CON 237
Liberty University
Page 4 out of 45 results
Sort by
-
CON 237 Simplified Acquisition Procedures Exam Questions and Answers Latest 2023 - 2024 [100% correct answers]
- Exam (elaborations) • 7 pages • 2023
-
- $8.99
- + learn more
CON 237 Simplified Acquisition Procedures Exam Questions and Answers Latest 2023 - 2024 [100% correct answers]
-
CON 237 DAU Questions and Answers Latest 2023 - 2024 [100% correct answers]
- Exam (elaborations) • 22 pages • 2023
-
- $8.99
- + learn more
CON 237 DAU Questions and Answers Latest 2023 - 2024 [100% correct answers]
-
CON 237 DAU QUESTIONS AND ANSWERS 100% CORRECT
- Exam (elaborations) • 4 pages • 2023
-
- $8.49
- + learn more
A public announcement by publishing a synopsis in the GPE is normally required for: correct answer: Acquisitions expected to exceed $25,000 By soliciting two sources under SAP, you have satisfied the requirement to obtain competition to the maximum extent possible. correct answer: False
-
CON 237 DAU QUESTIONS AND ANSWERS 100% CORRECT
- Exam (elaborations) • 4 pages • 2023
-
- $8.39
- + learn more
A public announcement by publishing a synopsis in the GPE is normally required for: correct answer: Acquisitions expected to exceed $25,000 By soliciting two sources under SAP, you have satisfied the requirement to obtain competition to the maximum extent possible. correct answer: False
-
CON 237 DAU QUESTIONS AND ANSWERS 100% CORRECT
- Exam (elaborations) • 4 pages • 2023
-
- $8.49
- + learn more
A public announcement by publishing a synopsis in the GPE is normally required for: correct answer: Acquisitions expected to exceed $25,000 By soliciting two sources under SAP, you have satisfied the requirement to obtain competition to the maximum extent possible. correct answer: False
Fear of missing out? Then don’t!
-
CON 237 QUIZ 71 QUESTIONS WITH COMPLETE SOLUTIONS
- Exam (elaborations) • 6 pages • 2023
- Available in package deal
-
- $8.49
- + learn more
1) What required source has priority for services? correct answer: Services which are on the Procurement List maintained by the Committee for Purchase From People Who Are Blind or Severely Disabled. 
 
2) The contracting officer can terminate a commercial purchase order for cause correct answer: All choices are correct. 
 
3) When no other exceptions apply, is a Government Point of Entry (GPE) synopsis required for purchases estimated to exceed $25,000 but not to exceed the simplified acquisit...
-
CON 237 DAU QUESTIONS AND ANSWERS 100% CORRECT
- Exam (elaborations) • 3 pages • 2023
- Available in package deal
-
- $8.99
- 7x sold
- + learn more
A public announcement by publishing a synopsis in the GPE is normally required for: correct answer: Acquisitions expected to exceed $25,000 
 
By soliciting two sources under SAP, you have satisfied the requirement to obtain competition to the maximum extent possible. correct answer: False 
 
The preferred type of item to satisfy agency needs: correct answer: Commercial item 
 
When should electronic commerce be used as a method of solicitation? correct answer: Whenever cost-effective and pr...
-
CON 237 QUIZ| 71 QUESTIONS| WITH COMPLETE SOLUTIONS
- Exam (elaborations) • 7 pages • 2023
- Available in package deal
-
- $10.49
- + learn more
1) What required source has priority for services? correct answer: Services which are on the Procurement List maintained by the Committee for Purchase From People Who Are Blind or Severely Disabled. 
 
2) The contracting officer can terminate a commercial purchase order for cause correct answer: All choices are correct. 
 
3) When no other exceptions apply, is a Government Point of Entry (GPE) synopsis required for purchases estimated to exceed $25,000 but not to exceed the simplified acquisit...
-
CON 237 Simplified Acquisition Procedures
- Exam (elaborations) • 2 pages • 2023
- Available in package deal
-
- $7.99
- + learn more
When buying a commercial item, an in-process inspection of the product need not be consistent with commercial practice correct answer: false 
 
Implied warranty of fitness for a particular purpose means that an item is correct answer: fit for use for the particular purpose for which the government will use the item 
 
The contracting officer can terminate a commercial purchase order for cause correct answer: all choices are correct 
 
Which of the following is not an acceptable technique for ...
-
CON 237 Simplified Acquisition Procedures QUESTIONS WITH COMPLETE SOLUTIONS
- Exam (elaborations) • 3 pages • 2023
- Available in package deal
-
- $10.49
- + learn more
You have a request to purchase 1,500 commercially available sheds, one for each family housing unit. Each shed will cost $1,500 (total of $2.25 million). correct answer: ? Choose from the remaining answers below: 
-Simplified acquisition procedures can be used ONLY if the contracting officer requests a request for proposals (RFP). 
-Simplified acquisition procedures can be used. 
 
What is the preferred method of solicitation for requirements over $25,000? correct answer: ? I answered Written ...