100% satisfaction guarantee Immediately available after payment Both online and in PDF No strings attached 4.6 TrustPilot
logo-home
Exam (elaborations)

CDFM Module 4 New Update 2025/2026) ||Questions and Verified Answers 100% Correct| Grade A||Latest

Rating
-
Sold
-
Pages
11
Grade
A+
Uploaded on
21-02-2025
Written in
2024/2025

CDFM Module 4 New Update 2025/2026) ||Questions and Verified Answers 100% Correct| Grade A||Latest

Institution
CDFM
Course
CDFM









Whoops! We can’t load your doc right now. Try again or contact support.

Written for

Institution
CDFM
Course
CDFM

Document information

Uploaded on
February 21, 2025
Number of pages
11
Written in
2024/2025
Type
Exam (elaborations)
Contains
Questions & answers

Subjects

  • cdfm

Content preview

CDFM Module 4

10 USC 2435 - ANS-Where we get the statutory authority to do stuff. It says the DoD won't
obligate funds for an MDAP after the program enters System Development and
Demonstration with out a Milestone Decision Authority-authorized baseline except the
USD(AT&L) specifically approves the duty. Four.1.19
2 Categories of Cost - ANS-Lifecycle and Total Ownership 4.3.7
2 Kinds of Performance Indices - ANS-Cost Performance and Schedule Performance 4.3.48
2 varieties of Unit Cost Reports - ANS-Significant Cost Growth Notification and Critical Cost
Breach Certification
-Significant is while APUC or PAUC exceeds 15% of CURRENT APB or 30% of ORIGINAL
APB
-Critical is when APUC or PAUC exceeds 25% of CURRENT APB or 50% of ORIGINAL APB
four.Nine.25
three Levels of Integrated Product Teams - ANS-1. Overarching Integrated Product Team
(OIPT)
2. Integrating Integrated Product Team (IIPT)
three. Working Level Integrated Product Team (WIPT) four.2.7
three Steps inside the Performance Measurement Baseline (PMB) Development - ANS-1.
Outline the work scope and damage it into manageable paintings packages
2. Decide the undertaking relationships most of the paintings programs and agenda the work
programs into a logical community
three. Classify the work, allocate the finances, and time segment the manipulate account
paintings package budgets four.3.44
3 terms related to realignment of the PMB (Performance Measurement Baseline) - ANS-1.
Rebaselining - Improves the correlation among the paintings plan and the baseline finances.
Consists of Replanning and Reprogramming.
2. Replanning - realignment of time table or reallocation of finances for last attempt WITHIN
the present constraints of the agreement.
Three. Reprogramming - realignment of the remaining performance size baseline that
consequences in a complete price range or time table that EXCEEDS the agreement.
Four.3.Forty six
four Major Technical and Engineering Reviews at some point of the acquisition method -
ANS--Materiel Development Review inside the Materiel Solution Analysis Phase
-Preliminary Design Review inside the Engineering & Manufacturing Development Phase
-Critical Design Review in the Engineering & Manufacturing Development Phase
-Full Rate Production Review inside the Production and Deployment Phase four.Nine.6
ACAT I"D" and IA"M" Programs - ANS-These packages can have an OIPT to offer
assistance and oversight. An appropriate legit inside OSD, i.E., Director, Defense Systems
or the Deputy to the ASD(NII) for IT acquisitions, will lead the OIPT. 4.9.13
Acquisition - ANS-This is one of the Life Cycle Sustainment activities. The device formally
enters this process at Milestone B, whilst Milestone Decision Authority approval lets in the
device to enter the Engineering and Manufacturing Development (EMD) Phase. A key

, Life-Cycle Sustainment emphasis all through EMD is to ensure operational supportability
with precise interest to minimizing the logistics
footprint. 4.4.7
Acquisition Category I and IA (Automated Information Systems) - ANS-These and different
excessive-hobby applications' JCIDS are reviewed and established by using JROC previous
to Milestone A.
Acquisition of Services - ANS-The acquisition of offerings does now not observe the materiel
systems phases, but has five elements that have to be addressed. The 5th detail is
Clinger-Cohen Act Compliance. Four.10.25
Acquisition Strategy - ANS-Guides the acquisition segment and is made out of 21 subjects.
Either evolutionary or unmarried object - evolutionary desired. Single step is whilst you make
a determination as to what you need, you then purchase it (ex: rifles) 4.1.15
Actual Costs and Engineering Cost Estimates - ANS-Detailed fee estimating strategies used
later in the existence of the purchase system. Four.Three.27
ACWP (Actual Cost of Work Performed) - ANS-the fee incurred and recorded for
performance measurement functions inside a given time period and is without a doubt the
real fee. Four.Three.40
Affordability Assessment - ANS-For foremost protection acquisition applications and major
automatic information system programs, those exams are required at Milestones B and C.
Their cause is for the DoD Component to illustrate that this system's projected funding and
manpower requirements are practical and viable. The evaluation typically need to be
performed by using useful resource analysts in the DoD Component headquarters or
assisting company. 4.3.2
Agility - ANS-A key function of a internet-centric surroundings. How a whole lot records and
the way rapid. 4.6.8
Analysis of Alternatives (AoA) - ANS-Required at primary milestone choice factors and at the
overall-rate production choice (or their equivalents). It's used to evaluate the capacity
material solutions to fulfill the functionality needs inside the authorized Initial Capabilities
Document. Four.Three.Sixteen
Apportioned Effort EV Technique - ANS-This is an EV technique as well as a piece bundle
category. An apportioned attempt work task is normally a help undertaking or body of
workers characteristic which can be tied to a discrete undertaking or set of duties. For
instance, a best guarantee that inspects a statistical pattern of a finished product. 4.3.42
APUC (Acquisition Procurement Unit Cost) versus PAUC (Program Acquisition Unit Cost) -
ANS--APUC includes flyaway expenses, assist items, and initial spares (Procurement-best
budget, not RTD&E, MILCON, or O&M). -PAUC consists of RTD&E, Procurement, and
MILCON (now not O&M) four.3.10
Assurance - ANS-A key characteristic of a internet-centric surroundings. Achieving predicted
stages of operational and structures overall performance inside a certain context.
Four.6.Eight
At Milestone Decision Point A - ANS-The MDA opinions the proposed Technology
Development Strategy (TDS)
At Milestone Decision Point B - ANS-Technology Readiness Assessments are reviewed.
Four.9.Three
BCWP (Budgeted Cost of Work Performed) - ANS-Also called Earned Value. The price of all
work definitely executed in a given time period and represents the completion of labor.
4.3.40

Get to know the seller

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
Purity96 Howard County Community College
View profile
Follow You need to be logged in order to follow users or courses
Sold
79
Member since
2 year
Number of followers
20
Documents
1140
Last sold
1 month ago

Welcome to Purity96 ! The place to find the best study materials for various subjects. You can be assured that you will receive only the best which will help you to ace your exams. All the materials posted are A+ Graded. Please rate and write a review after using my materials. Your reviews will motivate me to add more materials. Thank you very much!

3.1

11 reviews

5
4
4
0
3
3
2
1
1
3

Recently viewed by you

Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Frequently asked questions