conduct a productive meeting? A. Planning, probing questions, responding critically, and decision making B. Planning, timing, coordinating, probing, responding critically, and following up C. Listening attentively, responding constructively, soliciting all ideas, and matching decision making to the situation D. Coordinating, listening selectively, responding critically, soliciting supportive ideas, and adjusting decision making to the situation - CORRECT ANSWER C Which of the following statements made by the indicated parties below would least likely be made at an owner/architect/contractor progress meeting? A. Contractor: "There are 14 unanswered RFIs on the log." B. Superintendent: "A third party inspector will assist the supervision of the roofing installation." C. Owner: "It is very likely, that change order proposal #23 will be accepted." D. Project manager: "The bond rate for ABC subcontractor is 1.45%" - CORRECT ANSWER D What is a listener's retention percentage of an oral conversation? A. 10% B. 50% C. 60% D. 90% - CORRECT ANSWER A Which of the following communication methods is the most effective way to know that the communication has been understood? A. The sender should ask closed-ended questions and tell the receiver twice. B. The sender should ask open-ended questions and make them speak. C. The sender should ask how they feel and their attitude toward the activity. D. The sender should tell them what to do and get them back to work quickly. - CORRECT ANSWER B

Show more Read less
Institution
AIC.
Course
AIC.











Whoops! We can’t load your doc right now. Try again or contact support.

Written for

Institution
AIC.
Course
AIC.

Document information

Uploaded on
December 15, 2024
Number of pages
43
Written in
2024/2025
Type
Exam (elaborations)
Contains
Questions & answers

Subjects

  • aic

Content preview

AIC Exam with Detailed Answers.
What would be the most appropriate means for the contractor to communicate to the project owner an
unforeseen condition not identified in the soils report?

A. Document the issue in the job diary

B. Issue a jobsite memorandum

C. Draft a construction report

D. Write a formal business letter - CORRECT ANSWER D



When is the best time to distribute the working agenda to the participants of a meeting?

A. As a follow-up to the meeting

B. At the beginning of the meeting

C. About one day after the meeting

D. About one day prior to the meeting - CORRECT ANSWER D



The contractor has tasked his project engineer with developing an agenda for a preconstruction meeting
with the architect and owner. The project engineer has received numerous emails and RFIs from
subcontractors and vendors requesting a wide range of information. Which document is most
appropriate to distinguish between appropriate topics for the meeting and topics better addressed
through other means?

A. General conditions

B. General requirements

C. Technical specifications

D. Supplementary conditions - CORRECT ANSWER B



What is the best time to distribute the meeting minutes to the participants?

A. At the beginning of the meeting

B. About one day after the meeting

C. About one hour prior to the meeting

D. About one day prior to the meeting - CORRECT ANSWER B

,Which of the following statements is true about the use of texting as a means of communicating in the
construction industry?

A. A means of easily and effectively documenting communication

B. Appropriate for clarifying but not for formal direction

C. Should be completely avoided in construction

D. Acceptable for communication if specifically allowed in the contract - CORRECT ANSWER B



A subcontractor identifies a significant discrepancy between the architectural and structural drawings.
The subcontractor immediately meets with the general contractor at their construction trailer to discuss
the discrepancy. The general contractor agrees that this could be a significant change depending on
which of the drawings describes the designer's intent. Which of the following actions is the most
appropriate in this situation?

A. Draft a change order proposal and arrange a meeting with the design team and owner to resolve the
conflict.

B. Draft an RFI that describes the discrepancy in detail and submit it to the architect immediately.

C. Send a short text alerting the design team of the issue and discuss the discrepancy in detail at the
next meeting.

D. Email the engineer of record to collect relevant background information and follow up with a formal
RFI to the architect - CORRECT ANSWER B



What are the leadership skills needed to conduct a productive meeting?

A. Planning, probing questions, responding critically, and decision making

B. Planning, timing, coordinating, probing, responding critically, and following up

C. Listening attentively, responding constructively, soliciting all ideas, and matching decision making to
the situation

D. Coordinating, listening selectively, responding critically, soliciting supportive ideas, and adjusting
decision making to the situation - CORRECT ANSWER C



Which of the following statements made by the indicated parties below would least likely be made at an
owner/architect/contractor progress meeting?

A. Contractor: "There are 14 unanswered RFIs on the log."

B. Superintendent: "A third party inspector will assist the supervision of the roofing installation."

,C. Owner: "It is very likely, that change order proposal #23 will be accepted."

D. Project manager: "The bond rate for ABC subcontractor is 1.45%" - CORRECT ANSWER D



What is a listener's retention percentage of an oral conversation?

A. 10%

B. 50%

C. 60%

D. 90% - CORRECT ANSWER A



Which of the following communication methods is the most effective way to know that the
communication has been understood?

A. The sender should ask closed-ended questions and tell the receiver twice.

B. The sender should ask open-ended questions and make them speak.

C. The sender should ask how they feel and their attitude toward the activity.

D. The sender should tell them what to do and get them back to work quickly. - CORRECT ANSWER B



Which of the following is the best example of an open-ended question?

A. Do you understand what work is supposed to be completed?

B. Do you know which shovel to get me from the tool shed?

C. What steps are you going to take to complete the activity?

D. How do you feel about completing the activities assigned? - CORRECT ANSWER C



Which of the following statements about the following organizations and their justifications of its use is
most appropriate when designers develop project specifications?

A. Organize building materials by International Building Code chapters to facilitate inspections by the
authority having jurisdiction. B. Only use materials tested by Underwriters Laboratories to ensure the
highest quality and lowest flame spread rating.

C. Use the Construction Specification Institute's organizational system for categorizing construction
materials into divisions and sections as it is widely used by the industry.

D. Use products endorsed by the American Society for Testing Materials to prevent the likelihood of
structural failure. - CORRECT ANSWER C

, An HVAC technician is inspecting an outside condensing unit of an air source heat pump in the summer.
The unit is energized and appears to be operating normally. One of the refrigerant lines is cool to the
touch and insulated. Which of the following statements is most likely true about this refrigerant line and
the phase of the refrigerant in it?

A. It is a suction line and the refrigerant is a gas at a relatively low pressure

B. It is a suction line and the refrigerant is a liquid at a relatively high pressure

C. It is a liquid line and the refrigerant is a liquid at a relatively high pressure

D. It is a condensate line and the refrigerant is a gas at a relatively high pressure - CORRECT ANSWER A



Which statement most accurately describes how a 3-phase, 120/208V load would be wired?

A. One hot, one neutral and one ground conductor

B. Two hot and one neutral conductor

C. Three hot and one neutral conductor

D. Three hot conductors - CORRECT ANSWER C



Which fire protection system would be most appropriate for an unconditioned warehouse located in
Chicago if the warehouse contains materials such as paper, wood and other type A combustibles?

A. Wet pipe system

B. Dry pipe system

C. Deluge system

D. Clean agent system - CORRECT ANSWER B



The owner wants to fast-track a construction project. Which project delivery system best supports this
process?

A. Partnering

B. Design-bid-build

C. CM agency

D. Design-build - CORRECT ANSWER D

Get to know the seller

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
ROSEGRADES Nursing
View profile
Follow You need to be logged in order to follow users or courses
Sold
214
Member since
2 year
Number of followers
87
Documents
12160
Last sold
3 weeks ago
TOPGRADE

I HELP STUDENTS WITH REVISION MATERIALS WITH BETTER GRADES GUARANTEED. BEST OF LUCK.

3.4

30 reviews

5
10
4
3
3
11
2
2
1
4

Recently viewed by you

Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Frequently asked questions