CM 4100 Assignments Questions And Answers 2024 (Pass!)
  • CM 4100 Assignments Questions And Answers 2024 (Pass!)

  • Exam (elaborations) • 11 pages • 2024
  • CM 4100 Assignments Questions And Answers 2024 (Pass!) A significant difference between "planning" and "scheduling" is, Select one: Scheduling determines what is going to be done, and planning determines how to do. Scheduling determines how to do, and planning determines what to do. Scheduling determines when to do, and planning determines what to do, how to do and by whom. - ANS-Scheduling determines when to do, and planning determines what to do, how to do and by whom. What is not...
    (0)
  • $14.49
  • + learn more
CM 4101 Final Exam | With 100% Correct Answers, Graded A
  • CM 4101 Final Exam | With 100% Correct Answers, Graded A

  • Exam (elaborations) • 7 pages • 2024
  • CM 4101 Final Exam | With 100% Correct Answers, Graded A During which of the following process, questions such as what activities should be scheduled are typically asked and answered? a. Planning b. Scheduling c. Control Using traditional bar charts, it is always easy to tell the logic relationships between activities. a. True b. False An event consumes a. Resources b. Time c. Both Resources and Time d. Neither resources nor time Which of the following is correct regarding CPM and PERT? a. The...
    (0)
  • $15.99
  • + learn more
CM 4101 final Exam Questions Solved 100% Correct
  • CM 4101 final Exam Questions Solved 100% Correct

  • Exam (elaborations) • 14 pages • 2024
  • Available in package deal
  • work breakdown structure - Answer a _______ provides a framework for breaking a project down into successively greater detail by level and organizing activities that make up a project sequencing, scheduling - Answer a WBS organizes the work of a project but does not address the _____ and the _____ of project activities
    (0)
  • $12.99
  • + learn more
CM 4101 final Exam Questions Solved 100% Correct
  • CM 4101 final Exam Questions Solved 100% Correct

  • Exam (elaborations) • 13 pages • 2024
  • Available in package deal
  • What is not true about classic bar charts? a. Bar charts use a time-scaled presentation b. Bar charts often directly show resource consumption of each activity c. Bar charts can show the relative of each activity d. Bar charts cannot show the actual status of a project - Answer b. Bar charts often directly show resource consumption of each activity c. Bar charts can show the relative of each activity
    (0)
  • $12.99
  • + learn more
LSU CM 4100 Construction Scheduling and Cost Control quiz 5 Louisiana State University
  • LSU CM 4100 Construction Scheduling and Cost Control quiz 5 Louisiana State University

  • Exam (elaborations) • 5 pages • 2024
  • Available in package deal
  • LSU CM 4100 Construction Scheduling and Cost Control quiz 5 Louisiana State University
    (1)
  • $11.99
  • + learn more
CM 4100 Assignments Questions Solved 100% Correct
  • CM 4100 Assignments Questions Solved 100% Correct

  • Exam (elaborations) • 12 pages • 2024
  • Available in package deal
  • The conditions of limited resource availability dictate certain activities cannot be performed simultaneously. This is, Select one: a. Physical constraints b. Resource constraints c. Safety constraints d. Contractual constraints - Answer Resource constraints
    (0)
  • $12.74
  • + learn more
LSU CM 4100 Construction Scheduling and Cost Control final exam questions and answers 2024-2025 Louisiana State University
  • LSU CM 4100 Construction Scheduling and Cost Control final exam questions and answers 2024-2025 Louisiana State University

  • Exam (elaborations) • 13 pages • 2024
  • Available in package deal
  • LSU CM 4100 Construction Scheduling and Cost Control final exam questions and answers Louisiana State University
    (1)
  • $12.49
  • + learn more
CM 4100 Assignments with Questions and Answers 100% Correct
  • CM 4100 Assignments with Questions and Answers 100% Correct

  • Exam (elaborations) • 7 pages • 2024
  • CM 4100 Assignments with Questions and Answers 100% Correct A precedence diagram uses nodes to represent Select one: a. Activities b. Activity links c. Resources d. Time - CORRECT ANSWER-Activities A significant difference between "planning" and "scheduling" is, Select one: Scheduling determines what is going to be done, and planning determines how to do. Scheduling determines how to do, and planning determines what to do. Scheduling determines when to do, and planning determines ...
    (0)
  • $14.99
  • + learn more
CM 410 Final Exam Questions & Answers 100% Correct
  • CM 410 Final Exam Questions & Answers 100% Correct

  • Exam (elaborations) • 8 pages • 2024
  • 5 types of bonds* - ANSWERBid bond Performance bond Payment bond Warranty bond Green bond *A101* - ANSWERLUMP sum contract *A111* - ANSWERCOST OF THE WORK PLUS FEE *A121 CMc* - ANSWERCM @ Risk *A131 CMc* - ANSWERCM @ Management A141 - ANSWERDesign-build *A201* - ANSWERGeneral Conditions A401 - ANSWERAgreement between contractor and sub All Risk Insurance - ANSWERInsurance that covers loss caused by all perils except those specifically excluded in the contract. Cover...
    (0)
  • $11.99
  • + learn more
Study set for CM 4101 Final Exam Review Questions and Answers 2024/2025
  • Study set for CM 4101 Final Exam Review Questions and Answers 2024/2025

  • Exam (elaborations) • 8 pages • 2024
  • Study set for CM 4101 Final Exam Review Questions and Answers 2024/2025 Construction Planning - CORRECT ANSWER-The process of determining how a project will be carried out. Planning answers questions: who? what? where?, and how? Construction Scheduling - CORRECT ANSWER-Process to determine when activities need to be started and completed. Answers the question: when? Project Control - CORRECT ANSWER-Is an active process to monitor and update the construction plan and the schedule. Monitorin...
    (0)