COSC 475 Select all correct answers. What are the the essential skills for critical thinking - logical analysis - creative thinking - decision making - control calculation - Answer- - logical analysis - creative thinking - decision making what are the 4 level of scheduling - Answer- 1...

[Montrer plus]

Aperçu 2 sur 8  pages

  • 25 août 2024
  • 8
  • 2024/2025
  • Examen
  • Questions et réponses
  • COSC 475
  • COSC 475
avatar-seller
COSC 475
Select all correct answers. What are the the essential skills for critical thinking

- logical analysis
- creative thinking
- decision making
- control calculation - Answer- - logical analysis
- creative thinking
- decision making

what are the 4 level of scheduling - Answer- 1. proposal
2. pre-construction
3. construction
4. look ahead

what level fits best with this image
- level 1 - Answer- - summarize overall project
- start & finish dates for major phases & key milestones

what level fits best with this image: level 2 - Answer- - preconstruction
- starts to focus on the primary activities and task by trade, looks at critical
components

what level fits best with this image : level 3 - Answer- - critical path

in this course, a critical path method is utilized, and will have a start and finish dates
and links for all activities. also called - Answer- level 3

in this course for level 3 construction the duration is set to - Answer- not be longer
than 10 days

Activities are represented daily and often called a three or four week "___" ecasue it
has weekly input from all trades - Answer- look-ahead

T/F: tasks can be in any phase of the project or any schedule level - Answer- True

Generally tasks can be in any phase of the project, to define a tasks two factors are
required - Answer- task-dependent, resource-dependent

a zero duration on the project that are important to watch - Answer- milestones

a task with fixed dates and duration, should not have predecessors or successors -
Answer- deadlines/constraints

what are the five keys to successful teams? - Answer- - established roles and
responsibilities
- defined goals and objectives

, - know the system in which you are working
- identify problems and barriers
- know your people

how can quantity of work be examined - Answer- SF, LF, EA, CY

define the term
- the average efficiency of a standard crew in a task - Answer- production rate

weather, congested space, area layout, material handling, crew expertise, safety
requirements, complexity are all factors for ___ - Answer- productivity

work hours = - Answer- quantity of work/production rate

adjusted work hours = - Answer- work hours x productivity factor

activity duration = - Answer- adjusted work hours / hours per workday

gantt charts - Answer- bars show the relationship between tasks

T/F: Testing assumption is key in the logical analysis phase of critical thinking -
Answer- TRUE

in project management describe activitiesthat depend upon one another to proceed.
These dependencies amongactivities will determine the order in which the project
plan proceeds.Predecessors in project management are activities that must begin
orend before a successor task can proceed. - Answer- predecessors and successors

which scheduling relationship types do we use in this class? - Answer- Finish to
Start,
Start to Start, Finish to Finish

which scheduling link extends duration without any critical paths? - Answer- float

which scheduling link has two activities that have delay but it not careful could
become critical - Answer- lags

which scheduling link used level 3 scheduling where you put a specific date for that
activity to start of finish, if not it is considered a delay - Answer- constraints

SS, FF, FS are also called - Answer- logic relationship

the amount of time required to complete a task in work days - Answer- duration

activities with no float connected to determine the amount of time to complete the
project - Answer- critical path

float is called - Answer- free float, total float

which software calls the schedule level tasks - Answer- MP

Les avantages d'acheter des résumés chez Stuvia:

Qualité garantie par les avis des clients

Qualité garantie par les avis des clients

Les clients de Stuvia ont évalués plus de 700 000 résumés. C'est comme ça que vous savez que vous achetez les meilleurs documents.

L’achat facile et rapide

L’achat facile et rapide

Vous pouvez payer rapidement avec iDeal, carte de crédit ou Stuvia-crédit pour les résumés. Il n'y a pas d'adhésion nécessaire.

Focus sur l’essentiel

Focus sur l’essentiel

Vos camarades écrivent eux-mêmes les notes d’étude, c’est pourquoi les documents sont toujours fiables et à jour. Cela garantit que vous arrivez rapidement au coeur du matériel.

Foire aux questions

Qu'est-ce que j'obtiens en achetant ce document ?

Vous obtenez un PDF, disponible immédiatement après votre achat. Le document acheté est accessible à tout moment, n'importe où et indéfiniment via votre profil.

Garantie de remboursement : comment ça marche ?

Notre garantie de satisfaction garantit que vous trouverez toujours un document d'étude qui vous convient. Vous remplissez un formulaire et notre équipe du service client s'occupe du reste.

Auprès de qui est-ce que j'achète ce résumé ?

Stuvia est une place de marché. Alors, vous n'achetez donc pas ce document chez nous, mais auprès du vendeur Freshy. Stuvia facilite les paiements au vendeur.

Est-ce que j'aurai un abonnement?

Non, vous n'achetez ce résumé que pour 9,99 €. Vous n'êtes lié à rien après votre achat.

Peut-on faire confiance à Stuvia ?

4.6 étoiles sur Google & Trustpilot (+1000 avis)

84669 résumés ont été vendus ces 30 derniers jours

Fondée en 2010, la référence pour acheter des résumés depuis déjà 14 ans

Commencez à vendre!
9,99 €  1x  vendu
  • (0)
  Ajouter