Work Breakdown Structure as a Skeleton for Integration- Case Project Management Case Studies in Project, Program, and Organizational Project Management, ISBN: 97811181742965,26 €
Ajouter au panier
Work Breakdown Structure as a Skeleton for Integration- Case Project Management Case Studies in Project, Program, and Organizational Project Management, ISBN: 9781118174296
56 vues 1 fois vendu
Cours
Project Management
Établissement
Far Eastern University
Book
Case Studies in Project, Program, and Organizational Project Management
This note includes my personal answer to cases in the book mentioned below:
Milosevic, D. Z., Patanakul, P., & Srivannaboon, S. (2010). Case Studies in Project, Program, and Organizational Project Management. John Wiley and Sons Inc.
work breakdown structure as a skeleton for integrati
Livre connecté
Titre de l’ouvrage:
Auteur(s):
Édition:
ISBN:
Édition:
Plus de résumés pour
AtlasCom Case- Case Project Management Case Studies in Project, Program, and Organizational Project Management, ISBN: 9781118174296
Bad Metrics for Earned Value- Case Project Management Case Studies in Project, Program, and Organizational Project Management, ISBN: 9781118174296
Rapid Prototype for Fast Profits- Case Project Management Case Studies in Project, Program, and Organizational Project Management, ISBN: 9781118174296
Tout pour ce livre (12)
École, étude et sujet
Far Eastern University
Project Management
Tous les documents sur ce sujet (12)
Vendeur
S'abonner
GelC
Avis reçus
Aperçu du contenu
CASE STUDIES IN PROJECT MANAGEMENT SYSTEMS 1
Work Breakdown Structure as a Skeleton for Integration
Wilson Clark and Dragan Z. Milosevic
I. PROBLEM AND SOLUTION
Problem: The WBS created was inefficient since it overlapped with the other commitments of the
engineers.
Solution: Create an efficient WBS and proceed with other project requirements whereas the
construction of the WBS would be validated with major parties of the project to avoid concerns
that might arise if they failed to do so.
I. EXECUTIVE SUMMARY
The engineering manager of the Opto - Mechanical Group and the project manager of Lada
had a meeting regarding the unproductive WBS that was created. This was due to the inability of
the project manager of Lada to consider the other priorities of the engineers from the Opto-
Mechanical Group. As a result, it overlapped with the other projects that those engineers needs to
work on. Also, it was raised in the meeting about the possibility that the project manager was trying
to micromanage the Opto-Mechanical Group since the project manager interfered with their
activities on deliverables. To resolve the issue, the creation of an accurate WBS was suggested.
Whereas it would be validated with major parties of the project to avoid concerns like overlapping
with projects with higher priorities.
II. BRIEF HISTORY
Matt Boon is the engineering manager of the Opto - Mechanical Group, while Percy Bedge
is the project manager of Lada. They were having a meeting regarding the work breakdown
structure that Percy created for the well-timed termination of the Opto - Mechanical group’s
portion of work for Project Lada. During their conversation, they didn’t show much cooperation
which lead to an atmosphere of conflict and pressure between them. Meanwhile, as Matt discussed
the work of Percy, he stated that the WBS created by Percy was wrong since Percy assumed that
Matt’s engineers would be involved in one project only which was the Project Lada when in fact,
the engineers would be shared among six projects. Also, Percy scheduled them in a certain period
that overlapped with many prioritized projects. Matt was indeed unpleased with the planning of
Percy. Moreover, he raised the issue regarding the ownership issue which he thought was
concluded already. They were supposed to be the one’s planning, executing, and controlling the
activities on their deliverables that’s why he was mad with Percy meddling with their activities.
Nevertheless, Matt voiced out to Percy that it looked like he was trying to micromanage them
again since Percy ignored the Project Manager’s charter of the company. To define it,
micromanagement1 is a management style whereby a manager closely observes or controls the
work of subordinates or employees. Micromanagement generally has a negative connotation since
this results in (1) Loss of control; (2) Loss of trust; (3) Dependent employees; (4) Your burnout;
(5) High turnover of staff; (6) Lack of autonomy.
Les avantages d'acheter des résumés chez Stuvia:
Qualité garantie par les avis des clients
Les clients de Stuvia ont évalués plus de 700 000 résumés. C'est comme ça que vous savez que vous achetez les meilleurs documents.
L’achat facile et rapide
Vous pouvez payer rapidement avec iDeal, carte de crédit ou Stuvia-crédit pour les résumés. Il n'y a pas d'adhésion nécessaire.
Focus sur l’essentiel
Vos camarades écrivent eux-mêmes les notes d’étude, c’est pourquoi les documents sont toujours fiables et à jour. Cela garantit que vous arrivez rapidement au coeur du matériel.
Foire aux questions
Qu'est-ce que j'obtiens en achetant ce document ?
Vous obtenez un PDF, disponible immédiatement après votre achat. Le document acheté est accessible à tout moment, n'importe où et indéfiniment via votre profil.
Garantie de remboursement : comment ça marche ?
Notre garantie de satisfaction garantit que vous trouverez toujours un document d'étude qui vous convient. Vous remplissez un formulaire et notre équipe du service client s'occupe du reste.
Auprès de qui est-ce que j'achète ce résumé ?
Stuvia est une place de marché. Alors, vous n'achetez donc pas ce document chez nous, mais auprès du vendeur GelC. Stuvia facilite les paiements au vendeur.
Est-ce que j'aurai un abonnement?
Non, vous n'achetez ce résumé que pour 5,26 €. Vous n'êtes lié à rien après votre achat.