Which attribute most accurately describes a project? - The correct answer is:
| | | | | | | | | | |
Projects are finite.
| | |
What is an example of how project managers apply sound management
| | | | | | | | | |
techniques? - The correct answer is: they break down a task further if it
| | | | | | | | | | | | | |
remains at the same percent completion despite reported progress.
| | | | | | | | |
Which is an advantage of using a standardized project management model? -
| | | | | | | | | | |
The correct answer is: The model is a framework that project managers can
| | | | | | | | | | | | |
adapt to project specifics.
| | | |
In the project model, what do outputs from the Plan phase become? - The
| | | | | | | | | | | | |
|correct answer is: inputs to the Execute phase.
| | | | | | |
A project will have a long payback period. What should the project be linked to
| | | | | | | | | | | | | |
thus increasing the chances the project will be approved? - The correct answer
| | | | | | | | | | | | |
is: Strategic facility plans
| | | |
Which activity is set by policy at the start of a project? - The correct answer is:
| | | | | | | | | | | | | | | |
Estimating
|
What should a facility manager do at the beginning of a routine project to
| | | | | | | | | | | | |
achieve success? - The correct answer is: generate a shared understanding of
| | | | | | | | | | | |
the end purpose of a project.
| | | | | |
| | | | | | | | | | |
Projects are finite.
| | |
What is an example of how project managers apply sound management
| | | | | | | | | |
techniques? - The correct answer is: they break down a task further if it
| | | | | | | | | | | | | |
remains at the same percent completion despite reported progress.
| | | | | | | | |
Which is an advantage of using a standardized project management model? -
| | | | | | | | | | |
The correct answer is: The model is a framework that project managers can
| | | | | | | | | | | | |
adapt to project specifics.
| | | |
In the project model, what do outputs from the Plan phase become? - The
| | | | | | | | | | | | |
|correct answer is: inputs to the Execute phase.
| | | | | | |
A project will have a long payback period. What should the project be linked to
| | | | | | | | | | | | | |
thus increasing the chances the project will be approved? - The correct answer
| | | | | | | | | | | | |
is: Strategic facility plans
| | | |
Which activity is set by policy at the start of a project? - The correct answer is:
| | | | | | | | | | | | | | | |
Estimating
|
What should a facility manager do at the beginning of a routine project to
| | | | | | | | | | | | |
achieve success? - The correct answer is: generate a shared understanding of
| | | | | | | | | | | |
the end purpose of a project.
| | | | | |